What You Are Learning
By the end of this lesson you will be able to define a field and locate mismatch and name its five common forms: marks that are offset from the facility, a facility that was never marked, a marked facility that cannot be found, marks that have faded or been destroyed, and a ticket or positive response record that does not match what is on the ground. You will be able to state the response sequence that applies to every form: stop work in the affected area, do not guess and do not dig or drill on the marks alone, protect any facility that has been found, verify position only by safe exposure where you are qualified and authorized to do so, notify your supervisor, the 811 center, and the facility operator so corrected marks or a resolution can be issued, document the discrepancy in plain factual words, and resume work in that area only on corrected information or a revised plan. You will be able to explain how this lesson pulls together the earlier lessons in this level: mismarks from Lesson 67, unknown utilities from Lesson 68, utility conflicts from Lesson 69, strike prevention and strike response from Lesson 70, potholing from Lessons 65 and 66, positive response from Lesson 64, and the tolerance zone from Lesson 63. Finally, you will be able to state the boundary of this lesson clearly. It teaches recognition, stopping, protecting, notifying, and documenting. It does not qualify you to excavate, to pothole, or to locate facilities.
Start With the Basics
A locate is the process by which a facility operator, or a locator working for that operator, finds an underground facility and marks its approximate horizontal position on the surface with paint, flags, or stakes. The marks use the standard colors taught in Lesson 60, such as yellow for gas, red for electric, orange for communications, and blue for potable water. A facility is a pipe, cable, conduit, duct, or wire, above ground or underground, that delivers a service. An excavator is the person or company doing work that moves earth, including digging, trenching, boring, and drilling. Horizontal directional drilling, usually shortened to HDD, installs a new line by steering a drill head underground along a planned path.
Three facts about marks control everything in this lesson, and each one needs a definition before you build on it.
First, marks are approximate. Locating is not an exact science. A mark shows the locator’s best indication of where a facility runs on the surface. It does not guarantee that the facility sits directly under the paint, and it does not state depth. Operators are generally not required to provide depth information with their markings, and the depth of a facility can change over time because of erosion, later digging, and surface work. Treat every mark as a strong warning and a starting point for verification, not as a measurement.
Second, the tolerance zone is the area around a marked facility where state law and best practice require extra care and careful methods. Its width is set by state law and varies by state, so this lesson states no single width as a national rule. Verify the width that applies where you work. Inside the tolerance zone, the facility position must be confirmed by safe means before powered excavation or drilling relies on it.
Third, positive response is the system by which each facility operator tells the excavator, through the 811 process, that a facility has been marked, that the operator has no facility in the area, or that another stated status applies. Checking positive response lets the excavator confirm that every operator on the ticket has responded before digging starts. Paint on the ground by itself does not prove that every operator has responded, because one operator may have marked while another has not yet answered at all.
A mismatch is any case where what the field shows and what the locate information says do not agree. The field means the actual ground, the actual marks, and any facility actually found by safe observation or safe exposure. The locate information means the marks, the 811 ticket, the positive response record, and any locate sheet or job print the crew is working from. When those two sides disagree, the locate information has stopped being reliable in that area. The rest of this lesson is about what a careful worker does in that exact moment.
Hold one rule before you read further. A mismatch is not a problem to work around. It is a stop signal. The crew that treats it that way avoids the strike described in Lesson 70. The crew that guesses converts a paperwork and paint problem into a damaged facility.
What Is It?
A field and locate mismatch is a verified disagreement between the locate information and the physical evidence in the work area, discovered before or during excavation or drilling, that makes the planned work unsafe to continue in the affected area on the information currently in hand.
That definition has three parts worth pulling apart.
It is a disagreement, not a feeling. Examples include a facility exposed by careful work sitting clearly outside the line of its marks, a pipe or cable appearing in a trench wall where no mark and no ticket response placed anything, careful exposure inside a marked area finding no facility where one was marked, marks that can no longer be read, or a positive response entry that says marked when no marks exist or says clear when surface evidence such as a pedestal, a valve, a handhole, or a meter shows a facility is present.
It is discovered before or during work. A mismatch found during a prework walk is the cheapest kind, because no tool has entered the ground yet. A mismatch found at the digging face, with an opening already made, still counts in full. Discovery timing changes the cost. It does not change the response.
It makes the planned work unsafe to continue in the affected area on current information. That phrase matters. A mismatch in one crossing does not automatically shut down unrelated work in a separate area that does not depend on the disputed information, and only the supervisor process decides the scope of the stop. What it always does is stop the work that depends on the wrong information. You cannot bore through a crossing whose gas position is in dispute, and you cannot trench across a corridor whose marks have been destroyed, on the strength of memory or a photograph alone.
The industry practice for the core case is written down. Common Ground Alliance, usually shortened to CGA, Best Practice 5-21, Mismarked Facilities, states that the excavator notifies the facility owner or operator directly or through the 811 center if an underground facility is not found where one has been marked, or if an unmarked underground facility is found. Its description adds that when an excavator finds an unmarked or inaccurately marked facility, excavation stops in the vicinity of the facility and notification takes place. Following notification, the excavator may continue work only if the excavation can be performed without damaging the facility, unless state law says otherwise. Read the order carefully: stop in the vicinity first, notify second, and continue only under the condition the practice and state law allow. Guessing a new position and digging on it appears nowhere in that sequence.
Federal worker safety law points the same direction from a different angle. The OSHA excavation standard at 29 CFR 1926.651(b) requires that the estimated location of utility installations be determined before an excavation is opened, that utility owners be contacted and asked to establish the location before actual excavation starts, and that when excavation operations approach the estimated location, the exact location be determined by safe and acceptable means. It also requires that underground installations be protected and supported while an excavation is open. A mismatch is exactly the moment when the estimated location has been shown to be wrong, so the duty to determine the exact location by safe means, through the qualified parties and the operator process, is the duty that takes over.
A mismatch is different from three nearby ideas in this level, and keeping them separate helps you name what you found.
A mismark, from Lesson 67, is one form of mismatch: the marks themselves do not match the facility position the crew can verify. This lesson covers the mismark and every other form under one response.
An unknown utility, from Lesson 68, is a facility found that was not marked or not expected. Finding one creates a mismatch between the ground and the ticket, and this lesson’s response applies to it.
A utility conflict, from Lesson 69, is a case where a facility, marked correctly or not, sits where the new work needs to go, so the design and the existing plant cannot both occupy the planned space. A conflict can exist with perfect marks. A mismatch means the information itself is in dispute. Some jobs present both at once: the facility is not where it was marked, and once found, it also blocks the planned path. Name both, because the resolution needs corrected information and a revised plan, not one or the other.
What Does It Look Like?
A mismatch has five common forms. Learn to name the form out loud, because the name tells the supervisor, the 811 center, and the operator what kind of correction is needed.
Form one: marks offset from the facility. Careful exposure inside the tolerance zone finds the facility, but it sits to one side of its marks, outside the painted line the crew expected. Surface clues can point the same way before any digging: marks that jog around nothing visible, a line of paint that does not line up with the handholes, pedestals, or manholes the facility should connect, or a mark that ends at a structure and resumes on a line that does not fit the structure position. Offset marks are dangerous precisely because they look trustworthy. The paint is fresh, the color is right, and the position is wrong.
Form two: an unmarked facility. A pipe, cable, conduit, or duct appears in a trench wall, a bore pit, or a careful exposure, and no mark, no color, and no ticket response accounts for it. It may be an active facility an operator failed to mark, a private facility outside the 811 system, an abandoned facility whose status is not yet known, or a facility whose records were wrong. From the field, you cannot tell which one it is by looking, and this lesson does not ask you to. An unmarked facility is treated as active and as someone else’s property until the operator process establishes what it is. Lesson 68 covers this form in depth.
Form three: marked but nothing found. Careful exposure or careful checking inside the marked area, carried to the depth the planned work requires by qualified workers using the job’s approved methods, finds no facility where the marks and the positive response say one should be. Possibilities include a mark placed over the wrong alignment, a facility that sits deeper than the check reached, a facility removed in earlier work with the records never updated, or a signal from a different facility that the locator followed by mistake. None of those possibilities can be settled from the surface. Nothing found is a finding to report, not a clearance to dig freely, because the facility may still be present outside the checked spot or below the checked depth.
Form four: marks faded or destroyed. Paint has washed away, worn off under traffic, been mowed off, been covered by spoil or paving, or flags have been pulled, knocked down, or moved. The ticket may be fully valid and the positive response complete, but the information on the ground can no longer be read where the work is happening. CGA marking preservation practice addresses this form directly: the excavator protects and preserves marks until they are no longer required for safe excavation, and the excavator stops excavating and notifies the notification center for re-marks if any facility mark is removed or is no longer visible. A photograph of marks that no longer exist is useful evidence for the record. It is not a substitute for re-marks, and neither is a crew member’s memory of where the paint used to be.
Form five: ticket or positive response mismatch. The paper and the ground disagree. Positive response says an operator marked, but no marks for that operator can be found. Positive response says an operator is clear, with no facility in the area, but surface evidence shows that operator’s structures in the work area. An operator on the ticket has not responded at all by the planned start. The ticket describes a work area that does not match the area actually marked, or the ticket has expired while marks remain on the ground. State 811 guidance is consistent on the starting rule for this form: if a positive response is missing or incomplete, the excavator must take action before beginning excavation, by contacting the 811 center or submitting the additional notice or second notice the state system provides. Never assume a missing response means no facility is present.
Across all five forms, a few field signs should raise your attention before any tool confirms a mismatch. Marks in a color with no matching operator response. A facility corridor on the print with no marks at all. Fresh marks that stop at a property line, a pavement edge, or a fence for no stated reason. Two sets of marks in the same color that do not agree. A locate sheet or sketch that shows a facility the ground marks omit. Any one of these is a reason to stop and ask before the affected work starts, while asking still costs nothing.

What Does It Do?
A mismatch does four things to a job, whether the crew acknowledges it or not.
First, it removes the protection the marks were providing. The damage prevention system in this level works in layers: notice through 811, marks, positive response, careful methods in the tolerance zone, and exposure to verify. A mismatch means one of those layers has failed in that area. Continuing on the remaining layers alone, and especially continuing on the failed layer by trusting marks now known to be wrong, is how a crew drills through a line that was, on paper, marked.
Second, it transfers risk onto the crew and the public. While a mismatch is unresolved, every pass of a bucket or a drill head in the affected area is a guess about where gas, electric, water, sewer, and communications facilities actually sit. The consequences of a wrong guess are the ones Lesson 70 described: escaping gas, energized equipment, flooding and undermining, sewage contamination, and loss of communications that people use to call for help. A mismatch does not create those hazards by itself. Guessing after a mismatch is what creates them.
Third, it starts a correction process that only certain parties can complete. The crew can stop, protect, notify, and document. Only the operator or its locator can issue corrected marks, confirm that no facility exists, or clear a disputed response. Only the supervisor and, where the design is affected, the party who controls the plan can issue a revised plan for work that must move. A mismatch therefore pauses the affected work for as long as the correction takes. That pause is not a failure of the system. It is the system working, and it is far shorter and cheaper than a strike investigation and repair.
Fourth, handled well, it improves the information everyone works from next. A reported mismatch gives the operator the chance to fix marks and records. A documented discrepancy, tied to the ticket number and the exact location, becomes part of the job record and protects the next crew in the same corridor. Handled badly, by quietly shifting the dig line and saying nothing, it leaves wrong marks and wrong records in place for the next excavator, with your crew’s unrecorded knowledge buried with them.
Where Does It Fit?
This lesson is the capstone of Level 3 because it is where every earlier lesson in the level gets used at the same time, under field pressure.
It fits directly after Lessons 67, 68, and 69. Lesson 67 taught the mismark, Lesson 68 the unknown utility, and Lesson 69 the conflict. Each of those lessons taught its own case. This lesson teaches the shared response and the judgment to apply it when the case does not arrive neatly labeled, which is how mismatches actually arrive. A crew rarely knows at first sight whether it is looking at an offset mark, an unmarked private line, or a conflict that also involves a mismark. The response does not wait for perfect classification. Stop, protect, notify, and document come first. Naming the exact form can be refined as information arrives.
It fits on top of the verification tools from Lessons 63 through 66. The tolerance zone tells you where verification is required. Positive response tells you whether the locate process is actually complete. Potholing, also called daylighting or test holing, is the careful exposure of a facility at a specific point so its precise horizontal and vertical position can be measured at that point. In subsurface utility engineering, exposure and survey at a specific location is the highest accuracy form of utility information, often called Quality Level A under the ASCE 38 standard, because electronic locating alone cannot reliably establish depth. A mismatch is often discovered by one of those tools, and its resolution often uses potholing again, performed by qualified workers under the job plan, to establish where the facility truly is at the crossing that matters.
It fits immediately before Lesson 70 in consequence, even though it comes after it in number. Read together, the two lessons form one rule with two halves. Lesson 71 is what you do so that Lesson 70 never happens on your job: when the information fails, stop and fix the information. Lesson 70 is what you do when contact and damage have already occurred: stop, protect people, notify, and hand over to the operator and responders. If a mismatch response discovers that damage has already happened, for example an exposure shows a facility already nicked by earlier work, the Lesson 70 damage response takes over for that facility at once, in addition to the mismatch notifications.
It also fits forward into the rest of the Academy. Level 4 teaches what to do when a construction print does not match the field, which is the document version of this same discipline. Construction, verification, and documentation levels all assume the habit this lesson builds: when the record and the ground disagree, the ground is reported honestly, the record is corrected through the proper process, and work proceeds on corrected information, never on a quiet guess.
Why Does It Matter?
It matters because marks are the main protection most excavation relies on, and a mismatch is the moment that protection is known to be broken. Industry damage reporting collected through the CGA Damage Information Reporting Tool, usually shortened to DIRT, has repeatedly listed locator error, including facilities unmarked or inaccurately marked due to locator error, faded or unmaintained marks, and excavation without verification by potholing among the leading root causes of underground damage. You do not need any single year’s ranking to use that finding. The pattern is stable enough to act on: when marks are wrong, missing, or gone, damage follows unless the excavator stops and gets the information corrected.
It matters because the law assigns the excavator duties at exactly this moment. State damage prevention laws commonly require the excavator to notify the operator or the 811 center when a facility is not found where marked or when an unmarked facility is found, to protect and preserve marks, and to request re-marks when marks are no longer visible. Federal OSHA excavation rules require the exact location of an installation to be determined by safe and acceptable means as excavation approaches it. Exact duties, names of notices, and timelines vary by state. Verify the rule for the state where you work. What does not vary is the direction of every version: the excavator who discovers the disagreement is the person expected to raise it, not work through it silently.
It matters because the schedule argument runs the wrong way. Stopping one crossing for corrected marks costs time, and the wait depends on the state re-mark process and the operator response. A strike costs the repair, the outage, the investigation, and the project delay on top of that wait, and, in the worst cases, an injury that no schedule recovery can repay. A crew that stops early also keeps its credibility. An operator and a supervisor who see a crew stop, protect a found facility, and hand over clean facts will trust that crew’s next call. A crew known for digging through problems gets watched, rechecked, and eventually removed.
It matters because your report may be the only correction the record ever gets. Locators and operators cannot fix marks they do not know are wrong. Records cannot be updated from a discovery nobody reported. The unmarked facility you protect and report today becomes a marked facility for the next ticket. The offset mark you report today gets corrected before the next crew trusts it. Silence does the opposite, and it compounds: the next mismatch in the same corridor is more likely, not less, because the bad information survived.
What Does Good Look Like?
Good looks like a short, ordered sequence performed the same way every time, in a calm voice, without debate at the digging face about whether the mismatch is serious enough.
Step one: stop work in the affected area. The tool, the bucket, or the drill that was approaching the disputed area stops. Work that depends on the disputed information does not continue on memory, on a photograph, or on a verbal estimate of where the facility probably is. Work in a separate area that does not depend on the disputed information is a supervisor decision, made explicitly, not an assumption the crew makes on its own.
Step two: do not guess, and do not dig or drill on the marks alone. Nobody paints a corrected line from a guess, nobody shifts the bore path by a hopeful distance and proceeds, and nobody treats nothing found as proof that nothing is there. Inside the tolerance zone of a disputed mark, powered excavation and drilling wait until the position is verified or the operator resolves the dispute.
Step three: protect what was found. If a facility has been exposed or partly exposed, it stays protected and supported while the opening is open. OSHA 1926.651(b)(4) requires that underground installations be protected, supported or removed as necessary to safeguard employees while an excavation is open. Nobody uses the exposed facility as a step, a brace, or a tie off point. Nobody covers it back up to keep the job looking tidy before the discrepancy is resolved and the supervisor directs otherwise, because covering it destroys the evidence the operator and locator need. Keep people and equipment clear of an exposed facility whose type or status is unknown, and treat it as active until the operator establishes otherwise.
Step four: verify by safe exposure only where qualified. Where the job plan calls for verification, potholing by workers who are trained, equipped, and authorized for that work can establish the precise position of a facility at a specific point, so the corrected picture rests on measurement rather than opinion. Verification has limits a good crew respects. One exposure proves position at that point, not along the whole run, because a facility can curve, slope, or shift between exposures. Exposure is never expanded into exploratory powered digging to hunt for a missing facility. If verification is not within your qualifications or your authorization, your step four is to hold the stop and let the supervisor assign it to the party who is qualified. Recognizing that limit is part of doing this step well, not a failure to do it.
Step five: notify so corrected marks or a resolution can be issued. The supervisor is notified at once. The facility operator is notified directly or through the 811 center, following CGA Practice 5-21 for a facility not found where marked or an unmarked facility found. The 811 center is contacted for the correction the state system provides, which may be called a re-mark request, a second notice, an additional notice, a renotify, or a similar name depending on the state. Use the name and the form your state system uses, and verify it before you need it. For faded or destroyed marks, the request is for re-marks under the marking preservation practice. For a positive response dispute, the notice goes to the operator that has not responded or whose response conflicts with the ground. The point of every version is the same: the party who owns the information issues the correction, on the record, tied to the ticket.
Step six: document the discrepancy factually. A good record states the date and time, the ticket number, the exact location in a form someone else can find, the operator and facility type involved where known, the form of mismatch in plain words, what was actually observed, what safe exposure was or was not performed and by whom, photographs of the marks and the area taken before anything is disturbed further where that can be done safely, and who was notified and when. Write observed facts only. An offset is recorded as where the facility was found in relation to its marks, in measured terms where a measurement was actually taken. It is not recorded as a conclusion about why the locator marked it there or whose fault it is. Unknowns are written as unknown.
Step seven: resume only on corrected information or a revised plan. Work in the affected area restarts when corrected marks have been issued and checked against positive response, when the operator has confirmed in the state system’s form that no facility exists or that the found facility is identified and accounted for, when verification exposures ordered by the plan are complete, or when a revised plan moves the work clear of the disputed facility and the supervisor has approved that plan. A verbal assurance with no corrected mark, no updated response, and no revised plan is not a basis to resume. Neither is the passage of time. If corrected marks disagree with the ground a second time, the sequence starts again at step one.
Good also has a tone. The worker who finds the mismatch says what was found, plainly and promptly, including when the finder is the person whose earlier work relied on the bad marks. Good supervision treats a stop that follows this sequence as the correct action, and a crew that trusts that response will report the next mismatch earlier, while it is still cheap.
What Can Go Wrong?
The failures in a mismatch are predictable, because each one is a shortcut around a step in the sequence above.
The first failure is digging on the marks after the marks have been shown to be wrong. A crew exposes a gas line offset from its paint, notes the offset verbally, and then bores the next crossing on the same paint because the locator must have gotten that one right. Marks from the same locate, on the same ticket, in the same corridor, share the same reliability. One proven offset puts every related mark in question until the operator resolves it.
The second failure is guessing a corrected position. A locator is not the only person who can be wrong about an underground line. A crew member who paints a new line where the facility is believed to run, and digs on it, has replaced one unverified position with another and added false confidence to it. Corrected marks are issued by the operator or its locator through the ticket process. Crew estimates are reported as observations for that process to use. They are never dug on as if they were marks.
The third failure is treating nothing found as nothing there. A shallow check that finds no facility can miss a deeper facility, a facility offset outside the checked opening, or a facility made of a material the check method does not detect well. The correct report is narrow and exact: no facility was found in the stated opening, by the stated method, to the stated extent actually checked. The operator decides, from that report and its records, whether to re-mark, to direct further verification, or to confirm no facility. The crew does not upgrade its own narrow check into an all clear.
The fourth failure is hunting with powered equipment. Faced with a marked facility that cannot be found, a crew widens the search with a bucket or advances a bore to see what it meets. That converts verification into the exact uncontrolled excavation the tolerance zone rules exist to prevent, and it is the most direct route from a mismatch to a strike. Verification is by safe and acceptable means, performed by qualified workers under a plan. A bucket search is none of those things.
The fifth failure is destroying the evidence. Backfilling an exposed unmarked facility before it is identified, repainting faded marks from memory, moving flags back to where someone thinks they stood, or clearing the area so thoroughly that the locator cannot see what the crew saw, all force the correction process to start from nothing. Protect the found facility, leave the opening and the remaining marks as found, and let your photographs and notes carry the detail.
The sixth failure is notifying nobody outside the crew. Telling only the foreman, or only the worker on the next shift, leaves the operator working from records that still say the original marks were right, leaves the ticket and positive response unchanged for anyone who checks them, and leaves the next excavator in the corridor unprotected. The mismatch is not resolved until the operator or the 811 process has it. Internal notice is step five’s beginning, not its completion.
The seventh failure is a record that argues instead of reporting. A note that says the locator did a bad job, that the marks were useless, or that the facility was way off, with no ticket number, no location a stranger could find, no statement of what was actually observed, and no notification times, helps nobody correct anything and weakens the crew if the event is later reviewed. Facts travel. Opinions stall. Write the facts while they are fresh, including the uncomfortable ones, such as the time work continued before the stop was called, if that happened.
The eighth failure is resuming on pressure. A corrected mark is promised for tomorrow, the bore is behind, and someone proposes starting the undisputed end of the crossing today on the old information. If the work depends on the disputed position, it waits. If a genuinely independent portion of work exists, the supervisor defines it explicitly, in the record, so the boundary of the stop is clear to every shift. Vague partial resumption is how a stopped crossing gets drilled by a crew that thought the stop had been lifted.
What Should Someone Notice in the Field?
Notice the agreement, or the lack of it, among four things that should all tell the same story: the marks on the ground, the ticket and positive response record, the visible surface evidence, and the facility actually found by safe observation or safe exposure. A mismatch is present whenever any one of the four disagrees with the others in the area where you are about to work.
Notice marks against structures. A communications mark that never approaches the pedestals or handholes it should connect, a water mark that does not pass the valve or meter it should serve, a gas mark that does not fit the meter or regulator position at the building, or any mark that ends in open ground with no structure and no continuing flag line. Structures are hard evidence. Paint that ignores them deserves a question before a bucket, not after.
Notice marks against the ticket. Walk the area with the positive response in hand. For each operator listed as marked, can you find that operator’s color, with flags or paint that are still legible? For each operator listed as clear, is the surface truly free of that operator’s structures? Is any operator still without a response? Is the ticket still within its valid life under your state rules, and does the ticket work area match the ground you are standing on? Any no in that list is a mismatch to raise before the affected work, not a detail to sort out from the trench.
Notice the condition of the marks themselves. Paint broken by tire tracks, faded to a shadow, half covered by spoil, gravel, or new pavement, or flags leaning, scattered, or missing in the middle of a run. Ask the marking preservation question directly: can the operator of the tool, from the tool position, still read the marks that protect this dig? If not, the marks have failed in the only way that matters, whatever the ticket says, and re-marks are the next step.
Notice what careful work reveals, and stop at the first revelation. Soil that changes to trench backfill, bedding material, or warning tape where no facility was marked is evidence of a buried line or structure, even before the facility itself appears. Warning tape is a marker placed above a buried facility to warn excavators approaching it. Finding tape, conduit, duct, or a pipe or cable of any material or color in an unmarked position is a stop and protect moment under Lesson 68 and under this lesson. Do not pull, cut, move, or test the found object to identify it. Identification belongs to the operator process. Your job is to protect it, describe it plainly by material, color, size as observed, direction, and location, and notify.
Notice depth surprises without inventing depth rules. A facility found far shallower or deeper than the crew expected is a mismatch in the vertical sense, even when the marks are horizontally sound, because marks do not state depth and plans that assumed a depth are now unreliable at that crossing. Report the measured depth only where a qualified worker actually measured it during an authorized exposure, and report it as a measurement at that point, not as the depth of the whole run.
Notice your own limit, and notice it early. Recognizing a disagreement, stopping the affected work, protecting a found facility from the surface, notifying, and writing a factual record are within every worker’s role. Locating, re-marking, potholing, and declaring a facility identified, abandoned, or safe to work past belong to locators, operators, and qualified excavation workers acting under the job plan and state law. If you are handed one of those tasks because you read this lesson, say so and route it to the qualified party. That sentence is part of the skill this level teaches, not an excuse from it.
Practical Example
The following examples are hypothetical. They are invented to teach the response, not to describe real jobs or real companies.
Hypothetical example one: offset gas marks at a bore crossing, resolved by correction. A hypothetical fiber crew is preparing a small bore across a hypothetical residential street. A yellow marked gas line crosses the planned path, and positive response shows the gas operator as marked. Before drilling, the job plan requires the gas facility to be exposed at the crossing so the bore can be set from a verified position. A qualified worker on the crew, using the careful methods the plan and state law require inside the tolerance zone, exposes the gas pipe and finds it clearly to one side of the yellow paint line, still inside the tolerance zone but not where the paint placed it. The crew leader, Marcus, stops all work at that crossing. Nobody adjusts the bore path by eye and proceeds. The exposed pipe is protected and left open. Marcus notifies the supervisor at once and records the facts: the ticket number, the crossing location, the exposure point, and the measured offset as actually measured at that point, with photographs of the paint and the exposed pipe in the same frame where that can be done safely. The supervisor notifies the gas operator through the 811 center process for a mismark, and the operator’s locator issues corrected marks and updates the response. The crew checks the corrected marks against the exposed pipe, finds them in agreement, and the supervisor approves a revised bore plan set from the verified position, with clearance maintained as the plan requires. Only then does the bore at that crossing proceed. The lesson is the sequence: the exposure did its job by finding the truth, the stop protected that truth from being wasted, and the correction came from the operator, not from the crew’s estimate.
Hypothetical example two: marked but nothing found, plus marks destroyed, on the same morning. A hypothetical trench crew opens a hypothetical job where an orange marked communications line is shown crossing the trench path, and a blue marked water line runs along the same corridor. Overnight rain has washed the blue marks to faint shadows along half the corridor, and mowing has scattered the blue flags. Separately, careful checking for the orange facility at the crossing, by the qualified workers and methods the plan specifies, finds no conduit or cable in the area checked. The crew leader, Priya, treats the morning as two mismatches, not as a rough start to work through. Trenching in the affected corridor stops. Priya notifies the supervisor, who contacts the 811 center for blue re-marks because the marks are no longer visible while work continues around that facility, following the marking preservation practice, and separately notifies the communications operator directly and through the 811 center that the marked facility was not found where marked, following CGA Practice 5-21. Priya’s record separates the two reports: for water, marks no longer legible from a stated point to a stated point, photographs attached; for communications, no facility found in the stated checked area by the stated method, extent of the check described exactly, no conclusion drawn about where the facility is. The water locator re-marks. The communications operator reviews its records, directs a further verification step at a second point under its process, and the facility is located offset from the original mark near that second point and re-marked. The supervisor then releases the corridor in writing on the corrected marks. The trench proceeds two days later than the first plan and crosses both facilities without contact. The lesson is that nothing found and marks destroyed are both reportable findings with their own correction routes, and neither one is permission to proceed on the information that failed.
Key Terms
Mismatch: any disagreement between the locate information, meaning the marks, the 811 ticket, and the positive response record, and the physical evidence in the field, that makes planned work unsafe to continue in the affected area on the information currently in hand.
Locate: the process by which a facility operator or its locator finds an underground facility and marks its approximate horizontal position on the surface with paint, flags, or stakes in the standard colors.
Mismark: a mark that does not match the facility position the crew can verify, including a mark offset from the facility. One form of mismatch.
Positive response: the system by which facility operators tell the excavator, through the 811 process, that a facility has been marked, that the operator has no facility in the area, or that another stated status applies, so the excavator can confirm every operator has responded before digging.
Tolerance zone: the area around a marked facility where state law and best practice require careful methods and extra care. Its width is set by state law and varies by state.
Potholing: carefully exposing a buried facility at a specific point by safe excavation practices to verify its precise horizontal and vertical position at that point. Also called daylighting or test holing.
Operator: the facility owner or operator, the company, utility, municipality, or other owner responsible for a facility, for its marks through its locator, and for issuing corrected marks or confirming that no facility exists.
Re-mark: a fresh marking of a facility issued through the 811 process when original marks have faded, been destroyed, or been corrected. Names for the request vary by state and include second notice, additional notice, and renotify in different state systems.
Unknown utility: a facility found in the field that was not marked or not expected on the ticket. It is treated as active until the operator process establishes what it is.
Utility conflict: a case where an existing facility sits where new work needs to go, so the facility and the planned work cannot both occupy the planned space. A conflict can exist with correct marks and is different from a mismatch, where the information itself is in dispute.
Warning tape: a tape placed in the ground above a buried facility to warn an excavator approaching from the surface that a facility lies below. Finding it where no facility was marked is evidence of a buried line.
Affected area: the portion of the work whose safety depends on the disputed information. A mismatch stops work in the affected area. Work outside it continues only by explicit supervisor decision.
Check Your Understanding
- Name the five common forms of a field and locate mismatch, and give the first action that applies to all five.
- Under CGA Best Practice 5-21, whom does the excavator notify when a facility is not found where one was marked, or when an unmarked facility is found, and what happens to excavation in the vicinity of the facility while that notification takes place?
- A crew exposes a marked facility and finds it offset from its paint. A crew member offers to paint a corrected line where the facility was found and bore the next crossing on it. What is wrong with that plan, and what is the correct route to corrected marks?
- Careful checking inside a marked area finds no facility. Why is that finding not an all clear, and how should it be reported?
- Rain and traffic have destroyed the marks along a corridor, but the ticket is still valid and a crew member has clear photographs of the original marks. Can trenching continue on the photographs? State the rule and the correct next step.
Answer key:
- The five forms are marks offset from the facility, an unmarked facility that is found, a marked facility that cannot be found, marks faded or destroyed, and a ticket or positive response record that does not match the ground. The first action for all five is the same: stop work in the affected area. Notification, protection, and any qualified verification follow from that stop. No form is worked through on a guess.
- The excavator notifies the facility owner or operator directly or through the 811 center. Excavation stops in the vicinity of the facility while notification takes place. After notification, work may continue only if the excavation can be performed without damaging the facility, unless state law provides otherwise, and in this lesson’s sequence, resumption in the affected area rests on corrected information or a revised plan approved through the supervisor process.
- A crew estimate is not a mark. Painting and digging on a guessed corrected line replaces one unverified position with another and adds false confidence, and marks from the same locate share the same reliability, so one proven offset puts related marks in question. Corrected marks are issued by the operator or its locator through the 811 process after the supervisor and operator are notified of the measured discrepancy. The crew’s measured observation is valuable input to that process. It is never a substitute for it.
- Nothing found proves only that no facility was found in the area actually checked, by the method actually used, to the extent actually reached. The facility may sit deeper, offset outside the checked opening, or in a form the method does not detect well. The finding is reported narrowly and exactly, with the checked area, method, and extent stated and no conclusion drawn about where the facility is. The operator decides whether to re-mark, direct further verification, or confirm that no facility exists.
- No. Photographs are evidence for the record. They are not a substitute for marks on the ground. Under CGA marking preservation practice, the excavator protects and preserves marks until they are no longer required for safe excavation, and stops excavating and notifies the notification center for re-marks if any facility mark is removed or is no longer visible while work continues around the facility. The correct next step is to stop in the affected corridor, notify the supervisor and the 811 center, and resume on re-marks that have been issued and checked.
Lesson Takeaway
When the field does not match the locate, the locate has stopped protecting you in that area, and the response is always the same sequence: stop work in the affected area, do not guess and do not dig or drill on the marks alone, protect any facility that was found, verify position only by safe exposure where you are qualified and authorized, notify your supervisor, the 811 center, and the operator so corrected marks or a resolution can be issued, document the discrepancy in plain facts, and resume only on corrected information or a revised plan. Offset marks, an unmarked facility, a marked facility that cannot be found, marks faded or destroyed, and a ticket or positive response record that disagrees with the ground are five forms of one event, and none of them is permission to proceed. This lesson qualifies you to recognize a mismatch and run the protective response. It does not qualify you to excavate, to pothole, or to locate facilities.
Sources and Technical References
- Common Ground Alliance Best Practices, Practice 5-21, Mismarked Facilities: the excavator notifies the facility owner or operator directly or through the 811 center if an underground facility is not found where one has been marked or if an unmarked facility is found; when an excavator finds an unmarked or inaccurately marked facility, excavation stops in the vicinity of the facility and notification takes place; following notification, the excavator may continue work only if the excavation can be performed without damaging the facility, unless state law provides otherwise: https://www.pa1call.org/resourcelibrary/resource/download?id=260
- Common Ground Alliance Best Practices 17.0, Practices 5-20 and 5-21 and 5-17: Practice 5-20 requires reasonable care and safe excavation practices inside the tolerance zone, including hand digging or potholing among the methods states recognize; Practice 5-17, Marking Preservation, states that the excavator protects and preserves marking until no longer required for safe excavation and stops excavating and notifies the one call center for re-marks if any facility mark is removed or is no longer visible: https://nebraska811.com/wp-content/uploads/2020/06/CGA_BestPracticesV17.pdf
- OSHA excavation standard, 29 CFR 1926.651(b): the estimated location of utility installations must be determined before opening an excavation, utility owners must be contacted and asked to establish the location before actual excavation starts, the exact location must be determined by safe and acceptable means when excavation approaches the estimated location, and underground installations must be protected, supported, or removed as necessary while an excavation is open. Text via Cornell Law: https://www.law.cornell.edu/cfr/text/29/1926.651
- Tennessee 811, Before You Dig: after responses are received, compare the ticket response codes to the marks at the dig site, and if they do not match, contact 811 to have a second notice sent to that member; locating is not an exact science and the actual location of a facility can vary from the position of the marks; utilities are not required to provide depth information with their markings, and depth can vary over time: https://www.tenn811.com/before-you-dig
- Indiana 811, Professional FAQs: if a positive response is missing or incomplete, the excavator must take action before beginning excavation, by submitting an additional notice online where permitted or by contacting Indiana 811; the same action applies when positive response shows marked but no paint or flags are visible, and where markings have become illegible due to weather or excavation a new locate request is required in that state system: https://indiana811.org/pros/faqs-pros/
- South Carolina 811, FAQs and excavator checklist: excavators are required to check positive response to determine whether all facility operators have responded before beginning excavation, even when marks are already present; contact 811 to request a resend if a utility has responded as marked and the markings appear incomplete, inaccurate, or not visible; walk the site and document marks with photographs before digging: https://sc811.com/faqs/
- Blue Stakes of Utah 811, FAQ on faded or destroyed markings: it is the excavator’s responsibility to respect and protect the markings; if markings have faded or been destroyed by weather, traffic, or excavation, the excavator contacts the notification center and requests that the area be marked again; a re-mark notice in that state does not extend the legal life of the locate request: https://www.bluestakes.org/faqs/
- Texas 811, FAQ: pipeline markers indicate the general location of pipelines, not their exact location, and must not be used alone as the indication of an underground utility location; if a line is damaged, stop digging and notify Texas 811 immediately for the damage ticket process used in that state, and call 911 for a gas pipeline: https://texas811.org/faq/
- Subsurface utility engineering quality levels under ASCE 38, summarized by BSI Engineering: Quality Level A information comes from exposure and survey of the utility at each specific location where that quality of data is obtained; exposure is by non-intrusive methods such as hand excavation or typically vacuum excavation, because depth cannot be reliably determined electronically: https://www.bsieng.com/faq
Flagged and hedged items: No tolerance zone width is stated as a national rule in this lesson, because the width is set by state law and published state guidance differs between states; verify the width, the ticket life, and the exact names and timelines for re-mark, second notice, additional notice, and renotify requests in the state where you work, because each state 811 system uses its own terms and forms for the same correction routes. No depth, clearance, offset distance, or verification depth is stated as a requirement in this lesson, because marks do not state depth, depth varies over time, and any clearance or verification requirement for a specific crossing comes from state law, the operator, the contract, or the job plan for that crossing. Quality Level A is described only in its general ASCE 38 sense, as exposure and survey at a specific location; this lesson does not teach the ASCE 38 standard, subsurface utility engineering practice, or any locating or exposure method. Statements about DIRT root causes are stated as a recurring pattern in CGA reporting rather than as a ranking or percentage for any single year, because rankings and figures change between annual reports; verify the current DIRT report if a specific figure is needed. Whether work outside an affected area may continue during a mismatch stop is stated as an explicit supervisor decision, because no source reviewed for this lesson sets a single national rule for the scope of a stop beyond the vicinity of the facility in CGA Practice 5-21.