Lesson 69: What Is a Utility Conflict?

What You Are Learning

By the end of this lesson you will be able to explain, in plain language, what a utility conflict is and what it is not. You will be able to tell the difference between a true conflict, where new work cannot be built as designed because an existing utility is in the way or would be put at risk, and a near miss, where new work and an existing utility are close together but fit with verified separation. You will be able to describe how conflicts are found: review of records, field verification, subsurface utility engineering at stated quality levels, test holes at critical points, and conflict analysis during design. You will be able to read a conflict matrix or conflict list, the working document designers use to track each conflict, the quality of the data behind it, and the status of its resolution. You will be able to name the main resolution paths: adjust the proposed design, relocate the existing utility, protect or support the existing utility in place, change the construction method, or phase the work. Finally, you will be able to state who decides how a conflict is resolved, and what a field crew is supposed to do when it discovers a conflict that nobody recorded.

This lesson teaches recognition and reading. It does not qualify you to decide how a conflict is resolved, to redesign proposed work, to direct a utility owner to move its facility, or to improvise a workaround in the field. Conflict decisions belong to the designer or engineer, the facility owner, and the project owner, working through the project process. Your job as a reader of this lesson is to recognize a conflict, understand the paperwork that tracks it, and know why a discovered conflict is reported rather than fixed on the spot.

Start With the Basics

Start with ground that is already occupied. In earlier lessons you learned that an existing utility is a facility that is already in place when new work arrives: a pipe, cable, conduit, duct, wire, pole, vault, or structure that delivers a service such as electric power, gas, water, sewer, or communications. You also learned that buried facilities are out of sight, that records can be wrong, that locate marks show an approximate horizontal position, and that a test hole, also called a pothole or daylighting, exposes a facility at one point so its precise horizontal and vertical position can be measured. That work is covered in Lesson 65.

Now put a second facility into the same ground. A proposed facility is the new facility shown on the design: for fiber work, usually new conduit, new fiber cable, a new handhole or vault, a new pole, or a new bore path. The design also proposes more than the facility itself. It proposes a grade, which is the planned elevation of the ground surface or of a structure, and it proposes a work method, which is how the new facility will be installed, such as open trenching, boring, plowing, or excavation for a structure foundation.

A conflict starts with a simple question of space. Can the proposed facility, at its designed position and depth, with its designed structure, grade change, and work method, be built while the existing facility stays where it is, unharmed and still able to do its job? If the honest answer is no, there is a conflict. If the answer is yes, but only just, and the space between the two facilities has actually been verified, there may be no conflict at all. That second case has a name in this lesson: a near miss that fits.

Before going further, define the working words.

Separation is the distance between two facilities, measured horizontally, vertically, or both, depending on how the requirement for that situation is written. Clearance is closely related. In this lesson, clearance means the required empty space that must be kept around or between facilities or structures so they can be built, operated, and maintained without interference. The exact words and the exact numbers come from the governing requirement for the job, not from this lesson.

A governing requirement is the rule that actually controls a specific situation. It may be a code, a facility owner standard, a permit condition, or a project specification. Those sources are not interchangeable, and the next sections return to that point more than once, because treating a number from one job as a rule for the next job is one of the most common ways conflicts are misjudged.

Utility coordination is the organized communication among the project owner, the designer, and the utility owners during design and construction, so that existing facilities are identified, conflicts are found early, and resolutions are agreed before work reaches the ground. A utility coordinator is the person or role assigned to run that communication on a project.

Subsurface utility engineering, usually shortened to SUE, is the engineering practice introduced in Lesson 65 for gathering and depicting existing utility data at stated quality levels. It matters here because conflict decisions are only as good as the data behind them, and SUE is how designers label how good that data is.

What Is It?

A utility conflict is a situation in which a proposed new facility, structure, grade change, or work method cannot be built as designed because an existing utility is in the way, is too close under the governing separation or clearance requirement for that situation, or would be put at risk by the work.

Read that definition in three parts, because each part describes a different kind of conflict.

The first part is a direct physical conflict. The proposed facility and the existing facility want the same space. A new handhole is designed where an existing water main already runs. A new conduit bore path crosses an existing sewer at the same elevation. A foundation excavation removes the ground a gas line sits in. There is no version of the design as drawn in which both facilities occupy that space, so something in the plan has to change.

The second part is a clearance conflict. The two facilities do not touch, but the space between them is less than the governing requirement allows for that situation. Neither facility is damaged by the drawing alone. The problem is that the required separation exists for reasons such as safe construction, future maintenance access, heat, electrical safety, or protection of a pressurized or gravity line, and the design does not provide it. A clearance conflict is still a conflict, even though nothing overlaps on the plan. The requirement is part of the design, not an optional extra.

The third part is a risk conflict. The proposed facility itself might fit, but the work method or the construction activity would endanger the existing facility. Examples include excavation that would undermine an existing line and leave it unsupported, heavy equipment working directly over a shallow facility, a bore path that passes close enough that the drilling and reaming process could damage the existing line, and grading that would remove cover over an existing facility or bury it deeper than its owner allows. The facility does not move and the new line does not touch it, yet the work as planned puts it at risk. That counts.

A utility conflict is not the same thing as a utility strike. A strike, covered in Lesson 70, is physical contact or damage during work. A conflict is a problem identified in the relationship between a design, a work plan, and an existing facility. Conflicts are best found on paper and in verified field data, before any equipment moves. A conflict found in design costs discussion and redesign. The same conflict found by a drill head costs damage, delay, and possibly injury.

A utility conflict is also not the same thing as a mismark or an unknown utility, although those problems can create one. Lesson 67 covers what to do when a utility is mismarked, meaning the marks do not match the actual facility. Lesson 68 covers what to do when an unknown utility is found in the field. A conflict can hide behind both problems: a design that fits the marks perfectly can still conflict with the real facility if the marks were wrong, and a facility nobody knew about can turn a clean design into a conflict the moment it is uncovered.

Finally, a conflict is not a feeling and not a guess. It is a conclusion drawn from two sets of facts compared against each other: where the existing facility actually is, at a stated level of data quality, and what the proposed design actually requires, including its structures, grades, and methods. When the first set of facts is weak, the honest status is not conflict or no conflict. The honest status is potential conflict, needs more information. Good conflict work says that plainly instead of guessing in either direction.

What Does It Look Like?

A utility conflict has two looks: a physical look in the ground and on the plan, and a paperwork look in the documents that track it. Learn both.

The physical look starts on a plan view, which is the view from directly above. Two lines cross, or two lines run close and parallel, or a proposed structure symbol sits on top of or beside an existing line. On a cross section, which is a side view cut through the ground, the physical look is clearer still: the proposed conduit, structure, or excavation outline and the existing pipe or duct occupy the same elevation band, or sit closer together than the governing requirement allows. For a fiber bore, the cross section may show the planned bore path, including the larger hole created when the bore is reamed to pull in the product, passing through or grazing the space an existing facility occupies. The bore itself is not the only width that matters. The work around it matters too.

In the ground, the physical look is two facilities competing for the same space at a crossing, along a parallel run, or at a structure location. You cannot usually see both facilities at once, because the proposed one is not built yet. What you can see is the existing facility exposed in a test hole, the white lining or marks showing where the new work is planned, and the measurement between them. When those two things are placed side by side, the conflict stops being abstract. Either the new work fits with verified space to spare, or it does not.

The paperwork look is just as recognizable. On a design plan, a conflict is often marked with a callout, a note, or a conflict number tied to the crossing or location, so a reader can connect the spot on the drawing to a record somewhere else. In the project file, the conflict appears as a row in a conflict list or conflict matrix. That row names the existing utility and its owner, describes the location, states what proposed feature it conflicts with, records the quality level of the data behind the location, lists the resolution being considered or chosen, and shows a status such as identified, under review, resolved by design, resolved by relocation, or closed. A conflict that exists only as a conversation, with no row and no plan note, is a conflict that can be forgotten. The paperwork is how a project remembers.

In the field, the paperwork look shows up as an absence or a warning. A crossing that the plan flags as a conflict should reach the crew with instructions: expose first, hold at this point, use a stated method, or wait for a relocation that must happen before construction. If the plan shows a crossing with an existing facility and says nothing at all about it, that silence is itself worth a question, because it may mean the conflict was never analyzed rather than that it was analyzed and cleared.

Whiteboard illustration: what a utility conflict is

What Does It Do?

Strictly speaking, a conflict does nothing. It is not a tool or a process. This section answers a different question: what does identifying and managing a conflict do for a project? The answer is that conflict work converts a buried surprise into a planned decision.

First, it forces the comparison early. Conflict analysis is the design step in which depicted existing utilities are compared, feature by feature, against the proposed plans, including the proposed facility alignment, structures, drainage, grading, and construction phasing. The Federal Highway Administration, usually shortened to FHWA, describes conflict analysis in its SUE brochure as the engineering process of using a conflict matrix to evaluate and compare depicted designating information with proposed plans in order to inform all stakeholders of potential conflicts, potential resolutions, and costs to cure. That comparison is the moment a project stops assuming the corridor is empty and starts proving where it is not.

Second, it ranks risk by data quality. A crossing shown from record drawings alone carries more uncertainty than a crossing verified by a test hole. Conflict management uses that difference openly. Where the data is weak and the consequence of being wrong is high, the next step is usually more information, not a decision. Where the data is strong, the team can decide and move on.

Third, it gives every conflict an owner, a path, and a status. Without that tracking, each party can assume someone else is handling the crossing at the far end of the job. With it, the project can answer basic questions at any time: how many conflicts are open, which ones block construction, which utility owner has not responded, and which resolutions depend on long lead work such as a relocation design.

Fourth, it protects the schedule by moving hard conversations to the cheapest time to have them. FHWA and the second Strategic Highway Research Program, usually shortened to SHRP2, identify two recurring causes of utility problems in project delivery: inadequate information about the location and attributes of existing facilities, and the lack of an effective process to manage conflicts between those facilities and project features. Conflict management answers both causes at once. It improves the information and it supplies the process.

Fifth, it protects the existing facility and the people around it. A resolved conflict means a gas line, an electric duct bank, a water main, or a sewer is either avoided, moved by its owner, protected under an approved plan, or crossed by a method chosen with its actual position in mind. The benefit is not paperwork. The benefit is that a working facility keeps working and nobody has to manage an emergency that design could have prevented.

Where Does It Fit?

Conflict work fits inside design first, and inside construction second. The earlier it happens, the more options remain open and the cheaper those options are.

In project planning and early design, conflict work starts with records review. The designer gathers utility records, as built drawings, owner maps, and prior project files, and depicts the existing utilities on the base plan. In SUE quality level terms from ASCE 38, this is Quality Level D information, meaning information derived from existing records or oral recollections. Designers also walk the site and correlate visible surface features such as manholes, valve boxes, pedestals, and poles with those records, which produces Quality Level C information. At this stage, conflicts are labeled potential, because the data is not yet strong enough to prove them.

In preliminary design, surface geophysical methods are applied to designate the horizontal position of buried utilities. That designated and surveyed information is Quality Level B. The proposed alignment is laid over it, and the first real conflict list is built. Designers can often resolve early conflicts cheaply at this stage by shifting the proposed alignment, moving a structure, or adjusting a grade, because nothing has been finalized and no owner has started relocation design.

In final design, test holes are opened at critical points where the design and an existing utility appear to conflict or come close. Lesson 65 explains the method: minimally intrusive excavation, usually vacuum excavation, exposes the facility so its precise horizontal and vertical position can be measured and surveyed. That is Quality Level A information. The conflict matrix is then updated with the verified positions. Some suspected conflicts disappear at this stage, because verified separation is adequate. Some are confirmed. FHWA SUE practice describes exactly this loop: expose selected utilities, depict the Quality Level A results, resolve differences with the earlier quality level information, and return to the conflict matrix to determine the status of the conflicts that needed more information.

In construction, conflict work fits in two places. The first is verification: the crew confirms in the field that conditions match the resolved design, exposes facilities at crossings as the plan requires, and works by the method the resolution assumed. The second is discovery: when field conditions do not match the plan, because a facility is mismarked, unknown, or in a different position than depicted, the crew stops in that area and reports through the project process, as Lessons 67 and 68 teach. A construction discovery reopens the conflict process. It does not replace it.

Conflict work also fits inside utility coordination meetings, where the project owner, designer, and utility owners review the conflict list together, test proposed resolutions, and agree who does what and by when. FHWA SUE practice includes convening the utility owners to discuss potential conflicts and strategies to avoid them, and to identify where additional three dimensional information is needed. The conflict matrix is the shared document those meetings work from.

For fiber construction specifically, conflict work fits at every bore crossing, every proposed handhole and vault location, every pole setting or replacement, every trench line that parallels an existing corridor, and every place where grading, access, or restoration changes the ground over an existing facility. Fiber routes are usually new guests in corridors that are already full. Conflict analysis is how a fiber designer finds out whether there is actually room for one more guest.

Why Does It Matter?

It matters because space underground is finite and already claimed. The corridor under a street or along a road shoulder may hold water, sewer, storm drainage, gas, electric, and several generations of communications lines, installed over decades by different owners with different record keeping. A new design that ignores that reality does not make the corridor emptier. It only makes the collision later.

It matters because the same conflict costs radically different amounts depending on when it is found. Found in records review, it costs a designer an hour. Found after Quality Level B designating, it may cost an alignment shift. Found after a test hole in final design, it may cost a structure move or a planned relocation with time to schedule it. Found during construction, it costs standby time, redesign under pressure, possible damage, and sometimes a claim. Found by contact with the facility, it becomes a strike, with consequences that can include outage, flooding, fire, explosion, electrocution, and loss of emergency service, depending on the facility involved.

It matters because relocations are slow and are not the project crew’s to perform. A relocation is designed and built by or for the utility owner, under the owner’s standards, and it can require its own design, permits, materials, outages, and scheduling windows. A project that discovers late that a major facility must move has not just found a construction problem. It has found a schedule problem measured in weeks or months. Early conflict analysis is what gives a necessary relocation time to happen before construction reaches it.

It matters because designing around a utility is often possible, but only early. FHWA published guidance on avoiding utility relocations makes the point directly: every effort must be made to design around as many utilities as possible, good communication between the highway agency and utilities early in project development can produce minor plan changes that avoid costly and time consuming relocations, and SUE information is what lets designers make those changes with confidence. A small horizontal shift of a bore path, a moved handhole, or a modest vertical adjustment can retire a conflict entirely. Those moves are easy on paper and hard or impossible after conduit is in the ground.

It matters for responsibility. The conflict list is a record of what the project knew, when it knew it, and what it decided. A project that documented a conflict, verified the data, chose a resolution through the proper parties, and built to that resolution can show its work. A project that proceeded on a known, undocumented conflict, or on data it knew was weak, has a much harder story to tell after something goes wrong. This lesson does not give legal advice. It teaches the habit those records are built on: find conflicts with the best data available, write them down, and resolve them through the parties who own the decision.

Finally, it matters because today’s new fiber becomes tomorrow’s existing utility. Every conflict resolved cleanly, with the new facility placed where the record says it is, makes the next project’s conflict analysis in that corridor more truthful. Sloppy placement and sloppy records do not just risk this job. They manufacture conflicts for the next one.

What Does Good Look Like?

Good conflict work is early, written, verified at the points that matter, and resolved by the right parties. You can recognize it from its habits.

It starts early. Existing utilities are depicted on the plan from the beginning of design, not added after the proposed alignment is fixed. Utility owners are notified and asked to verify their facilities on the preliminary plans while changes are still cheap. The first conflict list exists before final design, and it is treated as a living document that is updated as data improves.

The data quality behind each conflict is stated honestly. Each depicted utility carries its quality level, and each conflict row reflects what that quality level can and cannot support. A potential conflict based on Quality Level D records is not written up as a confirmed conflict, and it is not written off as no conflict either. It is carried as potential until better data settles it.

Critical points are verified in the ground. Where the design and an existing utility appear to conflict or come close, and the answer changes the design, test holes provide Quality Level A positions before the decision is made. FHWA SUE practice describes selecting test hole locations at critical points, exposing the utility with nondestructive methods, surveying the result to project control, and resolving discrepancies with the information already on the plans. Good projects can point to the test hole record behind every close call they cleared.

The resolution follows a sensible order of preference. Utility conflict management guidance describes the goals in this order: first avoid the conflict by designing around the utility where the project can do so without compromising its purpose, then minimize the impact where avoidance is not possible, and then mitigate, which can include relocating the utility. Avoidance is preferred not because relocation is wrong, but because a design adjustment is usually faster, cheaper, and less disruptive than moving a working facility. The chosen resolution for each conflict is recorded, along with who is responsible for it and what it depends on.

Every party can see the same list. The conflict matrix or list is shared among the project owner, the designer, and the utility owners, and it is reviewed in coordination meetings rather than kept in one person’s inbox. Kentucky transportation practice, summarized from utility conflict management training built on the SHRP2 work, shows the common pattern: the matrix identifies, organizes, analyzes, tracks, manages, and mitigates conflicts, recording the utility location, type, and ownership, the identification of potential conflicts, the confirmation of the conflict against a project feature, the alternative resolutions considered, the analysis of those alternatives, and the resolution selected.

In construction, good conflict work looks quiet. Crossings the plan flagged are exposed and crossed as instructed. Resolutions assumed by the design are visible in the work plan. When the field finds something the plan did not show, work in that area stops, the condition is protected, and the discovery is reported the same day through the project process, so the conflict list gains a new row instead of the crew gaining a new improvisation.

What Can Go Wrong?

The first failure is designing in ignorance and calling it design. If existing utilities are never depicted, or are depicted from records and never checked, the conflict list is empty because nobody looked, not because the corridor is clear. The conflicts still exist. They are simply scheduled to be discovered by construction equipment instead of by analysis.

The second failure is trusting low quality data for a high stakes call. Records alone are Quality Level D, the least reliable level, and FHWA SUE material notes that record based information is often limited in accuracy and completeness. Clearing a close crossing on record data alone, or confirming a conflict and ordering a relocation on record data alone, are opposite errors with the same cause: the decision was bigger than the data behind it.

The third failure is inventing a separation number. A crew member or designer takes a distance remembered from another job, another state, or another utility owner, and treats it as the requirement for this job. Separation and clearance requirements come from the governing code, the facility owner standards, the permit, and the project specification for the specific situation. A number that was correct for a gas line on one project may be wrong for an electric duct bank on this one, wrong in the other direction for a gravity sewer, and irrelevant where the real issue is construction method rather than distance. This lesson deliberately teaches no universal separation distance, because no such universal distance was verified in the sources used. When the governing number is not in hand, the correct move is to get it from the controlling document or the facility owner, not to substitute memory.

The fourth failure is confusing a near miss with a conflict, or a conflict with a near miss. Calling every close crossing a conflict triggers needless redesigns and relocation requests, and it teaches utility owners to discount the list. Calling a true conflict a near miss because the lines do not quite touch ignores clearance requirements and construction risk, and it sends a crew into a crossing that the governing requirement never approved. Both errors come from skipping the same step: comparing verified positions against the actual governing requirement for that situation.

The fifth failure is resolving the conflict in the field without authority. A crew that finds an unrecorded facility in its bore path and decides on its own to shift the bore, deepen the bore, or crowd past the facility has made a design decision without the designer, a clearance decision without the facility owner, and a risk decision without the project owner. The shift may create a new conflict with a different facility, violate the permit, or put the new conduit where its own owner cannot maintain it. Field discovery is valuable. Field redesign is not the crew’s role.

The sixth failure is treating relocation as a phone call. A resolution that says relocate the existing utility is the start of the owner’s process, not the end of the conflict. The owner must agree, design the adjustment, obtain what it needs, schedule the work, and in many cases decide questions of cost and property rights that the project does not control. A conflict marked resolved because relocation was requested, rather than because relocation was agreed, designed, and scheduled, is a schedule surprise waiting to happen.

The seventh failure is letting the list go stale. Resolutions change, designs change, and new conflicts appear when either side changes. A matrix that was accurate at an early design milestone and never updated will confidently mislead the construction team. The document only works if it is maintained through design and into construction, with new field discoveries added as they occur.

What Should Someone Notice in the Field?

You can read the state of conflict work from the field if you know what to look for, even though the decisions themselves happen in design and coordination meetings.

Notice whether the plan you are handed shows existing utilities at all. A fiber plan that draws the proposed route in detail and shows no existing facilities along it is not a clean plan. It is an unexamined one. Notice whether crossings are called out, whether conflict numbers or notes appear at crossings and structure locations, and whether the plan carries instructions for specific points, such as expose before crossing or a stated method for a stated segment.

Notice the data behind a close crossing. If the plan shows a proposed bore passing close to an existing facility, ask what quality level the existing position is based on. Records only, surface features, designated position, or exposed and measured? A close call supported by a test hole record is a different thing from a close call supported by an old drawing, and you are allowed to ask which one you are looking at.

Notice white lining and marks at crossings. White lining, covered in Lesson 62, marks the planned work. Locate marks show the designated existing facilities. Where the two sets of marks converge, that is a point to slow down and check the plan notes before work starts, not after.

Notice exposure at flagged points. If the plan or the conflict list says a crossing was to be verified by a test hole, look for the evidence: the restored patch, the test hole number, or the record in the job file. A flagged conflict with no verification record and no other resolution note is an open conflict wearing a closed costume.

Notice separation being measured, not assumed. At an exposed crossing, someone should be comparing the actual position of the existing facility against the planned path and the governing requirement for that job. If you hear a separation distance quoted, notice whether anyone can name the document it came from. A number with no source is an opinion, and opinions do not clear crossings.

Notice what happens when something unexpected is found. The healthy pattern is the one Lessons 67 and 68 teach: work stops in that area, the facility is protected and not disturbed further, and the discovery is reported through the project process with location and description. The unhealthy pattern is a huddle that ends with the bore or the trench quietly rerouted by field decision. If you see the second pattern, you are watching a new conflict being created while an old one is being hidden.

Notice the conflict paperwork itself, if you have access to it. A living list has recent dates, statuses that change, and resolutions with names attached. A dead list has one date, vague statuses, and conflicts that never close. Notice also whether field discoveries from your own project appear on it in the days after they are reported. If they do not, report that gap too, because a list that does not absorb field findings will not protect the next segment of the same job.

Practical Example

The following example is hypothetical. It is invented to teach the process, not to describe a real job, a real utility, or a real requirement. No distance in this example is stated as a rule, because the governing requirement on a real job comes from that job’s code, owner standards, permit, and specification.

A design team is planning a hypothetical fiber route along a county road. The proposed work is a buried conduit placed by horizontal directional drilling, with a handhole near an intersection. During records review, the designer depicts a water main and a sanitary sewer from the owners’ records and places them on the base plan as Quality Level D information. A SUE provider then surveys the visible surface features, correlating manholes and valve boxes with the records for Quality Level C, and designates both lines with surface geophysical methods for Quality Level B.

The designer overlays the proposed conduit alignment, the bore path profile, and the handhole location on the depicted utilities and builds the first conflict list. Three entries appear. Entry one: the proposed handhole sits directly over the designated water main. That is a direct physical conflict, subject to field verification. Entry two: the bore path crosses the sewer at an elevation the records suggest is close, at an angle where the reamed bore could come near the sewer. That is a potential clearance and risk conflict, and the vertical data behind it is only record based. Entry three: along one segment the bore runs parallel to the water main at a steady offset shown on the plan. It does not cross, and whether it conflicts depends on verified positions and the governing separation requirement for that owner and situation, which the designer obtains from the water owner standards and the project specification rather than assuming.

The team orders test holes at the critical points: at the handhole location, at the sewer crossing, and at two points along the parallel segment. The exposures produce Quality Level A positions. The results settle all three entries. At the handhole location, the water main is confirmed within the proposed structure footprint, so the conflict is real. The designer moves the handhole to a verified clear location, an avoidance resolution, and the entry is closed as resolved by design. At the sewer crossing, the measured sewer elevation is lower than the records suggested, and the comparison against the governing requirement shows the planned bore passes with the required separation. The entry is closed as no conflict after verification, a near miss that fits, and the test hole record is attached so the closure can be checked later. Along the parallel segment, one test hole confirms adequate separation, but the second shows the water main bending toward the proposed path until the remaining space is less than the governing requirement allows. That entry is a confirmed clearance conflict. The designer adjusts the proposed alignment horizontally through that segment to restore the required separation, the water owner reviews the adjustment in a coordination meeting, and the entry is closed as resolved by design with the revised alignment shown on the plan.

Construction proceeds on the revised plan. Midway through the job, the bore crew’s pothole at a different crossing exposes a conduit that appears on no record and no conflict entry. The crew stops in that area, protects the exposure, and reports it through the project process the same day. A new entry is added to the conflict list as a field discovered potential conflict, the designer and the facility owner identified for the conduit decide the resolution through the coordination process, and only then does work at that crossing resume. Nobody on the crew redesigned the bore at the roadside, and nobody treated the discovery as a reason to crowd past an unidentified facility.

Notice what made the example work. Conflicts were found by comparison, not by contact. Weak data was upgraded exactly where the decision needed it. One conflict was avoided by moving the new work, one suspected conflict was honestly closed when verification showed it fit, one was resolved by adjusting the design, and one surprise was escalated instead of improvised. That is conflict management doing its job.

Key Terms

Utility conflict: a situation in which a proposed new facility, structure, grade change, or work method cannot be built as designed because an existing utility is in the way, is too close under the governing separation or clearance requirement, or would be put at risk by the work.

Proposed facility: the new facility shown on the design, together with its structures, planned grades, and installation method.

Existing utility: a facility already in place when new work arrives, owned and operated by its own utility owner.

Separation: the distance between two facilities, horizontal, vertical, or both, as the governing requirement for the situation defines it.

Clearance requirement: the required space that must be kept between or around facilities or structures under the governing code, owner standard, permit, or project specification for that job. There is no single universal number.

Near miss that fits: a case where new work and an existing utility are close but the verified separation meets the governing requirement, so no conflict exists. The verification and the requirement are both part of the finding.

Conflict analysis: the design process of comparing depicted existing utilities against the proposed plans to identify potential conflicts, potential resolutions, and the cost to resolve them.

Conflict matrix (conflict list): a working document that lists each conflict with its location, the utility and owner involved, the proposed feature it conflicts with, the quality level of the data, the resolutions considered, the resolution selected, and the status. Also called a utility conflict list.

Utility coordination: the organized communication among the project owner, the designer, and utility owners to identify facilities, find conflicts early, and agree resolutions before construction.

Subsurface utility engineering (SUE): the engineering practice of gathering, depicting, and managing existing utility data at stated ASCE 38 quality levels, from Quality Level D records up to Quality Level A exposure and measurement.

Quality Level A: the ASCE 38 level for precise horizontal and vertical position obtained by actual exposure and subsequent measurement of the facility, usually at a specific point. Lower levels are D (records or recollections), C (records correlated with surveyed surface features), and B (approximate horizontal position obtained by surface geophysical designating).

Relocation: moving an existing utility, permanently or temporarily, so the proposed work can be built. Relocation is designed and performed by or for the utility owner, under the owner’s standards and decisions.

Protect in place: a resolution in which the existing utility stays where it is and is shielded, supported, or otherwise protected under an approved plan so the proposed work can proceed without harming it.

Check Your Understanding

  1. State the three ways a utility conflict can exist, and give one short example of each.
  2. A bore path passes near an existing line without touching it, and a crew member says there cannot be a conflict because nothing overlaps. What two kinds of conflict could still exist, and what would you check?
  3. What is a conflict matrix, and what are four things a useful entry in one should record?
  4. A designer wants to clear a very close crossing using only the utility owner’s old record drawing. Using SUE quality levels, explain the problem and name the step that would settle it.
  5. A field crew exposes an unrecorded facility in the bore path and the crew leader proposes shifting the bore a short distance on the spot to get past it. What should happen instead, and who decides the resolution?

Answer key:

  1. A direct physical conflict, where the proposed and existing facilities need the same space, such as a handhole designed over a water main. A clearance conflict, where the facilities do not touch but the space between them is less than the governing requirement allows. A risk conflict, where the facility itself might fit but the work method or construction activity, such as excavation, grading, or reaming a bore, would endanger the existing facility.
  2. A clearance conflict could exist if the verified separation is less than the governing requirement for that situation. A risk conflict could exist if the drilling and reaming process, equipment loads, or excavation could damage the line even without direct contact. Check the verified position of the existing facility, at the best available quality level, and compare it against the actual governing code, owner standard, permit, or specification requirement for that job, not against a remembered number.
  3. A conflict matrix, or conflict list, is the working document used in design and coordination to identify, organize, analyze, track, manage, and mitigate utility conflicts. A useful entry records any four of: the location of the conflict, the existing utility type and its owner, the proposed feature it conflicts with, the quality level of the data behind the positions, the alternative resolutions considered, the resolution selected and who is responsible for it, and the current status.
  4. A record drawing alone is Quality Level D, the least reliable level, based on existing records or recollections. It cannot prove the precise vertical and horizontal position a close call depends on. The step that settles it is a test hole at the critical point, exposing the facility with minimally intrusive methods and measuring and surveying its position, which produces Quality Level A information for the conflict decision.
  5. Work in that area stops, the facility is protected, and the discovery is reported through the project process, following the same discipline as for a mismarked or unknown utility. The resolution is decided by the designer or engineer, the facility owner, and the project owner through their coordination process. The crew reports facts and follows the revised plan. It does not redesign the bore in the field.

Lesson Takeaway

A utility conflict is a space problem found by comparison: the proposed facility, structure, grade, or method cannot be built as designed because an existing utility occupies the space, sits closer than the governing requirement allows, or would be endangered by the work. Conflicts are found by layering records review, field verification, SUE data at honestly stated quality levels, test holes at critical points, and conflict analysis against the design, and they are tracked on a conflict matrix that records the data quality and the resolution status of every entry. They are resolved, in order of preference, by designing around the utility, minimizing the impact, or mitigating it, through paths that include adjusting the design, relocating the existing utility by its owner’s decision, protecting it in place, changing the method, or phasing the work. Separation numbers belong to the governing documents for the specific job, never to memory or habit. And the authority line is bright: designers, facility owners, and project owners decide resolutions. Field crews find, protect, and report. A conflict handled that way is a planned decision. A conflict handled any other way is a strike that has not happened yet.

Sources and Technical References

  • Federal Highway Administration, Subsurface Utility Engineering overview: SUE combines records research, site surveys, surface geophysical methods, and nondestructive vacuum excavation to provide quality levels of information; Quality Level D comes from existing records or verbal recollections and is often highly limited in accuracy, Quality Level C correlates surveyed visible features with records, Quality Level B gives approximate horizontal position by surface geophysical methods, and Quality Level A gives precise horizontal and vertical location by actual exposure and measurement, usually at a specific point; the highest level is generally needed only where conflicts with design features are most likely: https://www.fhwa.dot.gov/programadmin/sueindex.cfm
  • Federal Highway Administration, SUE Brochure: conflict analysis is the engineering process of using a conflict matrix to evaluate and compare depicted designating information with proposed plans (highway, bridge, drainage, and other) in order to inform all stakeholders of potential conflicts, potential resolutions, and costs to cure; includes the ASCE 38-02 quality level definitions used in this lesson: https://www.fhwa.dot.gov/design/sue/suebrochure.cfm
  • Federal Highway Administration, SUE Then and Now: develop a conflict matrix showing all possible conflicts, with columns for the physical location of each conflict, the utility involved, the nature of the conflict, and the action needed; some conflicts can be readily resolved, some are questionable and need additional information, and some cannot be resolved; expose selected utilities with minimally intrusive excavation such as vacuum excavation for Quality Level A information, then return to the conflict matrix with the new information to determine conflict status; includes convening utility companies to discuss conflicts and strategies to avoid them: https://www.fhwa.dot.gov/programadmin/history.cfm
  • Federal Highway Administration, The Proper Use of Subsurface Utility Engineering: for final design, test holes are selected at critical points where the design and underground utilities appear to conflict, nondestructive digging equipment is used to determine precise horizontal and vertical position for Quality Level A information, and discrepancies with previous plan information are resolved: https://www.fhwa.dot.gov/programadmin/proper.cfm
  • Federal Highway Administration, Subsurface Utility Engineering (EDC-8): unexpected utility conflicts during construction are one of the leading causes of project delays and cost overruns; SUE locates and maps utilities early in planning and design, identifies possible conflicts with planned work, and supports planning to move utilities or design around them; the current ASCE guideline is ASCE/UESI/CI 38-22, Standard Guideline for Investigating and Documenting Existing Utilities: https://www.fhwa.dot.gov/innovation/everydaycounts/edc_8/subsurface_utility_engineering.cfm
  • SHRP2, Identifying and Managing Utility Conflicts (R15B), lessons learned summary: utility conflict management is a comprehensive multistage process for the systematic identification and resolution of utility conflicts; two critical factors behind utility inefficiency are inadequate information about the location and attributes of existing facilities and the lack of an effective process to manage conflicts between those facilities and project features and phases; tools include a standalone utility conflict list template, a conflict data model, and training: https://shrp2.transportation.org/Documents/Renewal/Utilities final documents/SHRP2 R15B Lessons Learned 05_08_19.pdf
  • Kentucky Highway Knowledge Portal summary of utility conflict management training (3WH): the goals of utility conflict management in order of preference are avoid (design the project to avoid the conflict), minimize (reduce impacts where the design cannot avoid the utility), and mitigate (including relocating the utility); the Utility Conflict Matrix is a collaborative tool to identify, organize, analyze, track, manage, and mitigate conflicts, tracking utility location, type, and ownership, identification and confirmation of conflicts, alternative resolutions, analysis of alternatives, and the selected resolution; resolution actions include altering the design (horizontal or vertical alignment changes), protecting in place, and removing, abandoning, or relocating facilities: https://kp.uky.edu/knowledge-portal/articles/tracking-utility-conflicts-3wh/
  • Federal Highway Administration, Avoiding Utility Relocations, preface: every effort must be made to design around as many utilities as possible; consultation with utilities early in project development can produce minor plan changes that avoid costly, time consuming, and unnecessary relocations; SUE information allows designers to avoid relocations and to certify the accuracy level provided on plans: https://www.fhwa.dot.gov/utilities/utilityrelo/preface.cfm
  • Texas Department of Transportation, Utility Accommodation Process: utility conflicts should be identified as early in project development as possible, coordination with affected utility owners should begin early in design, and the department may determine it is preferable to design around a utility rather than require the owner to adjust it; adjustment plans show existing and proposed utilities and help resolve potential conflicts between utilities and construction activities: https://www.txdot.gov/manuals/des/pdp/chapter-6–right-of-way-and-utilities/6-4-utility-accommodation-process.html

Flagged for verification or follow-up: The full text of ASCE 38-22 is a copyrighted standard and was not read in full for this lesson. The quality level definitions used here follow the summaries published by FHWA, which cite the ASCE 38 framework, and are consistent with the framing in Lesson 65. Verify exact standard wording and any project accuracy or depiction requirements against the current standard and the project specification before using them in a contract document. No universal separation or clearance distance is stated in this lesson, deliberately: the sources used set those values by situation through codes, facility owner standards, permits, and project specifications, and no single distance was verified as applying generally. Any separation figure used on a real job must be taken from the governing document for that facility and that situation. The avoid, minimize, mitigate order of preference is stated as utility conflict management guidance in the training summary cited above; individual project owners and state agencies may structure their own resolution process differently, and the project process for the job in front of you controls.


Previous lesson: Lesson 68: What If You Find an Unknown Utility? |
Back to Level 3 hub |
Next lesson: Lesson 70: What Is a Utility Strike?