Introduction
A duct bank is an arrangement of multiple conduits installed together in one trench as a single structure, held in a fixed pattern and commonly surrounded by encasement, so the group runs as one organized pathway between structures such as a manhole and a handhole. Heldenfels describes the finished form in plain terms: conduits held in precise position by spacers and completely surrounded by concrete become a single rigid structure, and crews later pull cable through the empty ducts.
Level 8 studies the underground pathway piece by piece. Lesson 144 taught duct, Lesson 145 taught innerduct inside a duct, and Lesson 146 taught microduct. This lesson teaches the structure that groups several full size ducts together for one segment of the route, and it teaches why the work done before the trench is covered decides whether that segment stays usable for decades.
What This Lesson Gives You
- Look at an open trench before cover and tell whether the conduits in it form a duct bank, and name the parts that make it one: conduits, spacers, encasement, and ends entering structures.
- Explain how spacers and restraint during the pour hold each conduit in its assigned position, and why a conduit that floats or shifts during the pour stays in the wrong place after the encasement hardens.
- Read a duct bank position record and match each conduit position at one structure to the same position at the next structure.
- Name the checks that prove a bank before it disappears from view: alignment, spacer support, restraint, end condition, position record, and mandrel proofing where the project documents require it.
- State the hold decision when conduits move during a pour, when a position has no record, or when a finished conduit fails proofing, and name who must decide what happens next.
Start With the Basics
Picture an ice cube tray while it is being filled. The tray holds a set of separate compartments in a fixed grid. Water flows around and between the compartments, then freezes and locks every wall in the position the tray gave it. After freezing, the grid is permanent for the life of that block of ice. Moving one compartment would mean breaking the block apart.
A duct bank works through a similar mechanism, with one difference in what plays each part. The conduits are the compartments, long tubes instead of small cubes. Spacers are the frame that holds the tubes in a grid, with set separation between each tube and the next. The encasement is the material that flows around the tubes and then hardens or sets in place, commonly concrete on encased banks. Once that material sets, the grid stops being an arrangement a crew can adjust by hand. The grid becomes the pathway itself, fixed in the ground, and every later cable pull has to live with the positions the pour locked in.
That single fact explains the whole lesson. Work on a duct bank is front loaded. Alignment, support, restraint, and records all happen while the conduits still sit open in the trench and a hand can still correct them. After encasement and backfill, correction means excavation and demolition, and some defects have no practical correction at all.
What Is It?
A duct bank is a grouped pathway structure. The definitions below build the picture in order, from the single tube outward to the finished bank and its record.
Conduit and duct, recalled. A conduit is a rigid or flexible metal or nonmetallic raceway through which cables can be pulled. A duct is a tube, usually plastic in modern fiber work, that protects underground cable and provides its route. Lessons 4 and 144 covered these terms. A duct bank uses several conduits or ducts side by side, and the words conduit and duct appear interchangeably in much of the duct bank literature for the tubes inside the bank.
Duct bank defined. A duct bank, also called a conduit bank in some references, is a group of conduits arranged in a fixed pattern, usually in rows and columns, installed together in one trench and commonly encased in concrete or surrounded by engineered fill specified for the job. Muller EC defines a duct bank as a group of underground conduits, usually encased in concrete, that protects electrical and communications cables from soil, moisture, and damage. Heldenfels gives the structural version of the same definition: an underground array of conduits held in precise position by plastic spacers and then completely surrounded by concrete, so the loose conduits become a single rigid structure. A bundle of conduits laid loose in a trench, with no fixed pattern and no encasement or specified fill holding that pattern, is direct buried conduit. The fixed pattern and the material that locks the pattern in place are what make the group a bank.
Rows, columns, and position. Banks are commonly described by their grid, with conduits arranged in rows, meaning horizontal layers stacked in height, and columns, meaning vertical lines side by side across the width. Each conduit in the grid holds one position, meaning its named place in that grid, such as top row or bottom row and its place across the width, as the project record defines the naming scheme. Position is an identity, in the same way a channel identity was an identity in Lesson 145. A crew at one end of the segment and a crew at the other end must be able to use the position name and arrive at the same physical tube.
Spacer. A spacer is a nonmetallic support that holds conduits at a uniform separation and in alignment inside the bank before and during encasement. Laird Plastics defines a duct bank spacer in those terms: a nonmetallic support used to maintain uniform horizontal and vertical separation between conduits inside a concrete encased duct bank. The Fiber Optic Association, called FOA, states the field reason for spacers when several ducts share a trench: spacers prevent ducts from twisting over and around each other, and keeping ducts in straight alignment reduces cable jetting and pulling tensions. Spacers appear in two working roles on many product lines. A base spacer supports the bottom row and sets it off the trench floor. An intermediate spacer sits between rows and supports the row above it. Underground Devices describes its Wunpeece spacer as a one piece design that serves both roles for concrete encased duct runs, made of high impact polystyrene, with molded interlocks that join spacers side by side. Product design varies by manufacturer, so the spacer for a job comes from the project documents and the manufacturer instructions for the selected product.
Encasement. Encasement is the material placed around the assembled conduits to lock the pattern, spread surface loads, and protect the conduits as one structure. Concrete encasement is the common form on duct banks that carry the name, and project documents state the concrete requirements for the job. Some designs specify controlled fill instead of full concrete encasement, meaning an engineered fill material placed and compacted or flowed around the conduits under the project specifications. Maveric Contractors describes that choice directly: concrete encasement, or an engineered backfill where the design specifies it, is placed around the conduits, followed by compacted backfill up to finished level. The design decides which material a given bank receives. Field staff build the bank the drawings show, and they record any approved change through the project process.
Separation. Separation is the clear distance maintained between one conduit and the next, and between the outer conduits and the edge of the encasement. Separation does physical work. Open space between conduits lets encasement flow around every tube and surround it, so each conduit sits supported on all sides after the material sets. Separation values for a job come from the project drawings and specifications. One manufacturer guide specification shows how specific those documents get: the Underground Devices Wunpeece guide specification calls for concrete encasement with at least three inches of concrete at the top and bottom and two inches on each side, with the horizontal and vertical separation between ducts filled in from the table for the duct size selected. That language belongs to that guide specification. It sets no universal value for other jobs, and field staff take separation and encasement thickness from the documents for the bank in front of them.
Spacer interval. The spacer interval is the distance along the run between one set of spacers and the next. Interval matters because a conduit supported only at its ends can sag, bow, or shift between supports, and a long unsupported span can move when fluid concrete pushes against it. The Underground Devices guide specification states that spacers along the length of a duct run are placed at an interval stated in spacers per twenty feet, and it notes that three or four spacers per twenty feet is typically specified, with four spacers per twenty feet the common choice in that specification. Laird Plastics gives a similar general range in its spacer guide, with spacers typically installed every four to seven feet along the trench and closer spacing for larger conduits, deeper trenches, or unstable soil, while directing installers to project specifications and engineering direction. Both sources agree on the governing point: the interval for a job is set by the project documents, and a crew verifies the interval in the trench against those documents.
Structures at each end. A duct bank runs between access points where crews can reach the conduit ends. A manhole is a larger underground structure a person can enter under the applicable confined space program, covered in the structure lessons of this course. A handhole is a smaller access structure reached from the surface, with no entry by a worker. The bank itself is the buried segment between structures. The structures are where position records get checked, where cables enter and leave conduits, and where proofing and pulling work happens.
Spare conduit. A spare conduit is an empty conduit built into the bank for a future cable, deliberate in the design on many jobs. Muller EC notes the working reason: spare conduits let crews pull new cable later without digging. A spare has value only while it stays open, proven, capped against debris, and identified by position in the record. An unproven spare is a claim on paper, and Lesson 145 taught the same discipline for spare innerduct channels.
Position record. The position record, also called the duct bank section drawing or bank map in project files, is the record that names every conduit position in the grid, states which positions are occupied and which are spare, and lets a reader match each position at one structure to the same position at the next structure. A telecom duct bank checklist published by PakTechPoint states the underlying check in direct terms: corresponding conduits at conduit entrances in opposite ends of manholes shall be at the same level and in the same position with respect to the side walls. A bank built with one conduit crossed over another between structures breaks that correspondence, and a record drawn from one end then misidentifies conduits at the other end.
Mandrel and proofing. A mandrel is a sized slug or cylinder pulled through a conduit to prove the conduit is open, round enough, and free of obstruction along its full length. Proofing, also called mandreling in utility standards, is the act of pulling that mandrel through each conduit and recording the result. Seattle City Light Construction Standard U2-11.40 requires each duct run and conduit to be tested for obstructions or flattening by hand pulling a proofing mandrel through it after the concrete has been poured or the trench backfilled over the conduit, and it requires a section with an obstruction to be replaced under that standard. Sample duct bank specifications collected by Law Insider describe the same test at two points in the work: a mandrel test after the bank is assembled and before concrete is poured, and a second mandrel test after the concrete has set, drawn through each conduit with the inspector present. Mandrel size in those sources is set a stated amount smaller than the inside diameter of the conduit, with the exact size taken from the governing standard or specification for the job. Proofing is the last cheap chance to learn that a conduit was crushed, flattened, or blocked during encasement, while the segment is still new work under the builder.
Cover. Cover is the distance from finished grade down to the top of the bank or its encasement. Cover protects the bank from digging and surface loads, and cover requirements depend on what the bank carries and where it runs. For electrical conductors and raceways, the National Electrical Code, called NEC or NFPA 70, sets minimum cover in Table 300.5 for circuits at 1,000 volts or less and in Table 300.50 for higher voltage work, with values that vary by wiring method, voltage, and location, such as under a road or parking area. Heldenfels summarizes that table for duct bank readers and states the caution that travels with it: specific depth, spacing, and voltage requirements depend on the applicable code edition and the utility design standards, confirmed with the engineer for the job. Communications duct banks follow the cover stated in the project drawings, the owner standards, and the local requirements that govern that work. A fiber crew takes cover from the documents for the job and never borrows an electrical table value as a fiber rule, and an electrical crew works to the adopted code edition and local amendments for its circuits.
Reinforcement. Some bank designs add reinforcing steel, meaning steel bars placed in or around the encasement and tied as the drawings direct, so the hardened encasement acts with more strength across soft spots and under loads. Heldenfels describes that function: rebar ties the encasement into a beam that spans soft spots, resists point loads from traffic above, and helps keep the conduit array from shifting during backfill and compaction. Reinforcement belongs to the design. Its presence, size, and placement come from the drawings, and field staff verify what the drawings show before the pour covers it.
What Does It Look Like?
A beginner meets a duct bank in three states: an open trench before the pour, a finished segment known only by its ends and its record, and a drawing of the grid. Each state shows different evidence.
In the open trench before encasement:
- Parallel conduits running in a clean grid, with rows stacked evenly and columns in straight lines along the trench.
- Spacer frames visible at regular intervals along the run, each frame holding every conduit in the grid, with the bottom row lifted off the trench floor by base spacers or the base of the spacer system.
- Conduits running straight between spacer sets, with no sagging spans, no conduit resting on another conduit, and no crossing between positions.
- Restraint ready for the pour where the documents require it, such as hold down bars, straps, stakes, or tie downs holding the assembled bank against movement.
- Conduit ends entering the structure walls in the same grid pattern the trench shows, with ends capped or protected so concrete, soil, and debris stay out during the pour.
- A trench floor that is even and prepared as the documents direct, so the bottom row sits level along the run.
During and just after the pour:
- Fluid concrete or specified fill flowing around and between the conduits, filling the spaces the separation provides, with workers watching the top row for any rise or sideways drift.
- The top of the finished encasement sitting at a level, even surface, with the grid pattern still traceable by the conduit ends at the structure.
- Conduit ends at the structure face showing the same arrangement as the position record, row above row, in the order the record names.
At a finished bank, from a structure:
- A wall face with a grid of conduit openings, each opening round and clear, arranged in the rows and columns the record describes.
- Occupied openings with a cable leaving the conduit toward its splice case or equipment, and spare openings capped or plugged, clean inside as far as light allows.
- Labels, tags, or a posted section drawing at the structure that name each position, where the owner standard provides them.
- A bank face where one opening sits visibly out of line with its row, pinched oval, or offset from the position the record assigns it. That sight suggests movement or damage during construction, and the conduit behind that opening needs proofing before any cable is assigned to it.
In the record:
- A section drawing showing the grid as seen looking into the structure, with each position named, and a table or notes stating occupied and spare status per position.
- Route information tying the bank to its two structures, so a reader can stand at either end and use the same drawing with the orientation stated.
- Proofing results recorded per position, where the project documents require proofing, with any failed position named and held out of service.

What Does It Do?
A duct bank earns its cost through four mechanisms. Each mechanism follows from grouping conduits into one fixed, protected, and recorded structure.
One trench carries many pathways. Excavation, permits, traffic control, and surface restoration are paid once for the segment, and the bank places several conduits in that one opening. Each conduit is a separate pathway for its own cable, in the same way each innerduct channel in Lesson 145 held its own cable. Growth planned at design time becomes spare conduits in the bank. Growth ignored at design time becomes a second excavation on the same route later. FOA states the planning version of this point under its Dig Once material: burying conduit under roadways is disruptive, and many permitting authorities require extra conduits along a route to prevent digging again for future installations.
The fixed grid keeps every pathway findable and pullable. Spacers hold conduits parallel, separated, and straight for the full length of the segment. Straight and parallel conduits give a cable a predictable path with gentle contact along the run. FOA ties alignment to the pull directly: keeping ducts in straight alignment reduces cable jetting and pulling tensions, and spacers prevent ducts from twisting over and around each other. A conduit that crossed over its neighbor inside the bank would present the wrong position at the far structure and would add bends the record never shows. The grid prevents both failures by fixing each conduit in its position from structure to structure.
Encasement spreads load and shields the group as one structure. Soil weight, traffic, and equipment loads reach the top of the bank first. A hardened encasement spreads a concentrated load across the width and length of the bank, so a single conduit wall carries a share of the load instead of the whole load at one point. Heldenfels describes that protection in direct terms: the concrete distributes crushing loads from soil, traffic, and heavy equipment, so a passing loader or a stack of backfill never deforms a conduit or pinches the cable inside it. Encasement also gives later excavators a hard, visible structure to encounter and recognize as a utility bank, a warning function that loose conduits in soil cannot provide as reliably. Controlled fill specified by a design provides protection by the means that design states, and field staff judge a fill bank by its own documents.
The position record turns a buried grid into managed capacity. A bank underground is invisible. Its value reaches a planner, a splicer, or a restoration crew only through its record. A position record with occupied and spare status lets an owner assign a new cable to a named spare position, dispatch a crew to the correct structure, and prove the conduit before the pull date. A bank with no position record still holds conduits, and every future job on that segment starts with investigation work to learn which tube is which at each end. Records made before cover, while the grid sits visible in the trench, cost minutes. Records reconstructed years later cost structure visits, proofing runs, and schedule risk on a live job.
Where Does It Fit?
A duct bank is one segment type inside the underground pathway, and it connects to every phase of the network life around it.
- Design. The designer sets the route, the two structures, conduit count and size, grid pattern, spacer product and interval, encasement or fill material, cover, reinforcement where the design calls for it, spare count, and the position naming scheme. Code requirements for electrical circuits, owner standards, and local requirements enter here, each in its own lane.
- Trench and structure work. Crews excavate the trench, set or build the structures at each end, and prepare the trench floor. Conduit entries in the structure walls fix the grid pattern at both ends before the run between them is assembled.
- Bank assembly. Crews lay out spacers, set conduits row by row, check alignment and separation, fit restraint where required, cap conduit ends, and complete the position record while the whole grid is visible. Proofing before the pour, where the documents require it, belongs to this phase.
- Encasement. Concrete or specified fill is placed around the assembled bank in the manner the documents direct, with the crew watching for movement and holding the bank in position until the material sets. This phase converts an adjustable assembly into a fixed structure.
- Backfill and restoration. Compacted backfill and surface restoration follow over the set bank, with warning or marker tape placed above the bank where the documents require it, as FOA describes for buried conduit routes.
- Proofing and acceptance. Each conduit is cleaned and mandrel proofed where required, pull tape or rope is left in spare conduits as the documents direct, and results are recorded per position. Seattle City Light requires pull tape left in each conduit after cleaning and mandreling under its standard, with the tape type and slack stated in that standard. The governing documents for a job state the equivalent requirement for that job.
- Cable placement and splicing. Each cable is pulled through its assigned position, and the position record tells the splicer which cable arrived from which direction and position at each structure.
- Growth and repair. A new cable uses a proven spare position. A damaged cable is replaced through its own position or a spare. A failed position is held out of service in the record until a repair decision is made by the responsible authority.
- The neighboring lessons. Lesson 144 taught a single duct, Lesson 145 taught subdivision inside a duct, and Lesson 146 taught microduct. A duct bank groups full size ducts at the segment level. Innerduct can still subdivide an individual conduit inside a bank, so the two systems stack: the bank organizes conduits between structures, and innerduct organizes cables inside one of those conduits.
What Is at Stake
A defect locked in concrete. A conduit that floats, shifts, sags, or gets crushed during the pour holds that defect after the encasement hardens. Repair means breaking out and rebuilding a section of bank, with excavation, demolition, disposal, and restoration, or abandoning the position and losing its capacity for the life of the segment. Alignment and restraint checks before and during the pour are cheap. Every alternative after the pour is expensive.
Buoyancy during the pour. Hollow plastic conduits and plastic spacers weigh far less, volume for volume, than fluid concrete or flowable fill. Patent literature for duct bank hold down systems states the result plainly: the duct bank includes conduits and spacers with a specific gravity far less than concrete or flowable fill, so the bank may move and will float unless it is restrained when concrete is poured into the trench. A bank that rises during the pour can lose cover at the top, break its alignment at the structure entries, and trap conduits at wrong elevations. Restraint is a planned part of the assembly, with hold down bars, straps, stakes, or other methods as the documents and the spacer manufacturer direct.
Position errors that outlive the crew. A conduit crossed inside the bank, or a record drawn carelessly from one end, misidentifies positions at the far structure for every later user of that record. Consequences range from a crew pulling a cable into an occupied position, to a crew cutting or removing a cable believed spare that is in service, to restoration time lost while crews re-identify every position under pressure. The PakTechPoint checklist requirement, corresponding conduits at the same level and the same position at opposite ends, exists to prevent exactly this class of error.
Capacity that exists on paper only. A bank accepted without proofing can carry a flattened or blocked conduit that no cable will ever pass. The failure surfaces later, on a sold job with a due date, when the assigned spare position refuses a mandrel and refuses a cable. Proofing at acceptance converts that surprise into a construction finding, fixed by the builder while the segment is still new work.
Concrete that never surrounded a conduit. Separation exists so encasement can flow around every tube. Conduits touching each other, or a row resting on the row below with spacers missing, leave voids and thin spots in the hardened encasement. The affected conduits lose the load spreading and support the bank was built to provide, and the weak zone sits hidden until a load or a later excavation finds it.
Safety around trenches, pours, and structures. Trench work, concrete placement, and structure entry carry hazards covered by the safety lessons in this course and governed by employer programs and regulation. Duct bank work adds a specific trap for beginners: a bank looks solid and simple, and that appearance can invite a person to step into a trench, reach across a pour, or enter a structure beyond their training and authorization. The field checklist at the end of this lesson states the boundary in full.
What Does Good Look Like?
- The assembled grid matches the drawings for conduit count, size, row and column pattern, and position naming, and the pattern at the trench matches the entries at both structures.
- Spacers support every row at the interval the documents state, each conduit sits in its spacer seat, and no conduit rests directly on another conduit or on the trench floor.
- Separation between conduits and around the outside of the grid matches the drawings, with open space for encasement to flow around every conduit.
- Restraint for the pour is in place as the documents and the spacer manufacturer direct, and the bank shows no rise, drift, or sag while encasement is placed and after it sets.
- Conduit ends are capped or protected through the pour, cut and dressed cleanly at the structure faces, and each opening sits round and clear in its recorded position.
- The position record is complete before cover, names every position with occupied or spare status, and a reader at either structure can match the record to the openings in view.
- Proofing results are recorded per position where the documents require proofing, each passing conduit holds its pull tape or rope as directed, and any failed position is named in the record as held out of service.
- Encasement surrounds the full grid with no visible voids at the structure faces, and its top sits at the elevation the drawings state, with cover to finished grade as the documents require.

From the Field
Picture a road crossing segment built as a concrete encased duct bank between two handholes, with conduits arranged in two rows as the drawings show. The crew has assembled the grid on spacers, the position sketch is started, and the concrete truck is scheduled. The inspector walks the trench before the pour and checks the assembly against the drawings, spacer by spacer.
At the middle of the run, the inspector finds two problems in the same span. The spacer interval there runs well past the interval the documents state, with a long unsupported length of conduit sagging between spacer sets. No restraint holds that span down. The top row sits low in the sag and high at the ends, and the position sketch stops at the first structure, with the far end positions left for later.
The pour foreman raises the schedule pressure. The truck is coming, the road closure window is short, and the bank looks close enough to straight from the trench edge. Pouring on time keeps the day on plan, and the sag sits hidden once concrete covers it.
The inspector holds the pour at that span and works the problem in the order this lesson teaches. An unrestrained, under supported span is the exact setup for movement during a pour, because fluid concrete buoys hollow conduit and pushes hardest where support is missing. A conduit that rises or settles out of its row during the pour keeps that position after the concrete sets, and the missing half of the position sketch means the far end of the bank would be identified by guesswork after the grid disappears. The crew adds spacers to bring the span to the documented interval, fits the restraint the documents require, levels the top row, and completes the position sketch for both structures while every conduit is still visible.
The pour then proceeds with a worker assigned to watch the top row along the run. The row holds. After the concrete sets and the segment is proofed as the documents require, each conduit passes its mandrel, and the record handed over shows every position at both ends with its proofing result.
The schedule lost less than an hour. The alternative was a bank with a displaced conduit locked in concrete and a record finished from memory, discovered months later by a crew trying to pull cable through a position that no cable could pass.
The rule to carry is simple: a duct bank is proven and recorded while it is still visible, and a pour waits for support, restraint, and a complete position record instead of covering a span that nobody can verify.
What Can Go Wrong?
Floating during the pour. An unrestrained bank, or a span with spacers too far apart, rises in fluid concrete or flowable fill because the hollow conduits and plastic spacers are far lighter than the material around them. The bank loses cover and alignment, and conduits can end at wrong elevations at the structure entries.
Shifting sideways during placement. Concrete placed from one side, or fill flowing unevenly, pushes the assembled grid sideways in the trench. Conduits arrive at the structure face offset from their entries, with added bends at the wall and positions that disagree with the record.
Sagging between spacers. A long unsupported span bows under its own weight and the weight of material above it. The bow becomes a low spot in the hardened bank, adds pulling friction along the run, and can collect water inside the conduit at the sag.
Crossed conduits inside the bank. Two conduits that swap places between structures present reversed positions at the far end. Records drawn from one end misidentify both conduits at the other, and later work can act on the wrong cable with confidence in a wrong map.
Missing or collapsed spacers. A spacer left out, cracked, or displaced during assembly lets conduits touch or rest on each other. Encasement cannot flow into a contact point, so the finished bank holds a void and two conduits with no separation at that spot.
Concrete entering an uncapped conduit. An open conduit end at a structure or a damaged cap lets fluid concrete, soil, or debris enter during the pour. The conduit hardens with an obstruction inside it, and proofing after the pour finds a blocked position that cleaning cannot always clear.
Skipped proofing. A bank accepted on appearance alone can carry a flattened, oval, or blocked conduit that no one discovers until a cable pull fails on a later job. The repair then belongs to an owner with a due date instead of a builder with an open contract.
A position record finished from memory. A sketch completed after cover, or copied from the design drawing without field verification, records the bank somebody intended to build. Crossings, substitutions, and pour movement make the field bank different from the intended bank, and the record misleads every later crew.
Wrong material placed as encasement. Fill or concrete placed to a mix, depth, or method outside the project documents can leave the bank under protected or can damage conduits during placement. The design states the material, and a substitution belongs in the project approval process, recorded before placement.
Treating a bank face as proof of the segment. Clean, round openings at both structures say nothing about a sag, a crossing, or a crush at midspan. Only proofing per position and a record built before cover describe the buried segment honestly.
What Should Someone Notice in the Field?
- Count the conduits in the grid and compare count, sizes, and row and column pattern against the drawings and the position record.
- Check that spacers support every row at the interval the documents state, that each conduit sits seated in its spacer, and that no conduit touches another conduit or the trench floor.
- Confirm separation between conduits and around the grid matches the drawings, with open space for encasement to surround every conduit.
- Confirm restraint for the pour is fitted as the documents and the spacer manufacturer direct, and watch the top row for rise or drift while encasement is placed.
- Check conduit ends at both structures for caps or protection during construction, and for round, clear, clean openings in their recorded positions after the pour.
- Match every position at the structure face to the position record, and confirm the record states occupied and spare status and proofing results per position.
- Look for a conduit opening that sits out of line with its row, pinched oval, or offset from its recorded position, and record that position as suspect until proofing clears it.
- Photograph the assembled grid and the completed position sketch before cover, and photograph the bank face at each structure after the pour, naming positions in the record.
- Hold any pour over a span with missing spacers, missing restraint, sagging conduits, or an incomplete position record, and report the condition for a decision by the responsible supervisor instead of covering unverified work.
- Know the boundary: recognizing a duct bank, counting and identifying conduit positions, reading a position record, and reporting condition are tasks covered by this lesson. Designing a bank, setting cover or separation values, directing a concrete pour, entering a manhole under a confined space program, and working in an open trench under an excavation program belong to qualified people under the project documents and their training. Reading this lesson qualifies no one for that work, and no one should enter a trench or a structure, or join a pour, beyond their assignment, training, and authorization.
Key Terms
Duct bank: An arrangement of multiple conduits installed together in one trench as a single structure, held in a fixed pattern by spacers and commonly encased in concrete or specified fill, running between structures.
Spacer: A nonmetallic support that holds conduits at uniform horizontal and vertical separation and in alignment inside a duct bank before and during encasement.
Encasement: The material placed around an assembled group of conduits to lock the pattern, spread loads, and protect the conduits as one structure, commonly concrete where the design specifies it.
Separation: The clear distance maintained between one conduit and the next, and between the outer conduits and the edge of the encasement, as set by the project drawings and specifications.
Position: The named place of one conduit in the bank grid, by row and place across the width, used to identify the same conduit at both structures.
Spare conduit: An empty conduit built into a bank for a future cable, kept open, proven, capped, and identified by position in the record.
Position record: The drawing and notes that name every conduit position in a bank, state occupied and spare status per position, and match each position at one structure to the same position at the next structure.
Mandrel: A sized slug or cylinder pulled through a conduit to prove the conduit is open, round enough, and free of obstruction along its full length.
Proofing: The act of pulling a mandrel through each conduit and recording the result per position, also called mandreling in utility standards.
Cover: The distance from finished grade down to the top of a buried bank or its encasement, set for a job by the governing code, owner standard, or project drawings that apply to that work.
Check Your Understanding
- What turns a group of conduits in one trench into a duct bank?
Answer: A fixed pattern held by spacers and locked in place by encasement or specified fill, so the group acts as one structure between structures. A loose bundle with no fixed pattern and no material holding a pattern is direct buried conduit.
- Why does an assembled duct bank need restraint during a concrete pour?
Answer: Hollow plastic conduits and plastic spacers are far lighter, volume for volume, than fluid concrete or flowable fill. Patent literature for hold down systems states that an unrestrained bank may move and will float when concrete is poured into the trench. Restraint holds each conduit in its assigned position until the encasement sets.
- A position record shows a conduit as the top left position at one handhole. What must be true at the far handhole, and which published checklist states that check?
Answer: The same physical conduit must appear at the same level and in the same position at the far structure. The PakTechPoint telecom duct bank checklist states that corresponding conduits at conduit entrances in opposite ends of manholes shall be at the same level and in the same position with respect to the side walls.
- In the From the Field scenario, why did the inspector hold the pour at the middle span, and what three corrections did the crew complete before the pour proceeded?
Answer: The span had a spacer interval well past the documented interval, a sagging and unrestrained top row, and a position sketch finished at only one structure. Pouring would have covered an under supported span that fluid concrete could move, and the far end positions would have been identified by guesswork. The crew added spacers to the documented interval, fitted the required restraint and leveled the top row, and completed the position sketch for both structures while the grid was still visible.
- A finished bank shows clean, round openings at both structures. Why does that sight alone fail to prove the segment, and what proof completes the picture?
Answer: Structure faces show only the ends of each conduit. A sag, a crossing, a crush, or a blockage at midspan stays hidden behind clean openings. Mandrel proofing per position, where the documents require it, proves each conduit open and round enough along its full length, and a position record built before cover proves which conduit is which.
Lesson Takeaway
A duct bank is a promise made in an open trench. After this lesson, an assembled grid reads as a set of verifiable claims: every conduit supported, separated, restrained, and recorded in a named position that means the same thing at both structures. A reader who sees a bank that way protects the only moment when the work can still be corrected cheaply, and refuses to let a pour cover a span that nobody has proven.
Sources and Technical References
Fiber Optic Association, The FOA Reference for Fiber Optics, Outside Plant Construction, Underground Construction. Covers spacers used when placing multiple ducts in a trench, spacers preventing ducts from twisting over and around each other, straight alignment reducing cable jetting and pulling tensions, concrete encasement discussion, end caps at manholes and handholes, and Dig Once extra conduit practice: https://www.thefoa.org/tech/ref/OSP_Construction/Underground_Construction.html
Heldenfels Enterprises, What Is a Duct Bank? Complete Guide to Concrete-Encased Conduit. Covers conduits held in precise position by plastic spacers and completely surrounded by concrete as a single rigid structure, the three elements of conduits, spacers, and concrete envelope, and concrete distributing crushing loads from soil, traffic, and heavy equipment: https://heldenfels.com/what-is-a-duct-bank/
Heldenfels Enterprises, How Deep Should an Underground Duct Bank Be? Cover Requirements Guide. Covers cover as the distance from finished grade to the top of the conduit or encasement, NEC Table 300.5 and Table 300.50 as the governing references by voltage, rebar tying the encasement into a beam that spans soft spots and resists point loads, and the caution that depth, spacing, and voltage requirements depend on the code edition and utility design standards: https://heldenfels.com/underground-duct-bank-burial-depth-cover-requirements/
Muller EC, Duct Bank: What It Is, How It Works and Specs. Covers a duct bank as a group of underground conduits, usually encased in concrete, protecting electrical and communications cables, spare conduits allowing later cable pulls without digging, and a duct bank as an engineered, spacer aligned system distinct from a simple trench: https://www.mullerec.com/utilities/what-are-duct-banks-and-how-do-they-work/
Underground Devices, Inc., Guide Specification, Wunpeece Duct Spacer. Covers high impact polystyrene Wunpeece spacers maintaining horizontal and vertical separation, concrete encasement of at least three inches at the top and bottom and two inches on each side in that guide specification, spacers interlocked horizontally only and staggered along the run, and an interval of three or four spacers per twenty feet typically specified with four per twenty feet the common choice in that specification: https://powerplantsupplyco.com/ppsco-content/uploads/2017/03/Wunpeece-Duct-Spacers-Guide-Spec.pdf
Laird Plastics, Duct Bank Spacers Guide. Covers a duct bank spacer as a nonmetallic support maintaining uniform horizontal and vertical separation between conduits inside a concrete encased duct bank, spacers placed at intervals along the trench, typical spacer intervals of four to seven feet with closer spacing for larger conduits, deeper trenches, or unstable soil, and direction to follow project specifications and engineering direction: https://lairdplastics.com/resources/duct-bank-spacers-guide/
Maveric Contractors, Duct Bank Construction for Data Centres. Covers a duct bank as a group of conduits arranged in rows and columns and encased in concrete or surrounded by engineered backfill, each conduit as a dedicated pathway, and concrete encasement or engineered backfill placed around the conduits followed by compacted backfill and marker tape: https://www.mavericcontractors.com/blog/data-centre-duct-bank-purpose-design-construction
Seattle City Light, Construction Standard U2-11.40, Mandreling and Cleaning of Ducts and Conduits. Covers testing each duct run and conduit for obstructions or flattening by hand pulling a proofing mandrel after concrete has been poured or the trench backfilled, replacement of a section where an obstruction is found, and pull tape left in each conduit after cleaning and mandreling under that standard: https://web8.seattle.gov/city-light-engineering-standards/Home/GetPDF?libId=ConstructionStandards&searchForfileName=U2-11.40-NDK-40F2023.11.14.pdf
PakTechPoint, Duct Bank Fabrication, Installation Checklist and Mandrel Test. Covers verification that corresponding conduits at conduit entrances in opposite ends of manholes are at the same level and in the same position, spacer separation verification for concrete encased sections, encasement verification, and mandrel testing of each new conduit before and after concrete encasement in that checklist: https://paktechpoint.com/duct-bank-fabrication-installation-checklist-and-mandrel-test/
Law Insider, Mandrelling Sample Clauses. Covers specification language for a mandrel test after a duct bank is assembled and before concrete is poured, a second mandrel test after concrete has set drawn through each conduit with the inspector present, and a mandrel diameter set a stated amount smaller than the inside diameter of the conduit: https://www.lawinsider.com/clause/mandrelling
United States Patent 10,823,310, Method and Apparatus for Securing a Duct Bank via Hold-Down Bars, as published by Justia Patents. Covers duct banks floating or moving when a trench is backfilled with concrete or flowable fill, conduits and spacers with a specific gravity far less than concrete or flowable fill, an unrestrained bank floating during the pour, and hold down bars secured across the top of the bank as one restraint method: https://patents.justia.com/patent/10823310
Previous lesson: Lesson 146: What Is Microduct? |
Back to Level 8 hub |
Next lesson: Lesson 148: What Is Direct-Buried Construction?