Introduction
A site walk is a slow, systematic look at the ground where work is planned, done with the plan in hand, to find the conditions that will help or hinder the build. Lesson 113 covered what a preconstruction walk is and how it is run. This lesson covers what the eyes are actually searching for once the walk starts.
The search matters because a plan shows intent on paper, while the field shows what is really there. A trained scan catches mismatches between print and field early, when a note, a photo, and a question cost little, and it leaves a record the designer, the permit holder, and the crew can all use.
What This Lesson Gives You
- Run a repeatable scan that covers ahead, at your feet, below the surface by clues, above ground, and behind you for access.
- Read surface signs that point to underground utilities, even where no paint or flags are present.
- Judge whether equipment, material, and crews can get in, set up, work, and get out at each part of the route.
- Spot ground, drainage, traffic, and restoration conditions that change how or whether the plan can be built as drawn.
- Record a mismatch between the print and the field with a photo and a note clear enough for someone else to act on.
Start With the Basics
Think about proofreading a letter before it is mailed. A good proofreader does a first pass for spelling, a second pass for names and numbers, and a third pass reading backward so familiar words do not hide errors. Each pass looks for a different kind of problem, so nothing depends on one quick glance.
A site walk works the same way. One pass looks far ahead for crossings and traffic. One pass looks down for surface clues and ground condition. One pass looks up for overhead lines and clearances, and one pass looks back at how the crew and the truck arrived, because that path is also the way out. A systematic scan is a fixed order of looking that covers the same ground the same way every time, so the result depends on the method and the record, and the method can be taught, checked, and repeated by the next person.
What Is It?
A site walk search is the detailed observation work inside any site walk. The walker compares three sources at once: the plan set, the permits and limits shown on the documents, and the physical site itself. Where the three agree, the walker confirms the agreement. Where they disagree, the walker records the disagreement without redesigning the job on the spot.
Key terms for the search:
- Print means the plan drawings and details for the job, including route, structure locations, and notes. Field crews often call the set the prints.
- Right of way is land set aside for public or utility use, such as a road corridor. Work inside a right of way follows the permit and the rules of the agency that controls that corridor.
- Easement is a recorded legal right to use a defined strip or area of land owned by someone else for a stated purpose. The document for the parcel sets the rights and limits for that parcel.
- Locate marks are paint lines and flags placed on the ground to show the approximate horizontal position of underground facilities, using the American Public Works Association color code. Marks show approximate position. Marks do not show depth, and a mark is not a guarantee that nothing else is buried nearby.
- Surface encumbrance is anything on the surface that could create a hazard or block the work, such as a pole, a sign, stored material, a tree, or a structure near the excavation. Federal excavation rules require that surface encumbrances located so as to create a hazard to employees be removed or supported as necessary to safeguard employees.
- Constructability means a design can be built with the access, space, methods, and sequence that the real site allows. Federal Highway Administration constructability review practice treats buildable, cost effective, biddable, and maintainable as linked tests, and includes checks for access, permits, right of way limits, and whether permitted areas give enough work room.
The search covers eight families of conditions:
- Underground utility clues at the surface.
- Access and setup room for people, equipment, and material.
- Ground condition and drainage.
- Crossings, including roads, driveways, rail, water, and other utilities.
- Structures and restoration surfaces.
- Traffic, pedestrians, and public movement through or around the site.
- Environmental and permit flags visible in the field.
- Photo and record discipline, plus mismatches between print and field.
Framing note for the whole lesson: the detailed lists in this lesson are field practice for noticing and recording. A list in this lesson does not create a legal requirement. Requirements come from the law, the permit, the easement, the owner standard, and the project documents for that job.
What Does It Look Like?
A good search has a visible order. A person watching the walker can tell which part of the scan is happening.
Ahead. The walker looks down the route to the next structure, crossing, or change in surface. Long views show road crossings, driveway density, slope changes, standing water, and places where the route narrows. The walker notes where traffic comes from and where a work zone would push vehicles and people.
At your feet. The walker looks down at the exact line of the proposed work. The ground itself carries information:
- Paint, flags, and stakes from a locate, with colors and initials that name the facility owner.
- Cuts, patches, and trench lines in pavement or soil that show earlier excavation.
- Settled or heaved strips that follow a buried line.
- Valve boxes, meter boxes, cleanouts, and small lids that sit in line with each other.
- Bare soil, gravel, grass, concrete, and asphalt changes that mark property work or utility work done at different times.
Below the surface, by clues. The walker cannot see buried plant. The walker reads evidence for it:
- A row of pedestals, cabinets, handholes, or poles that implies a line connecting them.
- A manhole, a storm inlet, and a grate pattern that implies storm or sewer lines running between them.
- Trench settlement, patch lines, and locate marks that agree with each other.
- Records that disagree with the surface, such as a plan showing a line where no surface feature supports it.
ASCE 38 is the American Society of Civil Engineers standard guideline for investigating and documenting existing utilities. It grades utility information by quality level, a label that says how the information was obtained. Level D comes from records alone. Level C adds a survey of visible surface features correlated with the records. Level B uses appropriate surface geophysical methods to determine the existence and approximate horizontal position of a utility. That step is called designating. Level A exposes the utility and measures it directly. A site walk observes the same kind of evidence that sits at the low end of that scale: records, and visible surface features seen in the field. Observing features on a walk is not the same as a surveyed and correlated Quality Level C product, and the walk by itself does not raise the quality level of the data. The walk can show that higher level investigation is needed at a crossing.
Above ground. The walker looks up and out:
- Overhead electric and communication lines, poles, guys, and anchors near the route.
- Tree canopy, signs, and building overhangs that limit equipment height or swing.
- Existing structures, fences, walls, and gates that shape where work can happen.
Behind, for access. The walker turns around and judges the arrival path as a work path. A route that a person can walk may still fail for a drill, a reel trailer, a vacuum truck, or a splice vehicle. Width, turning room, surface strength, grade, and gate openings all belong in the record.

What Does It Do?
The search turns a general impression into specific, usable information. Each family of observations feeds a decision that someone must make before or during construction.
Utility clues reduce surprise underground. Federal rules for excavation require that the estimated location of utility installations that may reasonably be expected to be encountered be determined before an excavation is opened, and that utility companies or owners be contacted and asked to establish locations before actual excavation starts. A walk that records pedestals, lids, marks, patches, and mismatches gives the locate request and the design review better starting information. Common Ground Alliance best practice adds a visual inspection during locating and the use of on site records, plus correction of records when a locator finds an error or omission. The walk supports that system. The walk never replaces a locate ticket, a designation, or exposure where the project requires exposure.
Access observations test the method. A bore needs entry and exit room, a place for the drill, a place for mud handling where the method uses drilling fluid, and room to handle rods and product. Trenching needs room for excavation, spoil, shoring or sloping where required, and restoration material. Aerial work needs pole access and a safe setup for the vehicle and lift. The search records whether that room exists on the ground shown in the permit and the easement, and the search flags where the only workable room sits outside those limits.
Ground and drainage observations test sequence and timing. Soil at the surface, rock outcrops, wet areas, ditch flow, culverts, and low spots hint at what excavation and boring will meet and where water will go when the ground is opened. The walk does not classify soil for excavation safety. Soil classification for protective systems belongs to a competent person. Under the federal excavation rules, a competent person is someone who can identify existing and predictable hazards in the surroundings or working conditions and who has the authority to take prompt corrective action to remove those hazards. Appendix A to the excavation rules requires that each soil deposit be classified by a competent person, using at least one visual test and at least one manual test. The walk records visible conditions and photos so that qualified people can plan.
Crossing observations protect the highest risk points. Roads, rail corridors, waterways, driveways, and other utilities concentrate permits, owners, and methods at one spot. The search confirms the crossing exists as drawn, measures nothing by guessing, and records approaches, surfaces, and visible controls on each side.
Structure and restoration observations price the finish. Every surface the work crosses must be restored to the condition the permit, the easement, and the owner standard require. Concrete drives, pavers, retaining walls, irrigation, landscaping, fences, and specialty surfaces all change labor, material, and landowner impact. Photographing them before work starts protects the crew, the owner, and the landowner when questions come later.
Traffic and pedestrian observations shape the work zone. The Manual on Uniform Traffic Control Devices is the national standard for traffic control devices. Its Standard in Section 6D.01 states that the needs and control of all road users through a temporary traffic control zone shall be an essential part of highway construction, utility work, maintenance operations, and traffic incident management. Its supporting text adds that pedestrians affected by the zone need a clearly delineated and usable travel path. MUTCD guidance adds that pedestrians should not be led into conflicts with vehicles, equipment, and operations, and that pedestrians should be provided with a convenient and accessible path that replicates, as nearly as practical, the most desirable characteristics of the existing sidewalk or footpath. A walk that records sidewalks, crosswalks, school and bus stops, driveways, mail delivery, and business access gives the traffic control plan real inputs instead of assumptions.
Environmental and permit flags stop work in the wrong place. Wet areas, protected trees, marked boundaries, erosion controls already in place, and posted permit conditions can limit where equipment may travel and where soil may be placed. The walker records visible flags, signs, fencing, and boundaries, and reports them. The walker does not decide permit compliance from a glance. The permit documents and the responsible authority decide.
Photo and record discipline makes the walk count. A finding that lives only in memory fades and cannot be checked. A finding tied to a station, an address, a structure number, a compass direction, and a photo can be priced, designed around, permitted, and verified later. Federal construction inspection guidance treats advance preparation, data gathering, the physical review, evaluation, and written reporting as linked steps. The report and the photos are part of the work, and the walk is incomplete without them.
Where Does It Fit?
The search fits inside every walk in the course, and the emphasis changes with the stage.
At route review and design, the search tests whether the drawn line can be built and where the plan needs correction or higher level utility investigation before design is finished.
At the preconstruction walk from Lesson 113, the search supplies the detailed field content for the joint review with the owner, the designer, and the contractor. Agreements reached there should point back to specific recorded observations.
During construction, a shorter version of the same scan runs at each new segment, each crossing, and each structure location before work starts there. Conditions change after rain, after other trades work, and after locates expire or marks are disturbed.
At restoration and turnover, the same eyes run in reverse. The walker compares finished surfaces and structure positions against the prework photos and the record, and lists exceptions while correction is still part of the current job.
What Is at Stake
Safety. A missed overhead line, a missed surface encumbrance, or a missed sign of a buried facility can put a crew in contact with a hazard that was visible before work began. Federal excavation rules place related duties at different points in the job. Surface encumbrances and the location of underground installations are handled before an excavation opens. Access and egress and the protection of exposed installations apply while the excavation is open and in use. Finding a hazard on a walk is cheap. Finding the same hazard with equipment is not.
Utility damage. A line shown in the wrong place on the print, with no surface clue checked, invites a strike. Damage can cut service, injure people, trigger regulatory reporting, and stop the job. The quality level idea from ASCE 38 makes the stake plain: decisions made on records alone carry records alone reliability, and crossings deserve data that matches the risk.
Access failure after mobilization. A crew, a drill, and a reel on site with no legal or physical room to set up burn a day and damage credibility with the owner and the landowner. The cost is the idle spread plus the redesign and the remobilization.
Water and ground surprise. Unrecorded low ground, ditch flow, and wet soil change excavation support, bore fluid handling, spoil placement, and restoration. Water moves on its own schedule, and a site that was dry during design can carry flow during construction.
Public impact and permit risk. A work zone that blocks a sidewalk with no usable alternate path, blocks a driveway with no plan, or tracks soil into a protected area can draw complaints, stop work orders, and permit consequences. The traffic and permit observations from the walk are the early warning for those outcomes.
Restoration disputes. Without prework photos of drives, walks, walls, and landscaping, every crack and stain near the route becomes an argument. Dated, located photos settle most of those arguments before they grow.
Records trust. Mismatches left unrecorded teach the next crew that the print cannot be trusted anywhere. Mismatches recorded and corrected teach the opposite, and the correction helps every later phase, including future maintenance access from Lesson 110.
What Does Good Look Like?
- The walker follows a fixed scan order and can name which pass produced each note.
- Every structure location on the print is visited, photographed, and either confirmed or listed as a mismatch with a reason.
- Locate marks, surface features, and plan lines are compared at each crossing, and disagreements are written down at the crossing itself.
- Access is judged for the actual equipment for the method, including entry, exit, turning, and the way out, inside the permitted and easement limits.
- Ground, drainage, and restoration surfaces are photographed before any work disturbs them, with a landmark or address in the frame.
- Sidewalks, crosswalks, driveways, and business or residence access points along the work area are listed for the traffic control plan.
- Permit boundaries, flagged areas, and posted conditions seen in the field are recorded word for word where wording matters, and photographed.
- Notes use station, address, or structure references that let a stranger return to the exact spot.
- No finding is solved by redrawing the job in the field. Findings are recorded, flagged, and routed to the person who owns the decision.
From the Field
Picture a two person walk team checking a short arterial crossing for a planned bore. The print shows the bore crossing under the road between two handholes, with a storm inlet drawn on the near corner and a water valve box drawn in the parkway on the far side. The team starts with the ahead pass, then works down, up, and back, in their usual order.
On the near corner, the inlet sits where the print shows it. At their feet, fresh locate paint crosses the parkway in several colors, and the paint lines agree with the pedestals and lids in a row along the back of the sidewalk. The team photographs the inlet, the paint, and the row of surface features, and notes the agreement.
On the far side, the picture changes. The valve box on the print is not in the parkway. A wide, newer concrete driveway apron covers the parkway area where the print places the valve, and a clean pavement patch runs across the apron toward the road. No valve lid shows through the new concrete, and no locate paint marks a line under the apron. A mailbox and a low retaining wall also narrow the flat area where the exit pit and the drill setup were drawn.
The team does not move the pit on the print, does not guess where the valve sits under the concrete, and does not assume the patch is unrelated. The lead walker photographs the apron from both directions with the road name sign in one frame, photographs the patch line and the wall, and writes a mismatch note tied to the far handhole station. The note states what the print shows, what the field shows, and what is missing: no visible valve box, no marks across the apron, and reduced setup room at the drawn exit.
Back at the office, the note goes to the designer and the locate coordinator the same day. The crossing gets a fresh locate request covering the apron area and a higher level utility investigation at the conflict point before any bore is scheduled there. The setup location is reconsidered through the design and permit process, with the wall and driveway treated as real limits. The bore day is planned after those answers arrive, so the crew arrives to a crossing that has been investigated instead of a surprise under fresh concrete.
The rule to carry is simple: when the print and the field disagree, record the disagreement in place, with photos and a location reference, and route it for a decision. Never smooth over a mismatch by guessing in the field, and never let a scheduled workday be the investigation.
What Can Go Wrong?
Glance walking. The walker strolls the route, sees a tidy street, and reports no problems. Crossings, aprons, walls, and buried clues that needed a deliberate pass go unrecorded, and the crew finds them at production speed.
Trusting paint alone. Locate marks show approximate horizontal position for the facilities that were located, within the ticket scope and dates. Paint can be missing for private facilities, for facilities outside the ticket area, and for lines no surface feature reveals. Treating paint as a complete map invites a strike on the unmarked line.
Trusting the print alone. Records alone sit at the lowest ASCE 38 quality level. A plan line with no surface support at a crossing is a question, and building on it as a certainty transfers records error into the ground.
Solving in the field. A walker who shifts a pit, moves a handhole, or reroutes a line by verbal instruction creates unpermitted, unrecorded work. The next crew, the inspector, and the as built all inherit a site that matches no document.
Access judged by eye for a person, not for the method. A person fits through a gate that a drill cannot pass, and a lawn that carries a person can rut or fail under a loaded trailer. Judging access for the wrong user produces a mobilization that cannot set up.
Drainage ignored on a dry day. Ditches, culverts, and low crossings tell where water travels when it rains. Skipping them because the walk day is dry leaves excavation, bore pits, and spoil exposed to the next storm.
Photos with no reference. Close photos with no address, station, structure, or landmark cannot be matched to a place later. Restoration and mismatch claims built on them collapse for lack of proof of location.
Traffic and pedestrians treated as someone else job. A route that ignores sidewalks, crosswalks, bus stops, and driveway access hands the traffic control planner a blank sheet. The resulting work zone then improvises around the public, and improvisation is where complaints and incidents start.
What Should Someone Notice in the Field?
- Start with the ahead pass: next crossing, next structure, slope, traffic sources, and where the route narrows.
- Read at your feet: locate paint and flags, patches, trench lines, settlement, valve and meter boxes, cleanouts, and small lids in a row.
- Correlate below surface clues: rows of pedestals, cabinets, handholes, poles, manholes, and inlets, and note where the pattern breaks.
- Look above ground: overhead lines, poles, guys and anchors, canopy, signs, and overhangs that limit equipment.
- Turn around and judge access for the real method and equipment, including entry, setup, turning, material handling, and exit, inside permit and easement limits.
- Record ground and drainage: soil at the surface, rock, wet areas, ditches, culverts, low spots, and where water will go when ground is opened.
- List every crossing separately: road, driveway, rail, water, and other utilities, with surface condition and visible controls on each side.
- Photograph structures and restoration surfaces before disturbance: concrete, pavers, walls, fences, gates, irrigation heads where visible, and landscaping.
- Note traffic and public movement: sidewalks, crosswalks, bike lanes where present, school and bus stops, mailboxes, and business and residence access.
- Copy permit and boundary information seen in the field: flagged limits, posted conditions, protected trees or areas, and existing erosion controls.
- Compare print to field at each structure and crossing, and write each mismatch at the spot, with a photo and a station, address, or structure reference.
- Know the boundary: a site walk is observation and recording from the surface. Do not enter confined spaces, do not enter trenches or excavations to inspect them, and do not enter energized areas or open energized equipment. Report hazards and mismatches to the qualified people who own those decisions. Reading this lesson qualifies no one for excavation, confined space, electrical, or traffic control work.
Key Terms
Site walk: A slow, systematic look at planned work ground with the plan in hand, to find conditions that help or hinder the build.
Systematic scan: A fixed order of looking that covers ahead, at the feet, below the surface by clues, above ground, and behind for access, the same way every time.
Print: The plan drawings and details for the job, including route, structures, and notes.
Locate marks: Paint and flags showing the approximate horizontal position of underground facilities under the APWA color code. Marks do not show depth.
Surface encumbrance: Anything on the surface that could create a hazard or block work near the site, such as poles, signs, stored material, or structures.
Constructability: Whether a design can be built with the access, space, methods, and sequence the real site allows.
Quality level: In ASCE 38, a label for how utility information was obtained, from records alone at Level D to direct exposure and measurement at Level A.
Competent person: A person who can identify existing and predictable hazards in the surroundings or working conditions and who has the authority to take prompt corrective action to remove them. For excavation work, the competent person performs required inspections and classifies soil by the test methods the rules require.
Right of way: Land set aside for public or utility use, such as a road corridor, where work follows the controlling agency permit.
Easement: A recorded legal right to use a defined area of land owned by someone else for a stated purpose, with terms set by that document.
Temporary traffic control: The signs, devices, and layout that guide all road users safely through or around a work zone, covered in Part 6 of the MUTCD.
Mismatch: A recorded disagreement between what the print, permit, or record shows and what the field shows at the same place.
Check Your Understanding
- Name the five directions of the systematic scan and give one thing each direction catches that the others can miss.
Answer: Ahead catches crossings, narrowing, slope, and traffic sources down the route. At the feet catches paint, patches, settlement, and small lids on the work line itself. Below the surface by clues catches implied lines from rows of surface features and breaks in that pattern. Above ground catches overhead lines, guys, canopy, and overhangs that limit equipment. Behind catches whether the arrival path works for the real equipment, including turning and the way out.
- A print shows a water line crossing the bore path, and no paint, no valve box, and no surface feature supports that line at the crossing. Using ASCE 38 language, how should the walker treat the print line, and what should the walker do?
Answer: Treat it as records level information, Quality Level D, which carries the lowest reliability. Record the lack of surface support as a mismatch at the crossing, photograph the area with a location reference, and route it for designation or higher level investigation before construction relies on it. Do not treat the line as confirmed, and do not invent a new position in the field.
- In the From the Field scenario, what did the team find on the far side of the crossing, and what three things did the team refuse to do?
Answer: The team found a newer concrete driveway apron covering the area where the print placed a valve box, a pavement patch crossing the apron, no visible valve lid, no locate paint across the apron, and a mailbox and retaining wall narrowing the drawn exit setup area. The team refused to move the pit on the print, refused to guess the valve position under the concrete, and refused to assume the patch was unrelated. The team photographed, wrote a station tied mismatch note, and routed it for a fresh locate and higher level investigation.
- Why does the MUTCD discussion in this lesson belong in a site walk lesson, even though the walker does not design traffic control?
Answer: The MUTCD Standard in Section 6D.01 states that the needs and control of all road users through a temporary traffic control zone shall be an essential part of construction and utility work. Its supporting text adds that pedestrians need a clearly delineated and usable path that does not lead them into conflict with work or moving vehicles. The walk supplies the real inputs for that plan: sidewalks, crosswalks, driveways, bus stops, and access points. Without those observations, the plan is built on assumptions.
- A walker finds a flat, grassy spot that fits the drill perfectly, and the spot sits just outside the easement line shown on the print. What is the correct action?
Answer: Record the spot and the limit. Note that the workable room sits outside the easement shown, photograph the boundary evidence and the spot with a location reference, and route the conflict for a design, easement, or permit decision. Do not set up outside the authorized area on the strength of a field judgment, and do not redraw the job during the walk.
Lesson Takeaway
A plan tells a crew what someone intended. A systematic search tells the crew what the ground will actually allow, where the print and the field part company, and what must be answered before equipment arrives. After this lesson, a street stops looking like scenery. Paint, patches, lids in a row, a fresh apron, a narrow gate, and a dry ditch each read as information, and each one gets a photo, a note, and a place in the record.
Sources and Technical References
Federal Highway Administration, Constructability Review Checklist, on reviewing a design for whether it is buildable, cost effective, biddable, and maintainable, including checks for project access, permitted areas, permits, and right of way: https://highways.fhwa.dot.gov/media/49146
Federal Highway Administration, Construction Program Management and Inspection Guide, Chapter 4, on inspection and review as advance preparation, data gathering, the physical review, evaluation, and written reporting: https://www.fhwa.dot.gov/construction/cpmi0406.cfm
OSHA, 29 CFR 1926.651, Specific Excavation Requirements, on surface encumbrances in paragraph (a), determining estimated locations of underground installations and contacting owners before excavation in paragraph (b), and access and egress in paragraph (c), with the competent person definition at 29 CFR 1926.650(b) and soil classification in Appendix A to Subpart P: https://www.osha.gov/laws-regs/regulations/standardnumber/1926
Federal Highway Administration, Subsurface Utility Engineering, on ASCE/UESI/CI 38-22, Standard Guideline for Investigating and Documenting Existing Utilities, and its four quality levels, from Quality Level D based on existing records, to Quality Level C adding a survey of visible surface features correlated with records, to Quality Level B using surface geophysical methods to designate approximate horizontal position, to Quality Level A based on exposure and direct measurement: https://www.fhwa.dot.gov/programadmin/sueindex.cfm
Common Ground Alliance Best Practices, Chapter 3, Locating and Marking, on use of on site records, record corrections when errors are found, the APWA uniform color code, and visual inspection during locating. Chapter text verified in the Canadian Common Ground Alliance edition of the same best practices: https://www.info-ex.com/wp-content/uploads/2022/07/CCGA-Best-Practice-Manual-Version-4.0-chapter-3.pdf
Common Ground Alliance Best Practices, Chapter 4, Excavation, on notification, awareness of privately owned facilities that public locates may not mark, and visual inspection of the work area for indications of buried facilities. Chapter text verified in the Canadian Common Ground Alliance edition of the same best practices: https://www.info-ex.com/wp-content/uploads/2024/09/Chapter-4.CCGA-Best-Practices-Manual-Version-5.0.pdf
Federal Highway Administration, Manual on Uniform Traffic Control Devices, 11th Edition (December 2023), the current national standard adopted at 23 CFR 655.603, Part 6, Chapter 6D, Section 6D.01, Pedestrian and Worker Safety. Its Standard states that the needs and control of all road users through a temporary traffic control zone shall be an essential part of highway construction, utility work, maintenance operations, and traffic incident management, and its supporting text adds that pedestrians need a clearly delineated and usable travel path: https://www.ecfr.gov/api/renderer/v1/content/enhanced/2024-07-30/title-23?chapter=I&subchapter=G&part=655&subpart=F and Section 6D.01 text at https://mutcd.fhwa.dot.gov/HTM/2009/part6/part6d.htm
Graphic Brief 1
Graphic title: The Five Direction Scan
Main objects: A single walker figure standing at a handhole location on a short street segment, shown in plan view with a simple road, sidewalk, parkway, and a proposed route line. Five large viewing cones or arrows radiating from the walker position, each labeled for one scan direction. Small surface features placed where each direction looks: a crossing ahead, paint and a valve box at the feet, a dashed implied line below the surface, overhead lines above, and a drill vehicle behind on the access path.
Placement: Walker and handhole in the center of the board. Road running left to right across the lower third. Proposed route as a blue dashed line crossing the road. Ahead arrow pointing up the route toward the crossing. Feet zone as a tight circle around the walker. Below surface shown as a light cutaway strip under the route with a dashed utility line. Above shown at the top with pole and overhead lines. Behind arrow pointing down toward the vehicle at the bottom edge. Title in white space at the top. Key teaching point in white space at the bottom.
Labels: Ahead: crossing and traffic. At your feet: paint, patches, lids. Below, by clues: implied line. Above: overhead lines. Behind: access for equipment. Handhole. Proposed route.
Arrows and relationships: Five black arrows from the walker, one per direction, each ending at its feature group. Green check marks where print and field agree at the near handhole. Red question mark at the far side crossing where a dashed utility has no surface feature. Blue arrow from a small plan sheet beside the walker to the ground, showing constant comparison.
Important technical details: Locate paint shown as short colored dashes on the surface only, with no depth shown. The implied underground line stays dashed to show it is inferred from surface clues, and the line carries no depth label. Overhead lines stay above the pole tops. The vehicle sits on the road and driveway surface, outside the work line.
What not to show: No trench, no excavation, no worker below ground. No depth numbers, clearance numbers, or dimensions. No exposed utility shown as seen from the surface. No decoration, no extra buildings, no weather effects.
Key teaching point: One fixed scan order, ahead, at your feet, below by clues, above, and behind for access, catches what a single glance misses.
Graphic Brief 2
Graphic title: Print Versus Field at One Crossing
Main objects: A side by side comparison of the same road crossing in two panels. Left panel shows the crossing as the print draws it. Right panel shows the same crossing as the field presents it. Both panels show the road, the parkway, the proposed bore line, the far handhole, a valve box symbol, a driveway apron, a retaining wall, and a mailbox in consistent positions so differences stand out.
Placement: Two equal panels across the middle of the board, divided by a vertical line. Left panel header reads Print. Right panel header reads Field. A wide note strip runs under both panels for the record action. Title in white space at the top. Key teaching point in white space at the bottom.
Labels: Left panel: Valve box in parkway. Open setup area. Bore line as drawn. Far handhole. Right panel: New concrete apron over valve area. Pavement patch across apron. No paint across apron. Wall and mailbox narrow setup. Far handhole, confirmed. Note strip: Photo, station note, route for decision. No field redesign.
Arrows and relationships: Blue arrows on the left panel trace the bore line as drawn from handhole to handhole. Red circles on the right panel mark the three mismatches: the missing valve box, the unmarked patch, and the narrowed setup. A black arrow runs from the right panel down to the note strip, showing the mismatch becoming a record. A red X sits over a small pencil icon in the note strip, showing no redrawing in the field.
Important technical details: Both panels keep road width, handhole positions, and the wall base line in the same places, so only the surface evidence changes. The apron on the right fully covers the valve position from the left panel, and no lid outline shows through it. No depths, dimensions, or clearance numbers in either panel.
What not to show: No crew digging or boring. No exposed valve under the concrete shown as fact. No alternate pit location drawn as a solution. No decoration or extra labels.
Key teaching point: A mismatch is a record to route for a decision, never a problem to solve by guessing or redrawing during the walk.