Introduction
A jobsite read is a structured observation of a work area, done before construction starts, in which the reader walks and drives the full extent of the planned work, identifies the legal, physical, utility, access, and people conditions that affect the work, photographs and notes them in an organized record, compares them against the project prints and the locate marks, and reports questions and conflicts through the project process before ground is disturbed. The read uses observation, photographs, notes, and comparison only. It authorizes no digging, no entry into any structure, and no operation of any other utility’s equipment.
This lesson is the capstone of Level 2, Read the Physical Environment. Every earlier Level 2 lesson taught one part of the environment: legal lines, terrain, soil, water, drainage, road furniture, crossings, and the utility features that announce buried systems. This lesson assembles those separate readings into one repeatable sequence, five passes in a set order, that a reader can run on any block, lot, or rural stretch.
What This Lesson Gives You
- Run a complete site read in a set order: slow drive-by, walk on both sides, five passes, photograph and note as you go, compare, and escalate.
- Read surface features as evidence, naming what each pole, pedestal, meter, manhole, ditch, and mark announces about what is buried, allowed, or at risk.
- Compare the field, the prints, and the locate marks segment by segment, and record every disagreement exactly as found.
- Turn findings into a written questions and conflicts list, each item with a location, the conflicting sources, the risk of guessing, and the owner who must resolve it.
- State the limits of a read plainly: what observation can establish, what it can only flag, and which decisions belong to the designer, the locator, the surveyor, the utility owner, and the project lead.
Start With the Basics
Picture the morning before a fiber crew starts on a new street. The prints are in the truck. The locate paint is on the ground. The bore machine is still on the trailer. Nothing has been disturbed yet. That quiet hour is the most valuable hour on the whole job, because everything the street has to tell you is still visible and nothing has been covered, moved, or broken yet.
A beginner walks that street and sees houses, lawns, a road, and some colored paint. A trained reader walks the same street and sees a layered record:
- The curb line tells where the road drainage goes.
- A pink survey flag tells where someone measured.
- A green pedestal missing from the prints tells that a buried cable was placed after the prints were drawn, or that the prints missed it.
- A wet ditch in dry weather tells that water is moving where the drawing shows only grass.
- A driveway that drops steeply to the road tells where a bore pit will flood, where equipment will struggle to set up, and where restoration will be watched closely by the person who parks there every day.
None of that requires opening anything or digging anything. It requires a system, so you look at the same things, in the same order, every time, instead of relying on noticing only what happens to catch your eye.
Think of it the way a good home inspector works through a house before a sale. The inspector walks a set route, room by room and system by system, tests nothing apart, and writes down what the surfaces reveal about the hidden systems behind them: a stain maps to a leak, a patched wall maps to an old repair, a breaker panel maps to circuits the listing never mentioned. The inspector’s route keeps the inspection complete, and the written findings give the buyer decisions to make before money changes hands. A site read works the same way. The five passes are the route, the surface features are the stains and patches, and the questions list is the findings report the project acts on before machines change the street.
Three ideas carry the whole lesson:
- The surface is evidence. Poles, pedestals, meters, manholes, ditches, and marks each announce something you cannot see directly, about what is below and about what is allowed. Treat each one as a claim to check.
- No single source is complete. Prints can be old. Records can miss a facility placed recently. Locate marks are approximate. Your eyes can miss a buried lid. A good read compares at least three sources, the field itself, the prints, and the marks, and treats any disagreement between them as a finding. The Common Ground Alliance, the industry group that publishes damage prevention best practices and is called the CGA in this lesson, makes the same point in its visual inspection practice: a visual inspection during locating should check that plant shown on records matches the site, and should look for evidence of facilities that are not on record, such as poles, enclosures, pedestals, valves, meters, risers, and manholes.
- A question written down is the read doing its job. The read that ends with a short, precise list of conflicts for the designer, the locator, or the project lead to resolve before digging has succeeded, even if that list delays the start. The read that guesses past those conflicts has failed, even if the crew starts on time.
What Is It?
A jobsite read, also called a site read or a preconstruction walk in common practice, is the structured observation defined in the Introduction. Each part of that definition matters:
- Structured means the read follows a set sequence and a checklist. It is a working method, never a casual stroll.
- Observation means the reader looks, listens, and notes from the surface and from places the public and the project allow the reader to be. The reader enters no structures, opens no enclosures, moves no other utility’s property, and tests no soil or water by digging.
- Before construction starts means the read happens while findings can still change the plan, the route, the method, the schedule, or the locate, at low cost. After the bore starts, the same finding costs far more and may already be damage.
To use the read, you need its working words, each defined before it is built on:
- Prints, also called plans or construction drawings, are the project drawings that show the planned route, the existing features the designer knew about, the proposed handholes, ducts, and crossings, and the notes and limits that govern the work. Prints are a plan and a record of prior knowledge. Field conditions can differ from them, and the read exists partly to find where they do.
- Right-of-way is the strip of land reserved for a road and for utilities along that road. Public right-of-way is held for public use under the rules of the agency that controls the road, which may be a city, a county, or a state. Who controls the road, how wide the right-of-way is at a given address, and what work it allows are set by local records, plats, deeds, and agency rules. Those widths and limits vary and must be verified for the project in hand. No single width is universal.
- Easement is a legal right to use a defined part of another person’s land for a stated purpose, such as placing and maintaining utilities. A recorded utility easement states a location, a holder, and terms in the document that created it, and some recorded easements also state a width, while others do not. Easements can also arise by implication, necessity, or long use, so an easement may exist without a recorded document. The absence of a recorded document on a quick check is a question to escalate. It is never proof that no easement exists. A line on the prints labeled as an easement is a lead. The recorded document and, where needed, a survey are the proof.
- Property line is the legal boundary between parcels of land. Fences, hedges, mow lines, and driveway edges often sit near a property line, and they never prove it. Only a survey, plats, and recorded records prove a legal line. In a site read you record where fences and occupation lines sit and flag any place where the planned work depends on knowing the exact legal line.
- Locate mark is temporary paint, a flag, a stake, a whisker marker, or a combination of those, placed by a locator to show the approximate location of a buried facility. Marks follow the APWA Uniform Color Code. APWA is the American Public Works Association. In that code:
– White is proposed excavation. – Pink is temporary survey markings. – Red is electric. – Yellow is gas, oil, steam, petroleum, or gaseous materials. – Orange is communications, alarm, or signal lines. – Blue is potable water. – Purple is reclaimed water, irrigation, and slurry lines. – Green is sewers and drain lines.
Marks show an approximate center line. They show neither exact position nor depth, and depth is never proved by a mark at all.
- Locate ticket, also called an 811 ticket or a one call ticket, is the record created when an excavator contacts 811, the free national notification system in the United States, and asks member utilities to mark their facilities in a stated work area. State law sets who must contact 811, how far in advance, how long a ticket stays valid, and how the tolerance zone is defined and measured.
- Tolerance zone means the corridor around a buried facility where state rules require careful exposure methods, such as hand digging or vacuum excavation, and restrict mechanical digging until the exact location of the facility is determined. State law defines the zone and its width, and states measure it differently: from the facility itself, from the outside edge of the facility, or from the mark. The reader checks the definition in the rules for the state of the job. This lesson names no single width or measurement point as universal.
- Pedestal is a small above-ground enclosure, usually in a yard or in the right-of-way, that houses connections for communications or other distribution cables.
- Cabinet is a larger above-ground enclosure that houses equipment, power, or many connections.
- Manhole is a larger underground structure with a heavy cover at the surface that a person can enter under strict safety rules that this lesson does not teach or authorize.
- Handhole is a smaller underground enclosure with a lid at the surface that is reached from above and is not entered.
- Fire hydrant is a valved outlet on a pressurized water main that firefighters use.
- Gas meter set and water meter, covered fully in Lessons 39 and 40, are measuring assemblies that each announce a buried pressurized service to a property.
- Potholing is digging a small, careful hole, usually by hand or with vacuum equipment, to expose a buried facility and confirm its exact position at a specific point. Potholing is construction work done under the project plan and the locate rules. Noting that a crossing will need potholing is part of a site read. Doing the potholing is outside the read itself.
- Competent person, in the federal excavation rules of the Occupational Safety and Health Administration, called OSHA in this lesson, is a person who can identify existing and predictable hazards and who has authority to take prompt corrective action. OSHA requires that a competent person inspect excavations and that the estimated location of underground installations be determined before an excavation is opened. Naming the need for that inspection in your notes is proper. Claiming that role, or that qualification, from reading this lesson is not.
- Restoration is the work of returning disturbed surfaces, such as pavement, concrete, sod, gravel, and landscaping, to the condition and standard the permit, the contract, and the property owner require. A site read records the condition before disturbance, because restoration is judged against what was there before.
What Does It Look Like?
A good site read follows a sequence, done the same way on every job, so nothing depends on memory or mood. Adapt the paperwork to your project forms, and keep the order and the completeness.
Step one: the slow drive-by. Drive the full route in both directions if traffic and safety allow it, at a speed that lets you see, with a passenger noting if one is available, or stop in safe legal places to note what you saw. The drive-by answers the big shape questions:
- Where does the work start and end?
- How does traffic actually move?
- Where are the intersections, the school or business activity, the parked cars, and the narrow places?
- Where does the land rise, fall, or flatten?
- Where is water standing or flowing?
- Where will a truck and trailer, a bore machine, and a reel actually fit, and where will they clearly fail to fit?
Logging every pedestal from a moving vehicle is beyond the drive-by’s job. The drive-by builds the map in your head that the walk will fill in.
Step two: the walk, on both sides. Walk the work area on foot, on both sides of the road or route, for the full length of the work, plus a short distance beyond each end so tie-ins and crossings stay inside your notes. Walking both sides matters because many features hide from the opposite side. A pedestal behind a hedge, a culvert mouth under a driveway, a meter lid in tall grass, and a ditch that only shows its wet bottom from the low side are all walk findings, never drive-by findings. Walk facing traffic where road rules and safety practice require it, stay out of travel lanes, and stay off private property beyond the right-of-way and any permission the project holds. If you cannot legally or safely reach a place to observe it, note that limit as a finding instead of trespassing to close it.
On the walk, you work the five passes in order, even if you record them on one combined checklist.
Pass one: legal lines. Look for survey evidence and for the clues that surround it:
- Survey evidence: pink survey flags and paint, survey stakes, property corner markers, and monument boxes in the pavement.
- Right-of-way clues: the road, the curb or ditch line, sidewalks, utility corridors in a consistent line, fences set back in a pattern, and signs or posts the agency installed.
- Occupation lines: fences, walls, hedges, sheds, and landscaping that show how owners use the land. Note every place where occupation crosses or crowds the planned route.
Photograph any marker you will rely on, with enough context to find it again. Record what you did not find. If no survey evidence marks a line that the work depends on, that absence is a question for the list.
Pass two: ground and water. Read the terrain first, then the soil clues, then the water:
- Terrain: slopes, low spots, high spots, and places where the ground was clearly cut, filled, or leveled in the past, such as a flat pad in sloped ground or a sudden change in grass and soil color.
- Soil and rock clues at the surface: exposed rock, rock fragments in the ditch, gravel or sand patches, cracked or heaved pavement, and fresh or old trench lines where the surface sank or was patched in a long strip. Those clues suggest what digging and boring may meet. They prove neither soil type nor rock depth, which require the project geotechnical information and field verification the plan directs.
- Groundwater signs: wet soil in dry weather, standing water in ditches or low spots, sump or drainage discharge pipes, and areas of lush green growth in an otherwise dry corridor.
- Drainage as a system: where rain water enters, where it flows, and where it leaves. Follow ditches to culverts. A culvert is a pipe or box that carries drainage under a road, a driveway, or an embankment. Find both ends of each culvert on your route if you can do so safely from the surface, note its material and condition at the mouths, and note any mouth that is crushed, blocked, silted, or not found. Note ditches that are eroded, ditches that have been filled or piped, and driveway or road crossings where drainage will meet your pits and trenches.
- Vegetation as information: tree lines that may mean root zones and past clearing limits, stumps that mark removed trees over old routes, and protected or specimen trees the permit may name.
State no root protection distance and no soil classification as a fact from a surface glance. Record the clue and its location.
Pass three: road furniture. Read each built surface the work will cross, parallel, or restore:
- Curb and gutter as one system. Curb is the raised edge between pavement and the ground or sidewalk behind it. Gutter is the shaped channel at the edge of the pavement that carries water along the curb to inlets. Note where curb and gutter are present, absent, damaged, settled, or newly replaced, and where driveways cut through them.
- Sidewalks, panel by panel where your work crosses or parallels them: cracked, lifted, settled, or patched panels, and panels whose condition a resident will compare after restoration.
- Every driveway on the route: its surface material, its slope to the road, its width at the road, any culvert under it, and whether it is the only access to that property.
- Intersections, read fully: corner ramps, crosswalks, traffic signal cabinets and poles where present, stop signs, sight lines, and the heavy turning paths of trucks and buses that wear and load those corners.
- Bridges, observation only. Note the bridge, its approaches, guardrail, drainage scuppers or outlets you can see from allowed places, and any utility attached to or crossing near the structure that the prints show. Climbing on, entering, or attaching anything to a bridge is outside a read.
- Railroad crossings and corridors, observation only. Stay off the tracks and out of the railroad right-of-way, observe only from public places, and note the crossing, signals, and gates as a major constraint to escalate, because railroad work is governed by the railroad and its permits, on the railroad’s schedule.
Pass four: utility evidence. This is the longest pass. Work it feature by feature, and for each feature record what it is, where it is, what condition it is in, and what buried system it announces.
Start overhead:
- A utility pole is a vertical structure that carries overhead lines and equipment. Read each pole in order: what lines sit at each level, transformers, streetlights, guys and anchors, risers that take a line underground, and any pole tag or number you can read from the ground.
- Lines drop from poles to buildings and dive underground at risers. Each dive is a buried facility leaving that pole.
- Note poles that lean, are damaged, or sit in your planned pit or bore line.
Then work the ground-level enclosures:
- Find every pedestal and cabinet: its color, labeling you can read without opening it, its condition, whether it is locked, plumb, struck, or overgrown, and whether it appears on the prints.
- Find every manhole cover and handhole lid: its shape, its lid wording if any, whether it is flush, sunk, raised, cracked, paved over, or buried, and what system its wording and location suggest.
- Note sewer cleanouts, valve boxes and lids, storm inlets and grates, and irrigation boxes where you find them, naming them by what you observed and flagging any lid you cannot identify instead of guessing its system.
- Opening a manhole, handhole, pedestal, or cabinet belongs outside a site read unless your project role and authorization clearly cover that enclosure, and entering a manhole is never part of a read.
Then read the property services:
- At each lot, find the fire hydrant if one serves that stretch, the gas meter set, the water meter box, and the electric meter and service drop or riser. Each one announces a buried service crossing your route, as Lessons 38, 39, and 40 teach.
- Note any property with no visible meter or service evidence and treat that as a question, because an occupied building is served somehow.
Then read the marks themselves:
- Walk the paint and flags as a language. Name each color by the APWA code. Follow each color run from end to end.
- Note where a run starts, where it ends, where it crosses your planned route, where it fades, is paved over, or is missing where a surface feature says a facility should exist.
- Note white proposed excavation marks if your crew or another crew placed them, and pink survey marks, and keep those two meanings separate from utility colors in your notes.
- Note the locate ticket number, the date, and the responding utilities if the project paperwork gives them to you in the field, and note any facility the ticket lists as cleared with no marks, so the walk can confirm that the field shows no conflicting surface evidence for that facility.
Pass five: access and people. Read how the work will actually live on this street:
- Equipment access: gates, narrow drives, soft ground, steep grades, low overhead lines or tree canopy, and bridges or pavement that may limit loads. Those load and clearance limits are set by the agency, the structure, and the equipment maker, and must be verified rather than guessed from a glance.
- Setup room: where a bore machine, an excavator, a vacuum truck, and material can sit without blocking driveways, hydrants, mailboxes, or travel lanes beyond what the traffic control plan and permit allow.
- Traffic as it is: bus stops, school activity, delivery patterns, parked cars that will be in the bore line, and intersections where a lane closure will back traffic up quickly.
- Residents and businesses: front doors, fences with dogs, yards and plantings that owners clearly maintain with care, and businesses whose access or parking is their livelihood. Note any person who speaks with you during the walk. Be courteous, identify your project role truthfully, promise no dates, methods, or restoration results you do not control, and record concerns you hear as notes for the project lead, never as agreements you made.
- Restoration surfaces, in detail, because you will be judged on them: pavement age and patches, concrete panels, decorative drives, gravel, sod and seed areas, flower beds, and sprinkler heads you can see. Photograph preexisting damage and careful landscaping before anyone disturbs it.
Step three: photograph and note, as you go. A photo without a location is almost useless a week later. Tie each photo to an address, a station, a pole number, or a clear landmark by your project method, and keep the sequence in walk order. Note condition in words as well as pictures, because a photo may fail to show that a lid rocked underfoot, that soil was soggy, or that water was moving. Write notes in complete, plain language that a person who was not there can act on: what, where, which side of the road, how far from a named landmark, and why it matters to the work.
Step four: compare field against prints and marks. Do this comparison while you are still on site if you can, and complete it the same day. Lay the three sources side by side for each segment:
- Does every enclosure on the ground appear on the prints?
- Does every facility on the prints have field evidence or marks?
- Do the marks connect sensibly to the surface features, such as blue marks ending at a water meter box and orange marks running pedestal to pedestal?
- Does the planned route on the prints respect the legal lines, the drainage, and the access you just walked?
Mark each segment as matches, differs, or not enough information. Adjusting one source quietly in your notes to make it agree with another corrupts the record. Record the disagreement exactly as found.
Step five: list questions and conflicts, and escalate them. End the read with a written list. A feeling that the site is probably fine is not an ending. Each item names the location, the sources that conflict, the risk if the crew guesses, and who must resolve it: designer, locator, utility owner, surveyor, permitting agency, railroad, or project lead. Typical escalations include:
- A facility in the field that is missing from the prints.
- A facility on the prints with no field evidence and no marks.
- Marks that conflict with surface features.
- A legal line the work depends on that has no survey evidence.
- A culvert or drainage path the route will block or flood.
- No workable equipment access or setup area.
- Any damaged, leaking, or hazardous condition you observed.
Hand that list through the project process before digging. A site is ready to start only when the project, acting through its named roles, has resolved or planned around each item. The reader alone cannot clear that list.

What Does It Do?
A jobsite read does four jobs for a fiber project. It prevents damage, it makes the plan real, it prices and schedules the work honestly, and it creates the before record that protects everyone later.
For damage prevention, the read is the field half of a system that federal rules, state laws, standards, and best practices each govern in part. Federal OSHA excavation rules require that the estimated location of underground installations that may reasonably be expected to be encountered be determined before an excavation is opened, that utility companies or owners be contacted, and that the exact location be determined by safe and acceptable means as excavation approaches that location. State one call laws put that contact into the 811 ticket system, with state notice times, ticket validity, positive response, and tolerance zone rules. CGA best practices add the disciplines of visually inspecting the site against the records, preserving marks, verifying facilities at crossings, and white lining the proposed excavation when the site cannot be clearly and adequately identified on the locate ticket. A site read replaces none of those steps. It is how a crew discovers, early and cheaply, that one of those steps is missing, stale, or contradicted by the ground, while there is still time to fix it.
For planning, the read turns a line on paper into a method in a place. The prints may show a bore. The read shows that the bore entry sits in a ditch that carries water after every rain, that the exit sits in a driveway that is the only access to a house, and that a cabinet the prints missed occupies the planned handhole location. With those findings, the designer or project lead can move a pit, shift a handhole, choose a different method, order traffic control that fits the real intersection, or sequence the work so a business keeps its access. Without the read, the crew discovers the same facts with machines on site and the road already opened.
For honest pricing and scheduling, the read surfaces the slow parts before they become surprises: rock clues that suggest slower boring or different tooling, groundwater signs that suggest dewatering planning, long restoration runs, tight access that rules out the largest machine, and railroad, bridge, or permit constraints that run on another organization’s clock. A read can set neither a production rate nor a price. It can stop a plan from assuming an easy street that the walk just proved is hard.
For the record, the read creates dated, located, before photographs and notes. That record proves preexisting cracked sidewalks, leaning fences, flooded boxes, buried lids, and leaking services were found that way, routes later questions to the right segment, and gives restoration a target: the condition the site was in before your work. Projects that skip the before record end up paying for old damage or arguing about it with no evidence. Projects that keep it can show, lot by lot, what they found and what they left.
Where Does It Fit?
Level 2 built this read one feature at a time:
- Lessons 21, 22, and 23 taught the legal lines.
- Lessons 34, 35, 36, and 37 taught terrain, soil and rock, groundwater, and vegetation.
- Lessons 28, 29, 26, and 27 taught drainage, waterway crossings, ditches, and culverts.
- Lessons 24, 25, 33, 32, 30, and 31 taught curb and gutter, sidewalks, driveways, intersections, bridges, and railroads.
- Lessons 38, 39, 40, 41, 42, 43, and 44 taught hydrants, gas meters, water meters, pedestals, cabinets, manholes, and poles.
This lesson is where those separate readings become one pass over one real place, in the order the work will meet them.
In the project life, the site read sits between design and construction, and it feeds both. Upstream, design, utility records, as-built drawings, prior tickets, and subsurface utility engineering where the project commissions it give the reader leads to verify. The Fiber Optic Association, called the FOA in this lesson, covers underground outside plant construction in its reference material, including manholes and handholes, markers, and records, and it states that the contractor is responsible for locating all existing services, that mapping of underground services should be done during the design phase, and that the mapping should be double checked before digging. Downstream, the read feeds the final locate confirmation, the traffic control plan, the bore and excavation plan, the dewatering and erosion controls where they apply, the restoration plan, and the crew briefing. A finding that changes any of those downstream plans must travel through the project process, with the prints or the plan updated where the project requires it. A tailgate mention alone carries no finding anywhere.
In the highway and road picture, the Federal Highway Administration, called FHWA in this lesson, treats right-of-way, utility, and railroad coordination as work that must be coordinated with physical construction so it causes no unnecessary delay or cost, and federal rules for federal-aid projects address how utilities are accommodated in and relocated from highway right-of-way. Fiber jobs in this course usually run on local roads under local permits, so FHWA rules serve as background there and never as the permit for your street. The principle still holds at every scale. Legal lines, utilities, and access are coordinated before construction, or construction pays for the lack of coordination.
The read also fits inside the locate timeline. In the usual sequence, the project white lines or otherwise defines the proposed work area where state rules and CGA practice call for it, the excavator contacts 811 and receives a ticket, locators mark facilities and utilities give positive responses, and then the crew verifies in the field that responses and marks match the surface evidence. That verification is part of this read. If the walk happens before marks exist, it is a preliminary read, and the comparison step must be repeated once marks are down and before digging. A read done too early to check marks is useful, and it stays incomplete until that comparison runs.
What Is at Stake
Safety comes first. The most dangerous buried facilities on a residential street, pressurized gas and water and energized electric, all announce themselves at the surface to a reader who knows their signs: a gas meter set and yellow marks, a water meter box and blue marks, a pole riser and red marks. Missing those announcements leaves the facilities in the ground and removes only the warning. OSHA treats determining underground installations before opening an excavation as a basic requirement for that reason, and state damage prevention laws treat contacting 811 and respecting marks as legal duties. A site read that is rushed, partial, or done from the truck window weakens every protection that follows it.
The neighbors carry a stake too. The people on the street did not ask for this work. A crew that read the site knows which driveway cannot be blocked at school pickup time, which business cannot lose its parking on its busiest day without notice the project lead must give, which yard has a sprinkler system and plantings that took years to grow, and which sidewalk panel was already cracked. That knowledge, passed through the project lead who owns customer communication, is the difference between a project that a street tolerates and a project that a street fights, complains about, and remembers when the next permit is discussed.
Money and the schedule are at stake in the plainest way. Nearly every expensive construction surprise was visible at the surface the week before, to a reader with a system: the unmarked pedestal in the bore line, the culvert that turns the exit pit into a pond, the rock outcrop two lots down from the entry pit, the cabinet that takes the only setup space, the railroad corridor the prints crossed with a casual line. Finding those on foot, with a camera, costs an hour. Finding them with a bore head, an open trench, or a strike costs days, repairs, claims, and reports.
Restoration and trust in the record close the list. Restoration disputes rarely turn on whether concrete or sod was placed. They turn on whether it matches what was there before. The site read’s photographs and panel-by-panel, driveway-by-driveway notes are the only honest answer to that question. They also protect the crew. A leaking water service, a cracked gas meter guard, or a leaning pole that predates your work will be blamed on the newest work on the street unless your before record, made before disturbance, shows it was already there.
What Does Good Look Like?
- The full work area was driven slowly and then walked on foot, on both sides, including a short distance beyond each end of the work. Any segment that could not be walked or legally observed is named in the notes with the reason, never silently skipped.
- All five passes were worked in order, legal lines, ground and water, road furniture, utility evidence, and access and people, using a checklist, so completeness does not depend on what caught the reader’s eye.
- Every surface utility feature on the route is logged by type, location, side of the road, and condition: poles with their risers and guys, pedestals, cabinets, manhole covers, handhole lids, hydrants, gas meters, water meter boxes, valves, inlets, and cleanouts. Unidentified lids and enclosures are logged as unidentified, with a photo, never guessed into a system.
- Drainage is traced as a path. Ditches, culverts with both mouths sought, inlets, low spots, groundwater signs, and discharge points are connected in the notes, and any place where pits, trenches, spoil, or setup will block or receive that water is flagged.
- Legal lines are treated honestly. Survey evidence found is photographed in context. Occupation lines are described as occupation only. Any segment where the work depends on an exact right-of-way, easement, or property line and no reliable evidence or record was available is escalated for records or survey, never resolved by eye.
- The field, the prints, and the marks were compared segment by segment, on site or the same day. Each segment is recorded as matches, differs, or not enough information, and every difference is written exactly as found, with no source quietly edited to agree with another.
- Photographs are located, sequenced in walk order, and paired with written condition notes that capture what a photo cannot: movement, sogginess, sound, a smell noted only as an observation to report and never as a reason to linger near a suspected gas condition, and preexisting damage.
- The read ends with a written questions and conflicts list. Each item has a location, the conflicting sources, the risk of guessing, and the owner who must resolve it. That list was handed through the project process before digging, and the start decision reflects its resolution or an explicit plan around it.
- The before record for restoration is complete: pavement, concrete panels, driveways, gravel, landscaping, and sprinkler evidence photographed lot by lot, with preexisting damage named, so restoration has a target and the project has evidence.
- Nothing was entered, opened, operated, moved, or tested beyond the reader’s authorization during the read. Structures were not entered, enclosures were not opened without authority, valves were not touched, and private property was not entered beyond the project’s permission.
A good read can still find a street full of problems. Good means every problem the surface could reveal was found, written, located, and routed to the person who can resolve it, before machines made it expensive.

From the Field
Picture a fiber project set to bore along the east side of a residential street for four blocks, cross the street once, and place five handholes. The prints show a clear right-of-way corridor, pedestals at even intervals, and one water crossing per lot. The locate ticket is current, and marks are down. Before any machine is unloaded, the crew lead and one crew member spend a morning on the site read, following this lesson’s sequence.
The slow drive-by, done in both directions, shows three things the prints do not emphasize. The street falls gently toward a low intersection at the south end, so the whole corridor drains that way. Cars park densely on the east side near a small church, exactly where two handholes are planned. The street crossing sits just past a driveway on a blind rise, where traffic appears quickly.
The walk works the five passes. On legal lines, pink survey flags mark the right-of-way at the north end, while the two middle blocks carry no survey evidence and fences sit at uneven distances from the curb. The readers photograph the flagged segment, describe the fences as occupation only, and list the middle blocks as a question: confirm the corridor limit from records before handhole positions are final. On ground and water, the ditch on the east side is dry at the north end and wet at the south end in dry weather, with a green strip along it. Two driveway culverts are open. A third culvert mouth cannot be found on the upstream side, and the driveway above it shows a sunken patch. The readers note a probable blocked or crushed culvert as a question for the project and the road authority, and flag the south handhole pit as a place that will meet groundwater or drainage water and needs the project’s water plan. On road furniture, they log two lifted sidewalk panels and one cracked driveway apron, photographed with addresses, before anyone disturbs them, and they note that the blind rise crossing will need the traffic control the permit and the project traffic lead specify for that sight distance, rather than the standard setup used on the flat blocks.
On utility evidence, the walk earns its keep. One green pedestal stands in a hedge between two lots and appears nowhere on the prints. Orange marks run to it and away from it, so the readers treat it as live plant in the bore line, because marks prove that a facility is there to be located, and only the facility owner can confirm that a facility is abandoned and out of service. A water meter box on one lot is buried under mulch, found only because blue marks run to a flower bed with no visible lid, the same mismatch Lesson 40 teaches. The box is photographed as found and reported, and the fiber crew leaves resetting it to the party authorized to do that work. At the street crossing, red electric marks and a pole riser on the west side show that the crossing must pass an electric facility the prints drew on the other side of the driveway. The readers record the conflict exactly: prints place the electric crossing at the driveway, marks and riser place it past the driveway. Moving the crossing on their own authority is outside their role, so the conflict goes on the list as found.
On access and people, they find that the church parking fills the planned setup area on the days the project schedule assumed, that one driveway is the only access to a house whose resident tells them about a daily medical visit, and that a decorative concrete driveway on the crossing block would be crossed by tracked equipment under the first setup idea. The readers note the resident’s concern courteously and promise nothing. All three facts go to the project lead the same day, because schedule, access sequencing, and customer communication belong to the lead.
The comparison that afternoon is written segment by segment. North block: matches. Middle blocks: differ, for the pedestal missing from the prints, the buried meter box, and the unconfirmed corridor limit. Crossing: differs, for the electric position. South block: matches on utilities, differs on water, for the wet ditch and the missing culvert mouth. The questions list carries five items, each with a location, the conflicting sources, the risk of guessing, and an owner: designer for the pedestal and handhole shift, locator and utility records for the electric crossing verification and potholing plan, road authority or designer for the culvert, project lead for church and resident scheduling, and records or survey for the corridor limit.
Construction starts on that street only after the pedestal is added to the prints, the crossing is verified and its potholes are planned, the corridor limit is confirmed, and the schedule is moved around the church and the resident. The bore then runs without a strike, the south pit is ready for the water it actually meets, and restoration is judged against before photos that show the lifted panels and cracked apron were already there. The morning’s walk removed the five delays, and the one possible strike, that guessing would have delivered later at machine prices.
Carry the rule out of this story: read first, in order, with all three sources open; write every conflict exactly as found, with a location and an owner; and let the project resolve the list before the bore starts, because a morning of reading is always cheaper than one guessed crossing.
What Can Go Wrong?
Jobsite read failures are usually ordinary shortcuts, repeated until one of them meets a live facility or a flooded pit.
- Reading from the truck. A crew drives the route once, at traffic speed, and calls it read. The buried meter lid, the pedestal behind the hedge, the culvert mouth under the driveway, and the sunken handhole in tall grass were all invisible at that speed and angle. The walk exists because the drive-by cannot see them.
- Walking one side only. The route is read from the side the work is on, while the ditch, the pole risers, and the services on the far side, which the bore will cross the road to reach, are never seen. Crossings fail on the unread side.
- Trusting the prints alone. Prints show a clear corridor. In the field a cabinet placed last year, a replaced water service on a new path, and a private line to a detached garage occupy that corridor. Records lag the field, which is why CGA visual inspection practice tells locators and excavators to look for facilities that are not on record.
- Trusting the marks alone. Paint is treated as the exact line and depth. A bore runs tight along a mark, inside the tolerance zone the state rules protect, without the verification or potholing the plan requires, and strikes a facility that sat to the side of its paint, at a depth no mark ever promised.
- Trusting the eyes alone. A reader sees no surface feature and declares a segment clear. An occupied house with no visible meter, a lot with no pedestal, and a street with no manhole can each still be crossed by buried facilities with no surface evidence, including private facilities a public ticket may not mark. Absence of evidence is recorded as a question, always.
- Guessing a legal line from a fence. Work is laid out from a fence or a mow strip as if it were the property line or the easement edge. The fence sat well inside the owner’s land, or well outside it, and the new handhole lands on private land the project has no right to use, or in a place the easement does not allow. Legal lines come from records and surveys, and landscaping is never one of those sources.
- Reading utilities and skipping water. Every pedestal is logged, and no one follows the ditch. The first rain, or the first groundwater the trench meets, fills the pits, softens the trench walls, washes spoil into the culvert, and stops the job. Drainage and groundwater are construction conditions.
- Reading the ground and skipping the people. The technically perfect plan blocks the only driveway to a house during the hours its resident needs medical transport, closes a business entrance on its delivery day without project notice, and sets a vacuum truck where children board a bus. The project lead owns those communications and decisions. The reader’s job is to surface the facts in time for the lead to act on them.
- Photographing without locating. A folder of close photos with no addresses, no sequence, and no notes cannot prove which cracked panel belonged to which house, or find a buried lid again. Unlocated photos are decoration.
- Burying the conflicts list. The reader finds real mismatches, mentions them verbally, and no written list reaches the designer or locator. The crew that starts Monday never hears about the pedestal missing from the prints, because the finding lived only in Friday’s conversation.
- Treating the read as permission. A thorough walk is mistaken for clearance to dig, to enter a handhole or manhole, to open a cabinet, or to shift another utility’s facility out of the way. The read authorizes none of those. Tickets, permits, plans, and named roles authorize work. The read informs them.
These failures share one root. The site was looked at, and it was never read: no order, no comparison, no written conflicts, and no escalation before digging.
What Should Someone Notice in the Field?
Notice the site the way the designer, the locator, the utility owners, and the restoration crew will each need it described, from the surface, within your authorization. You are observing, photographing, noting, comparing, and reporting. Digging, entering, opening, operating, and certifying all belong to other roles.
- Start with limits and safety for the read itself. Confirm where you may walk: public right-of-way, project easements, and any permissions the project holds. Wear the visibility and protective equipment your project requires for roadside work, walk facing traffic where required, stay out of travel lanes, and stay out of roadways, railroad corridors, bridge structures, and private yards beyond your permission in pursuit of a better look. If a condition looks hazardous, such as a damaged energized facility, a strong gas odor, a collapsed cover, or an unstable slope, approach no closer to investigate it. Move to a safe place and report it through the project and emergency process your plan directs. This lesson does not teach hazard investigation.
- Legal lines. Note pink survey flags, stakes, corner markers, and monument boxes, photographed in context. Note fences, walls, hedges, and mow lines as occupation only. Note any place where a planned pit, handhole, or bore line sits near, on, or across an apparent boundary, and any segment where no evidence marks a line the work depends on. Record the exact wording of any easement or right-of-way sign you find.
- Terrain, soil, and rock clues. Note slopes, cuts, fills, pads, retaining walls, and erosion. Note exposed rock, rock in ditches, gravel and sand patches, patched or sunken trench lines, cracked or heaved pavement, and spoil or stockpiles from other work. Describe the clue and its location. Assign no soil type, rock depth, or boring difficulty rating as fact from surface clues alone.
- Water and drainage. Note standing water, flowing water, wet soil in dry weather, lush strips in dry ground, discharge pipes, and sump outlets. Trace each ditch to its culverts and inlets. Note each culvert mouth you can safely observe: open, crushed, blocked, silted, or not found. Note low spots where pits will collect water and any place where your spoil or setup would block a drainage path.
- Vegetation. Note tree lines, large or protected looking trees in or near the work, stumps, cleared corridors, and dense brush that hides surface features. Brush that hides the ground is a limit on the read itself. Note hidden segments for clearing by the authorized crew or for a second look, instead of claiming they were read.
- Road furniture. Note curb and gutter presence and condition, gutter flow line obstructions, sidewalk panels that are cracked, lifted, settled, or patched, driveway surfaces, slopes, and culvert crossings, intersection corners, ramps, crosswalks, signal equipment, and sight line obstructions. At bridges and railroads, note the constraint, the approaches, and the prints crossing, and escalate. Observe only.
- Poles. For each pole on or near the route, note its location, any tag number readable from the ground, lines and equipment you can identify at a recognition level, transformers, streetlights, guys and anchors, and every riser where a line goes underground. Note leaning, damaged, or rotted looking poles as conditions to report, without touching or testing the pole.
- Enclosures and structures at the surface. Find and log every pedestal, cabinet, manhole cover, handhole lid, valve box, cleanout, inlet, and irrigation box. Note lid wording, color, condition, flush or sunk or raised or buried or paved over, and whether the feature appears on the prints. Open, enter, lift, or move none of them beyond your explicit project authorization. An unidentified cover is logged as unidentified.
- Property services. At each occupied property, find the hydrant coverage for the stretch, the gas meter set, the water meter box, and the electric service point. Note services you cannot find as questions. Note preexisting damage, flooding, leaks suggested by surface signs, or guards and protection already in place, described as observations, never as diagnoses.
- Marks and flags. Walk each color run end to end under the APWA code: red electric, yellow gas and petroleum, orange communications, blue potable water, green sewer and drain, purple reclaimed and irrigation, pink survey, white proposed excavation. Note crossings of your route, faded or destroyed marks, marks that end without a feature, features with no marks, and any place where marks and prints or marks and features disagree. Note ticket information your project provides and any cleared facilities with no marks to check against the field.
- Access and setup. Note gates, widths, grades, soft ground, low lines and canopy, load sensitive surfaces, and turning room for the equipment the plan names. Note where bore, excavation, vacuum, and material equipment can set up under the permit and traffic plan, and where they clearly cannot. Verify limits with the agency, the owner, and the equipment documentation. Invent no clearance, load limit, or width from a glance.
- Traffic and people. Note travel patterns, parked vehicles in the work line, bus stops, school and business activity, mailboxes, hydrants that must stay accessible, and driveways that are a property’s only access. Record resident or business concerns you hear, worded as their concern, for the project lead. Make no promises about schedule, method, or restoration on the project’s behalf.
- Restoration surfaces. Photograph and note, lot by lot: pavement patches and age clues, concrete panels, decorative surfaces, gravel, sod, seed, beds, and visible sprinkler heads. Name preexisting cracks, stains, settling, and damage before disturbance, in words tied to located photos.
- Close the read properly. Complete the field against prints and marks comparison, write the questions and conflicts list with locations and owners, and hand it through the project process the same day where possible. State plainly which segments match, which differ, and which could not be fully read and why. A read that hides its own limits misleads the crew more than a read that names them.
Safety and limits, plainly. A jobsite read qualifies no one to locate buried facilities as a locator, to survey or establish a legal line, to classify soil as an OSHA competent person, to design excavation protection, to enter a manhole or any confined space, to open or work in energized or pressurized utility equipment, to operate any other utility’s valve or switch, or to authorize excavation. Those roles have their own training, credentials, and authority under federal rules, state laws, utility rules, and the project plan. Your read supports them with early, accurate, written field information. It replaces none of them.
Key Terms
- Jobsite read. A structured preconstruction observation of a work area that identifies legal, physical, utility, access, and people conditions, compares them against the prints and locate marks, and reports questions and conflicts before ground is disturbed.
- Prints. The project construction drawings showing the planned route, known existing features, proposed structures, and governing notes. Prints are prior knowledge and a plan, and field conditions can differ from them.
- Right-of-way. The strip of land reserved for a road and utilities along it, controlled under the rules of the agency that controls the road. Its width and allowed uses vary by location and must be verified from records.
- Easement. A legal right to use a defined part of another person’s land for a stated purpose. A utility easement used on a project is normally created by a recorded document that sets its location, holder, and terms, and in some documents its width. Some easements are unrecorded, and some recorded easements state no width.
- Property line. The legal boundary between parcels. Fences and mow lines are occupation evidence only. Surveys, plats, and recorded records prove the legal line.
- Locate mark. Temporary paint, flag, stake, or whisker placed by a locator to show the approximate location of a buried facility, colored under the APWA Uniform Color Code. Marks prove neither exact position nor depth.
- APWA Uniform Color Code. The American Public Works Association color system for temporary utility marks: white proposed excavation, pink survey, red electric, yellow gas and petroleum, orange communications, blue potable water, purple reclaimed water and irrigation, green sewer and drain.
- Locate ticket. The record created by contacting 811 and asking member utilities to mark facilities in a work area. State law sets notice, validity, positive response, and tolerance zone rules for the ticket.
- Tolerance zone. The corridor around a buried facility, defined by state rules, where careful hand or vacuum exposure methods are required and mechanical digging is restricted until the exact location of the facility is determined. States define and measure the zone differently, from the facility, its outside edge, or the mark, and its width varies by state.
- Potholing. Digging a small careful hole, by hand or vacuum, to expose a buried facility and confirm its exact position at a specific point, done under the project plan as construction work, outside the read itself.
- Pedestal and cabinet. Above-ground enclosures for distribution connections and equipment. A pedestal is the smaller yard level enclosure. A cabinet is larger and may house powered equipment. Neither is opened in a read without authorization.
- Manhole and handhole. Underground enclosures reached from a surface cover or lid. A manhole is large enough for person entry under strict rules this lesson does not authorize. A handhole is smaller and is worked from the surface.
- Culvert. A pipe or box that carries drainage under a road, driveway, or embankment. A complete read seeks both mouths and notes blockage, crushing, or a mouth that cannot be found.
- Competent person. In OSHA excavation rules, a person who can identify existing and predictable hazards and has authority to take prompt corrective action, including inspecting excavations. The role requires training and authority beyond this lesson.
- Restoration. Returning disturbed pavement, concrete, soil, gravel, and landscaping to the condition and standard the permit, contract, and owner require, judged against the before record.
- White lining. Premarking the proposed excavation area in white, where state rules and best practice call for it, so locators mark the right area and the crew can compare marks against the intended work.
Check Your Understanding
- Put the five passes of a jobsite read in order and, for each pass, name two specific things the reader looks for.
- A pedestal stands in the bore line and appears nowhere on the prints, but orange marks run to it and away from it. A trainee says to ignore it because the prints are the plan and the plan is clear. Identify the errors and state the correct response.
- During the walk you find pink flags on one block, no survey evidence on the next two blocks, and fences at uneven distances from the curb where handholes are planned. What can you honestly record about the legal lines, and what must happen before handhole positions there are treated as final?
- Your prints, your marks, and the field disagree at a street crossing about where an electric facility runs. List the steps a good read takes with that conflict, in order, and name what the reader must not do with it.
- A lead says the site was driven twice and looks fine, so the walk, the comparison, and the written questions list can be skipped to save a morning. Give three concrete findings, from this lesson, that a drive-by alone would likely miss, and state what each miss could cause.
Answer key
- Order: first, legal lines, right-of-way evidence, easements, property lines, survey flags, corner markers, and occupation lines such as fences. Second, ground and water, terrain and slopes, soil and rock clues, groundwater signs, drainage paths, ditches, culverts, and vegetation. Third, road furniture, curb and gutter, sidewalks, driveways, intersections, and bridges or railroads where present, observed only. Fourth, utility evidence, poles and risers, pedestals, cabinets, manholes, handholes, hydrants, gas and water meters, and all paint marks and flags by APWA color. Fifth, access and people, equipment access and setup room, traffic and parked vehicles, residents and business needs, and restoration surfaces with their before condition.
- First error, treating the prints as complete. Records lag the field, and CGA visual inspection practice exists to catch facilities that are not on record. Second error, ignoring the marks. Orange marks running to and from the pedestal are located communications facility evidence that agrees with the surface feature, so two sources say the facility is real and the prints are the source that is wrong. Third error, deciding alone in the field. The correct response is to log and photograph the pedestal by location and condition, record the conflict exactly, place it on the written questions list for the designer and project lead, and hold the bore plan for that segment until the prints or the route are corrected through the project process and any verification the plan requires is done.
- You can record that survey evidence, the pink temporary survey marks, was found on the first block, photographed in context, and that no survey evidence was found on the next two blocks, where fences sit at uneven distances and are occupation evidence only. You cannot honestly record the exact right-of-way, easement, or property line on the unsurveyed blocks, because fences, hedges, and mow lines never prove a legal line. Before handhole positions there are treated as final, the corridor limit must be confirmed from reliable records, plats, or a survey through the project process, by the people qualified and authorized to establish it. The read escalates the gap. Filling it by eye is outside the read.
- Steps in order: record the conflict exactly as found, with the crossing location and what each source shows, prints, marks, and surface evidence such as the pole riser. Photograph the marks and the riser in context and note the ticket information. Place the conflict on the written questions and conflicts list with the risk of guessing, a strike on an energized facility, and the owners who must resolve it, typically the locator, the electric utility, and the designer or project lead. Hand the list through the project process before digging and hold that crossing until the project resolves it, which may include re-marking, records checks, and potholing under the plan to determine the exact location by safe means as the work approaches, as OSHA excavation rules require. The reader must never quietly pick the source they like best, never redraw the prints or move the marks to make them agree, never shift the crossing on their own authority, and never let the bore proceed on a guess.
- Any three of these, with a plausible consequence for each: a meter lid buried under mulch where blue marks run to a flower bed, missed from a vehicle, which could lead to a water service strike planned on the assumption that no service crosses there. A pedestal hidden in a hedge that is missing from the prints, missed at driving speed, which puts live communications plant in the bore line. A culvert mouth that cannot be found under a driveway with a sunken patch above it, missed without walking the ditch, which leaves a blocked drainage path to flood a pit or undermine a driveway. A wet ditch and green strip in dry weather at the low end, missed without tracing drainage on foot, which leaves the crew unprepared for groundwater in the south pits. A lifted sidewalk panel or cracked driveway apron, missed as a before condition, which the project will later be blamed and billed for as new damage. Survey flags present on one block and absent on the next, missed as a pattern from the truck, which lets handholes be set to a fence line mistaken for a legal line. The point in every case is the same: the drive-by gives the shape of the site. Only the walk, the comparison, and the written list give the evidence the start decision needs.
Lesson Takeaway
Reading a jobsite is a system, and the system is learnable. Drive the route slowly to learn its shape. Then walk both sides and work five passes in order: legal lines first, so you know where work is allowed; ground and water next, so you know what the earth and its drainage will do to the work; road furniture next, so you know the built surfaces you will cross and restore; utility evidence next, poles, pedestals, cabinets, manholes, handholes, hydrants, meters, and marks, so every buried system that announces itself is logged; and access and people last, so the plan fits the real street and the real neighbors. Photograph and note as you go, with locations a stranger can follow. Compare field, prints, and marks segment by segment, and record disagreements exactly as found. End with a written list of questions and conflicts, each with a location and an owner, and escalate it before digging. Treat every mark as approximate, every fence as occupation only, every occupied building as served, and every absence of evidence as a question. A read is observation and documentation. It authorizes no digging, no entry, no opening, and no operation of anything. Done well, it is the cheapest damage prevention, planning, and restoration protection a project will ever buy, and it is the habit that turns all of Level 2 into field judgment.
Sources and Technical References
- Common Ground Alliance, Best Practices, Version 22.0. Practices on planning and design records and site interviews, white lining the proposed excavation, visual inspection during locating to check that records match the site and to find evidence of facilities not on record including poles, enclosures, pedestals, valves, meters, risers, and manholes, and temporary facility markings matched to surface conditions. Used for the visual inspection, records comparison, and white lining disciplines in this lesson. https://carcga.org/BP_22.0_Web.pdf
- Occupational Safety and Health Administration, 29 CFR 1926.651, Specific excavation requirements, federal regulation text via Cornell Law Institute. States that surface encumbrances that create a hazard must be removed or supported, that the estimated location of utility installations that may reasonably be expected to be encountered must be determined before opening an excavation, that utility companies or owners must be contacted and asked to establish locations before excavation starts, and that the exact location must be determined by safe and acceptable means as excavation approaches it. Used for the federal excavation duties a site read supports. https://www.law.cornell.edu/cfr/text/29/1926.651
- American Public Works Association, Uniform Color Code for Marking Underground Utility Lines, summary sheet via City of Dover. States white for proposed excavation, pink for temporary survey markings, red for electric, yellow for gas, oil, steam, petroleum, or gaseous materials, orange for communication, alarm, or signal lines, blue for potable water, purple for reclaimed water, irrigation, and slurry lines, and green for sewers and drain lines. Used for every mark color named in this lesson. https://www.cityofdover.gov/media/Public Works/APWA Uniform Color Code.pdf
- Federal Highway Administration, Construction Program Guide, Utilities. Summarizes federal authority for utility accommodation and relocation in highway right-of-way, including 23 USC 109 and 123 and 23 CFR Part 645, and the public interest basis for joint use of road right-of-way by utilities. Used as background for right-of-way and utility coordination on road projects, stated in this lesson as background for local permit work, never as the permit for a local street. https://www.fhwa.dot.gov/construction/cqit/utilities.cfm
- Federal Highway Administration, Right-of-Way and Utility coordination review material. Quotes the federal-aid coordination principle that right-of-way clearance, utility, and railroad work are to be coordinated with physical construction so no unnecessary delay or cost occurs. Used for the coordination principle only. https://www.fhwa.dot.gov/construction/reviews/revrow1.cfm
- The Fiber Optic Association, FOA Reference for Fiber Optics, Outside Plant Construction, Underground Construction. Covers underground outside plant construction, manholes and handholes, markers, records, and placing practice in shared utility corridors. Used for outside plant context, handhole and manhole recognition, and records as part of construction documentation. https://www.thefoa.org/tech/ref/OSP_Construction/Underground_Construction.html
- The Fiber Optic Association, FOA Reference for Fiber Optics, Outside Plant Fiber Optic Network Design. Covers outside plant design, splice closures and hardware including pedestals, handholes, and manholes, and the need to select hardware for the location it serves. Used for pedestal, cabinet, and enclosure context in the utility evidence pass. http://www.foa.org/tech/ref/OSP/design.html
- Columbia Gas of Ohio, Contact 811 Before You Dig. States the excavator steps of contacting 811 at least two working days before work in that state system, waiting for marks, respecting the marks, and hand digging or using nonmechanical means within the tolerance zone under that state’s rules, and warns never to assume pipeline location or depth because locating does not verify depth and conditions change. Used as one state system’s published example of the 811 sequence and the depth warning. Notice times and tolerance rules are state rules and vary, and this lesson states no state example as a national rule. https://www.columbiagasohio.com/safety/damage-prevention/call-811-before-you-dig
- GPRS, What Do Utility Marking Colors Mean. Summarizes the APWA colors and states that calling 811 marks public utility lines and that private lines on a property are not covered by that public locate, a gap where many strikes occur. Used for the public versus private facility distinction, stated in this lesson as a common pattern that must be confirmed for the ticket and state in hand. https://www.gp-radar.com/article/what-do-the-utility-marking-colors-mean
Previous lesson: Lesson 44: What Can You Learn From a Utility Pole? |
Back to Level 2 hub |
Next lesson: Lesson 46: What Is an Existing Utility?