Lesson 12: What Is a Central Office / Headend / Hub?

Introduction

A central office, a headend, and a hub site are provider facilities where active network electronics are housed and where outside plant fiber begins and ends. A telephone provider calls its origin building a central office. A cable provider calls its origin facility a headend. A hub site is a smaller secondary facility fed from one of those origins to serve part of an area. Three names, one idea: the secure building where service originates.

This lesson sits early in Level 1 because every route you will study after it starts at one of these buildings. Feeder fiber, the subject of the next lesson, leaves the facility and runs outward. A beginner who can recognize the origin building, name what happens inside it, and respect its access boundary can read the shape of the whole network built from it.

What This Lesson Gives You

  • Tell a central office, a headend, and a hub site apart by provider and by role, and explain what the three names share.
  • Name the four elements found inside all three facilities and say what each one does.
  • Read a plain, windowless building or hut from outside and decide, from the clues, whether it is a live fiber facility.
  • State where outside plant work ends at a facility and where authorized inside work begins.
  • Spot exterior problems worth reporting the same day, and state the access boundary you never cross without authorization.

Start With the Basics

Every fiber network you have seen so far runs outward toward homes and businesses. Poles, conduit, handholes, terminals, and drops all point in one direction: toward the customer. It is natural to ask where that direction starts.

It starts in a building.

Somewhere in or near every service area there is a provider facility where the network begins. Inside that building, electronic equipment creates the signals that travel out on fiber. Outside plant fiber, the feeder cable you will meet in the next lesson, leaves that building and carries those signals toward neighborhoods. Think of the drop from Lesson 10 as a driveway serving one house. This facility is the depot the whole road system runs out of: every route in the area traces back to it, and nothing on those routes carries service until the equipment inside it is running.

Different kinds of providers use different names for that origin building, and larger networks add a second, smaller kind of site between the origin and the neighborhood. The three names in this lesson title cover those cases:

  • Telephone companies call the origin building a central office, often shortened to CO.
  • Cable providers call the origin facility a headend.
  • Both kinds of providers, and many internet service providers building fiber today, also use hub sites. A hub is a smaller secondary facility fed from a central office or headend that serves a portion of the service area.

The names differ. The core job is the same: house the active electronics, terminate the outside plant fiber in an organized way, provide power and backup power, and keep it all secure and running around the clock.

What Is It?

A central office, headend, or hub is a provider owned or controlled facility where active network electronics are housed and where outside plant fiber originates or terminates. Take each name in turn.

A central office is the telephone company term. In its original use, a central office was the building that housed the telephone switch for an area: the equipment that connected one subscriber line to another so calls could be completed. Telephone industry references and carrier definitions still describe a central office as a switching center where loops and trunks terminate. In a modern fiber network, the same building also houses fiber equipment, including the optical line terminal described below. The words wire center are also used in North America for a central office location. A fiber provider that is not a traditional telephone company may still call its main facility a central office, using the established telephone industry term for an origin building.

A headend is the cable provider term. A headend is the master facility where a cable operator receives signals from sources such as satellite feeds and off air broadcasts, processes them, and inserts them into the cable distribution system. Industry references describe the headend as also handling data and voice switching and administrative functions for the system. In a modern cable network that delivers internet and phone service as well as television, the headend houses the electronics for all of those services, and fiber leaves the headend toward neighborhood nodes and, in fiber to the home designs, toward homes.

A hub site is a smaller distribution facility between the origin and the customer. Cable industry usage describes hubs as key facilities served by the network backbone, typically connected to each other and to the headend over redundant fiber paths. In fiber to the home work, hub can also describe a site that houses optical line terminals or distribution equipment for one part of a town, fed by feeder fiber from the main central office or headend. A hub site may be a small purpose built building, often called a hut, or a large cabinet. Not every network has hubs. A small network may run everything from one central office or headend. A large network uses hubs to shorten the outside plant runs and to divide a big service area into manageable pieces.

Two cautions about the word hub:

  • Hub is also used in this curriculum for a different piece of field equipment, the fiber distribution hub, an outdoor cabinet where feeder fiber is split and connected to distribution fiber. That cabinet is covered in later lessons. A hub site in this lesson is a facility with a building or hut and active electronics. Context tells you which meaning is in use: a site you could stand next to and be locked out of is the facility, and a street cabinet is the distribution equipment.
  • Providers do not all use these three names the same way. Some call every origin site a hub. Some call a large hub a regional headend. Read the name on the project drawings and learn what that provider means by it on that project, instead of assuming one naming system fits every network.

Inside all three kinds of facility, four elements appear again and again:

  • Active electronics. For fiber to the home, the key device is the optical line terminal, often shortened to OLT. An OLT is the provider side endpoint of a passive optical network, often shortened to PON. A PON is a fiber architecture in which one feeder fiber is passively split to serve many customers, without powered equipment in the outside plant between the OLT and the customer. The OLT converts signals between the provider core network and the fiber plant, manages traffic to and from many customer optical network terminals, and controls the PON. Cable headends also house their own access electronics for data and video services. The concept level point is the same: the building holds the powered equipment that originates the service.
  • Fiber termination and organization. Outside plant cables entering the building terminate on a fiber distribution frame, also called an optical distribution frame, or on patch panels. A patch panel is a panel of connector ports where fiber cables terminate so they can be connected to equipment or to each other with short patch cords. A distribution frame is the larger rack or frame system that holds those panels and organizes splicing, termination, and patching for many cables in one place. Manufacturer and FOA guidance for central office and headend work describes all optical cables in these facilities terminating on a patch panel or distribution frame so active and passive equipment can be connected in an orderly, testable way. Outside plant cable is generally terminated shortly after entering the building, in part because outside plant cable jackets do not meet indoor fire protection requirements. That termination point is where inside plant work and outside plant work meet.
  • Power and backup. The electronics need continuous electrical power, plus backup power so service continues during a utility outage. At an overview level, these facilities have a dedicated power plant and battery backup, and larger sites may also have a standby generator. This lesson states no capacities, runtimes, or voltages, because those are design and provider specific and must be read from the project and the equipment documentation, not assumed.
  • Controlled environment and security. The building provides cooling, controlled access, alarms, and physical protection for equipment that serves many customers. That is why these facilities look plain and stay locked, a point the appearance section below returns to.

Full inside plant construction, rack layout, splicing inside the frame, and electronics installation belong to later levels and to qualified inside plant and network technicians. This lesson is the concept lesson: what these facilities are, where they fit, and how to recognize them from outside.

What Does It Look Like?

From the street, a central office, headend, or hub often looks like almost nothing. That plain appearance is deliberate and normal, and learning to read the small clues is the field skill in this lesson.

A traditional central office is usually a solid, purpose built building, often brick or concrete block, with few windows or no windows at street level. Many older central offices are substantial buildings in the middle of a town, sometimes with the provider name on the building and sometimes with no signage at all. You may see:

  • Heavy doors without public entrances
  • Ventilation louvers
  • Conduit and cable entries at the rear or side
  • A fenced equipment yard
  • A standby generator enclosure
  • Cooling equipment

A cable headend looks similar, with one extra clue that is often visible from outside: satellite dish antennas in a fenced yard or on the roof, used to receive programming feeds. Many feeds now arrive by fiber, so a headend may show few dishes or none. The absence of dishes does not rule a site out.

A hub site is smaller. Look for:

  • A small windowless hut or walk in cabinet on a concrete pad
  • A chain link fence around the pad
  • A power meter
  • Conduit stubs coming up from underground
  • Fiber warning markers or signs on the fence or nearby
  • Sometimes a small generator or battery cabinet beside the hut

Hub huts are frequently unmarked or marked only with a site code, an address, and a warning or contact placard. They sit in easements, on provider owned lots, or beside roads, and they are easy to drive past for years without noticing.

Common clues across all three facility types:

  • No public lobby, no customer parking, and no retail signage. These are operations buildings.
  • Locked doors, access control readers or keypads, security cameras, and alarm or restricted access signage.
  • Multiple large conduit entries, a cable vault or entry room on larger buildings, and fiber route markers leading away from the building along streets or easements.
  • Backup power clues: a generator, an exhaust stack, a fuel tank, or a battery cabinet.
  • Cooling clues: large air conditioning units or louvers sized for equipment heat, beyond what people comfort alone would need.
  • A dense convergence of outside plant: many pole lines, conduit banks, or fiber routes in the surrounding streets lead toward the building, because feeder routes radiate out from it.

One caution on identification: other utilities also use plain secure buildings and huts, including water, electric, and cellular sites. A windowless fenced building is not automatically a fiber facility. Read signage and project records where you can do so from a public or authorized position, note the satellite dishes, fiber markers, and cable entries that support an identification, and report an uncertain site as unidentified rather than guessing.

Whiteboard illustration: central office, headend, and hub

What Does It Do?

These facilities do five jobs for the network. A beginner needs the jobs, not the electronics detail.

First, they originate the service. The OLT and related access electronics take traffic from the provider core network and put it onto the fiber plant in the form the PON uses, and they receive traffic coming back from customers and pass it onward. The mechanism is conversion at a boundary: on one side, the provider core network; on the other side, light signals shaped for the passive plant. Without this equipment running, the fiber in the ground is dark glass: physically complete, but carrying no service.

Second, they aggregate many customers in one place. One OLT serves many optical network terminals at customer premises through splitters in the outside plant. That aggregation is why one building can serve a whole town area, and why a failure inside that building can affect many customers at once.

Third, they provide the organized boundary between inside plant and outside plant. Feeder cables terminate on the distribution frame or patch panels. From there, patch cords connect individual fibers to individual equipment ports. That structure is what makes testing, record keeping, service changes, and troubleshooting possible fiber by fiber, instead of as an unmanaged tangle. The frame turns a building full of cables into an indexed system: every fiber has a position, every position has a record, and a technician can find, test, or reroute one fiber without disturbing the rest.

Fourth, they keep service running. Power backup, cooling, alarms, and remote monitoring exist so the site keeps operating through utility outages and equipment faults, and so the provider learns about a problem at the site quickly, often before customers call.

Fifth, in the headend case, they receive and prepare content and services. A cable headend receives programming and combines television, data, and voice services for distribution. A telephone central office historically switched voice calls for its area, and its modern fiber role sits alongside that switching heritage in the same building. A hub does a smaller version of the originating and aggregating jobs for its portion of the area, relying on the central office or headend behind it for the core connection.

Where Does It Fit?

The central office, headend, or hub is the start of the outside plant chain you have been learning. In sequence: the facility comes first, then feeder fiber leaves it, then distribution fiber carries the signal through neighborhoods, then terminals provide connection points, then drops reach individual premises, where optical network terminals convert the light signal for customer devices.

That position explains construction order and crew boundaries. Outside plant crews build feeder routes outward from the building entry. Their fiber work for a new feeder typically ends at the building entry point and at the distribution frame, where the outside cable is terminated. Work on the active electronics themselves, including turning up an OLT, configuring it, and connecting live services, is done by qualified and authorized network or inside plant personnel, not by outside plant construction crews as a matter of course. Project plans and provider rules define the exact handoff on each job. When your assignment says a feeder terminates at the central office, it means the building and its frame, not that your crew will work on live electronics inside it.

Hubs fit between the origin and the neighborhood. Feeder fiber runs from the central office or headend to the hub. From the hub, shorter feeder or distribution routes run to the surrounding area. This two level pattern lets a provider serve a wide area without running every neighborhood fiber all the way back to one central building.

These facilities also fit at an operational boundary. Construction ends, operations begins, and the building is where that change happens. Once a site is live, it is an operating network facility under the provider control systems, alarms, and access rules, even if construction is still underway in the streets outside it.

What Is at Stake

Everything downstream depends on these buildings. In the PON designs this curriculum covers, every terminal, splitter, and drop in an area traces back to an OLT port in one of these facilities. If you understand where the origin site for an area is, you understand the shape of the whole network built from it: which streets are fed from which site, why feeder routes converge where they do, and why a single building appears on so many project drawings.

The stakes concentrate because the service concentrates. A cut drop affects one customer. A problem at the distribution frame, the power plant, or the OLT in the origin facility can affect hundreds or thousands of customers at once. That concentration is why these buildings are secure, backed up, alarmed, and restricted, and why outside plant work near a facility entry, including digging near its conduit bank or working around its cable vault, carries outsized risk. The conduit bank at a building entry is where the area’s feeder cables converge, and damage there lands on many neighborhoods at the same time.

Your own conduct at these sites carries stakes too. Two opposite mistakes come from failing to recognize the building for what it is: treating a live network facility like an empty building you can enter or store material in, or treating a plain unmarked hut like it is nothing important and digging or parking equipment against it without checking. The first mistake can become a security incident or an outage. The second can damage the support systems, vents, generator, and conduit entries the site depends on. Recognition is what keeps both mistakes from happening.

What Does Good Look Like?

Good, for these facilities, is judged mostly by authorized personnel inside the building. From a beginner and outside plant perspective, good looks like this:

  • The site is secure and intact. Fences and gates are closed and locked, doors are shut, and there is no sign of forced entry, vandalism, or an open cabinet or hut door.
  • The exterior is maintained. The pad, yard, and access path are clear enough for authorized crews to reach the building, vegetation is not growing into fences, entries, vents, or generators, and drainage is not ponding against the building or pad.
  • Cable entries and outside plant connections look orderly. Conduit entries are sealed as the design requires, feeder routes leaving the site are marked where the provider marking practice requires it, and there is no damaged, hanging, or exposed cable at the building entry.
  • Identification and records are in place. The site carries the address, site code, or provider identification the project requires, emergency or contact information is posted where the provider practice calls for it, and the outside plant records you are given name the correct facility as the origin for each feeder.
  • Backup and support systems show no obvious distress from outside: no alarm sounding, no generator running unexpectedly without explanation through project channels, no cooling unit visibly damaged or blocked.

One distinction matters here: these are general condition observations. The inspection standard for a site, covering security requirements, entry sealing methods, generator and battery maintenance, cooling specifications, and inside plant standards for frames, patching, labeling, and fiber management, is set by the provider standards, applicable codes, manufacturer instructions, and the contract specifications for the site. A beginner reports exterior condition. Qualified facility and network personnel inspect, maintain, and certify the site itself.

Whiteboard illustration: where fiber starts, central office, headend, and hub

From the Field

Picture a construction crew starting a new feeder build on the edge of a small town. The drawings show the route beginning at a windowless brick building on a side street, with no provider sign on the front. A new crew member looks at the building, sees no sign and no windows, and assumes it is a warehouse. He plans to stage reels in its side yard, where the ground is flat and the trucks can turn around.

The foreman stops that plan before a single reel moves. He walks the crew around the site from the public sidewalk and reads the building out loud, clue by clue: the fenced rear yard with a generator enclosure, the bank of large conduits leaving the back wall and turning into the street easement, the access reader beside the heavy rear door, the cooling units sized for equipment, and a small placard carrying a site code and a provider contact number. He explains that the building is the central office for the area, that the feeder they are about to build will terminate at its frame, and that the yard is a secure operations area where authorized crews need clear access at any hour.

The crew stages somewhere else. The small delay costs the morning some repositioning and nothing more. Had the reels gone into that yard, the crew would have blocked access to a live facility, put material against equipment that has to stay reachable, and created a security problem on a site the provider monitors.

Later that week, the same crew member is sent to check a second starting point for the next phase. He finds a small unmarked hut on a pad inside a chain link fence, with a power meter, conduit stubs coming up from the ground, and fiber warning signs on the fence. This time he reads the pattern on his own: a hub site, fed from the central office, serving the new subdivision. He photographs the exterior from outside the fence, notes that the gate is locked and the pad is clear, and reports the site ready for the feeder termination work to be scheduled through the provider access process.

The lesson in both stops is the same recognition sequence. The most important building on the project had no sign and looked like nothing. The clues were in the power, the cooling, the conduit convergence, the security, and the records.

The rule to carry: read the clues before you treat any plain, locked, powered structure as empty, and never stage, park, dig, or store against a facility until project records confirm what it is and where you are allowed to be.

What Can Go Wrong?

Problems at or around these facilities tend to be high impact or high risk, even when they look small from outside.

  • Power problems. A utility outage plus a failed battery or generator start can take a whole service area down, even though every fiber in the ground is intact. Outside plant crews cannot fix this. Recognizing that a dark facility during an outage is a network emergency, and reporting it through project channels instead of assuming someone else knows, is the useful move.
  • Damage at the building entry. Feeder cables converge at the entry conduits and vault. Construction digging, vehicle strikes, or water entry at that convergence point can damage many fibers at once, including fibers serving different neighborhoods. This is one of the worst places on a project to dig without exact locates and the approved dig plan.
  • Water, heat, and pests inside. A roof leak, a failed cooling unit, or pest entry can damage electronics and fiber terminations that serve many people. From outside, the clues are stained walls, damaged vents or louvers, and cooling equipment that is visibly broken or not running on a hot day when it normally would be. Report clues. Do not enter to investigate.
  • Unauthorized entry and theft. Secure network buildings are targets for vandalism and for theft of batteries, copper, and equipment. An open gate, a cut fence, or a forced door at one of these sites is a security event. Report it and stay out.
  • Bad records and bad patching inside. If the frame records do not match the actual patching, troubleshooting for a whole area slows down and a working customer can be disconnected by mistake during a change. Outside plant crews contribute to this problem when feeder fibers are terminated or labeled differently from the design. The fix a beginner controls is simple: terminate and label exactly to the project records, and report any mismatch you find instead of improvising.
  • Confusing the site with something else. Mistaking a hub hut for a general storage cabinet, a staging point, or an abandoned enclosure leads to blocked access, damaged vents, or material stored against a generator exhaust. If a structure has a power meter, conduit entries, fiber markers, and a lock, treat it as a live facility until project records prove otherwise.

What Should Someone Notice in the Field?

Your job with these facilities is to recognize them, note their exterior condition from a safe and authorized position, and respect the access boundary without exception.

  • Identify the facility type if you can. Central office or headend building, or smaller hub hut or cabinet? Note the clues you used: building size, satellite dishes, generator, fence, signage, site code, and converging feeder routes. If the clues do not settle it, record the site as an unidentified secure facility and ask through project channels.
  • Note the origin relationship. Which feeder routes leave the site, and in which directions? On project drawings, which neighborhoods or terminals trace back to this building? Connecting the building to its routes is the recognition skill this lesson is building.
  • Check the exterior condition from outside the fence or from your authorized position. Gate and doors closed and locked? Fence intact? Pad and access path clear? Vents, louvers, and cooling units visibly intact and unblocked? Any sign of water ponding, erosion against the pad, vehicle damage, or forced entry?
  • Look at the building entry area without touching it. Are conduit entries and cable transitions intact, with no hanging, cut, or exposed cable? Are fiber warning signs and route markers present where you would expect them near the entries?
  • Note anything abnormal and report it the same day through the project process: an open or damaged door or gate, a sounding alarm, visible damage, or signs of break in. A generator running during a known outage is expected; a generator running with no known reason is worth an exact, factual report.
  • Respect the access boundary without exception. These are restricted access facilities. Do not enter a central office, headend, hub building, fenced yard, or cable vault without explicit authorization for you, for that site, and for that visit, plus any escort or credential the provider requires. A door being unlocked or open is not authorization.
  • Do not open hut or cabinet doors, frame panels, or entry covers to look inside, photograph inside, or check whether equipment is running. Your observation stops at the exterior.
  • Do not touch, move, splice, patch, or test any fiber or equipment at or inside these facilities unless your role, training, and written assignment specifically cover that work. Outside plant crews terminate at the building entry and frame only as the project directs. Active electronics are for qualified and authorized personnel.
  • Treat electrical service, generators, fuel, and battery systems at these sites as hazards to stay clear of, not systems to inspect or adjust.
  • Reading this lesson teaches you to recognize these facilities and their exterior condition. It does not qualify you to enter one, work inside one, or work on the electronics, power plant, or live fiber terminations inside one.

Key Terms

  • Central office (CO). The telephone company name for the origin facility for an area. Historically the building housing the telephone switch for that area. In fiber work, the building that houses access electronics such as OLTs and terminates outside plant fiber on a distribution frame. Also called an exchange or, in North America, a wire center.
  • Headend. The cable provider name for the equivalent origin facility. The master facility where signals are received from sources such as satellite and off air broadcasts, processed, and inserted into the cable distribution system, along with data and voice services.
  • Hub site. A smaller secondary distribution facility fed from a central office or headend, serving a portion of the service area. May be a small building, a hut, or a large cabinet with active electronics. It shortens outside plant runs and divides a large area into smaller serving areas.
  • Optical line terminal (OLT). The provider side endpoint of a passive optical network, housed in a central office, headend, or hub. It converts signals between the provider core network and the fiber plant, manages traffic, and controls communication with many customer optical network terminals.
  • Passive optical network (PON). A fiber architecture in which feeder fiber from an OLT is split passively, without powered equipment in the outside plant, to serve many customers. The outside plant between the OLT and the customer is passive. The endpoints are powered.
  • Optical network terminal (ONT). The powered device at the customer premises, from Lesson 10, that converts the light signal from the fiber into electrical signals customer devices can use. The far end of the PON from the OLT.
  • Fiber distribution frame / optical distribution frame. The rack or frame system inside a facility where outside plant cables terminate and are organized for splicing, termination, storage, and patching. Often shortened to FDF or ODF. It is the organized boundary between inside plant and outside plant.
  • Patch panel. A panel of connector ports, mounted in a rack or frame, where fiber cables terminate so they can be connected to equipment or to each other with patch cords for testing, changes, and troubleshooting.
  • Feeder fiber / feeder cable. The high fiber count outside plant cable that runs from the central office, headend, or hub out toward distribution points in the service area. It is the first outside plant segment after the facility.
  • Inside plant / outside plant. Inside plant is the equipment and cabling inside the facility, including electronics and frames. Outside plant, or OSP, is the cable plant outside the building. The distribution frame is where the two meet.

Check Your Understanding

  1. A telephone company and a cable company each build fiber to the home in neighboring towns. Each has one main origin building. What will each company probably call its building, and what is the same about the two buildings underneath the names?
  2. What does an OLT do, where is it housed, and what does it communicate with at the customer end of the network?
  3. A crew member wants to stage reels in the flat side yard of a windowless brick building with no sign on it, because the yard is convenient. What should happen before anything is staged there, and which clues say the building is a live central office?
  4. Where does outside plant fiber terminate inside one of these facilities, what is that termination structure called, and why is the cable terminated shortly after entering the building?
  5. Why can a problem inside one of these buildings affect a whole town area, when a cut drop affects only one customer?

Answer key

  1. The telephone company will probably call its building a central office. The cable company will probably call its facility a headend. Underneath the names, both house the active electronics that originate service, terminate outside plant feeder fiber on a distribution frame or patch panels, provide power with backup and cooling, and operate as secure restricted access facilities.
  2. An OLT is the provider side endpoint of a passive optical network. It converts signals between the provider core network and the fiber plant, manages traffic, and controls the PON. It is housed in a central office, headend, or hub site. At the customer end it communicates with optical network terminals, the powered ONTs at customer premises, through passive splitters in the outside plant.
  3. The staging plan stops until the building is identified from its clues and project records. The clues are the fenced rear yard with a generator enclosure, the bank of large conduits leaving the back wall into the street easement, the access reader beside the heavy rear door, the cooling units sized for equipment, and the placard with a site code and provider contact number. The building is the central office for the area, its yard is a secure operations area that authorized crews must be able to reach at any hour, and the feeder on the drawings terminates at its frame. Material goes somewhere that blocks nothing and touches nothing live.
  4. Outside plant fiber terminates on a fiber distribution frame, also called an optical distribution frame, or on patch panels mounted in that frame system. There, each fiber is spliced to a connectorized pigtail or terminated so it can be patched to equipment. It is terminated shortly after entry in part because outside plant cable does not provide the indoor fire protection required inside buildings, and in part so connections stay organized, testable, and recorded in one place.
  5. Because service is aggregated at the facility. One OLT and one frame serve many customers through shared feeder fiber and splitters, so a power, electronics, or frame problem at the origin affects every customer fed from that equipment. A drop, by contrast, serves one premises, so damage to a drop affects only that one customer.

Lesson Takeaway

A central office, a headend, and a hub are the same idea under provider specific names: the secure facility where active electronics originate service and where outside plant fiber begins and ends. You now read these places the way the field story’s crew learned to read them: by power, cooling, conduit convergence, security, and records, and you treat any name sign as the least reliable clue on the site. Connect every facility you meet to the routes it feeds, note its exterior condition from outside the boundary, and hold the boundary completely. No entry, no opening, and no touching without explicit authorization.

Sources and Technical References

  • The Fiber Optic Association (FOA), “Basic Rules for Cable Installation and Termination in the CO/HE/POP” by Vladimir Grozdanovic. Guidance on termination of optical cables in central office, headend, and point of presence facilities on patch panels and optical distribution frames, and on why outside plant cables are terminated shortly after building entry. https://foa.org/tech/ref/install/Basic%20Rules%20for%20Cable%20Installation%20and%20Termination%20in%20the%20CO-HE-POP.pdf
  • The Fiber Optic Association (FOA), “The FOA Reference For Fiber Optics: Fiber To The Home: Multiple Dwelling Units.” Background on FTTH architecture and delivery of voice, data, and video services from the provider facility to subscribers. Used at a concept level only. http://thefoa.org/tech/ref/appln/FTTH-mdu.html
  • Wikipedia, “Telephone exchange.” Summary of central office as a Bell System term for the switching facility and building housing inside plant equipment, and of wire center usage in North America. Used for terminology history, not for construction requirements. https://en.wikipedia.org/wiki/Telephone_exchange
  • Wikipedia, “Cable television headend.” Summary of a headend as the master facility for receiving television signals for processing and distribution over a cable system, and of typical security fencing, sturdy purpose built construction, and cooling. https://en.wikipedia.org/wiki/Cable_television_headend
  • CTC Technology and Energy, “The State of the Art and Evolution of Cable Television and Broadband Technology” (2014). Glossary definitions used in summary form: a headend receives satellite and off air video feeds and inserts signals into the cable system and includes data and voice switching, and hubs are key facilities served by the network backbone and typically connected to each other and the headend over redundant fiber paths. https://www.ctcnet.us/wp-content/uploads/2014/01/SeattleCATVTechnologyReport.pdf
  • FS.com, “OLT vs ONT: What Are the Key Differences?” Overview of the OLT positioned at the service provider central office as the control point for the PON, managing traffic to and from ONTs at customer premises, and converting signals between the broader network and the PON. https://www.fs.com/blog/olt-vs-ont-what-are-the-key-differences-4161.html
  • Lightwave, “Architecture Choices in FTTH Networks.” Describes centralized split architecture with a splitter in a fiber distribution hub connected by a single fiber to a GPON OLT in the central office, and cascaded alternatives. Used to distinguish a hub site from a fiber distribution hub cabinet. https://www.lightwaveonline.com/fttx/cables-enclosures/article/16673516/architecture-choices-in-ftth-networks
  • Clearfield, “FieldSmart Fiber Distribution System (FDS) Patch Panel: 72 Port.” Manufacturer application note describing a high density fiber distribution patch panel providing an interconnect or cross connect environment in central office and headend environments. Used as an example of manufacturer documentation for frame and panel equipment, not as a universal requirement. https://www.seeclearfield.com/assets/documents/legacy/app-guide-pages/clearfield-fiber-distribution-system-fds-patch-panel-72-port.pdf
  • Corning, “Centrix System: Central Office / Headend.” Manufacturer description of a cross connect frame system for jumper connections between indoor and outdoor cables, distribution fibers, and active electronics in the central office, and of use in space constrained hubs and hub sites. Used as an example of manufacturer documentation. https://www.corning.com/optical-communications/in/en/home/applications/central-office-headend-solutions/solutions/centrix/centrix-cabinets.html

Previous lesson: Lesson 11: ISP vs. OSP |
Back to Level 1 hub
| Next lesson: Lesson 13: What Is Feeder Fiber?