Introduction
Public right of way is land, and the legal rights in that land, held for public transportation and the utility uses the controlling public agency allows inside it. The word public describes who the corridor serves and who controls it. The word public does not mean the ground is open for anyone to occupy, store material on, or build in without written authorization.
This lesson opens Level 6, Understand Permission to Build. Lesson 21 introduced right of way as the road corridor. This lesson goes one level deeper on the public form of that corridor: who owns it, who controls it, why fiber work inside it still needs a permit or another written authorization, and where the limits on that work come from.
What This Lesson Gives You
- State whether a given stretch of public ROW is held in fee or held as an easement, and explain why the difference changes what the underlying owner may still do there.
- Name the agency that controls a given segment of public ROW, and explain why an authorization from one agency does not carry into the next agency segment.
- Explain why being inside public ROW still requires a permit, a use and occupancy agreement, or another written authorization before fiber work starts.
- Read a permit for its work limits: the location, the extent of work, the traffic protection, the restoration, and the conditions that apply inside the ROW lines.
- Recognize a private use or an unauthorized placement inside public ROW and route it as an encroachment question to the controlling agency.
Start With the Basics
Think about a public library. Anyone in the community may walk in, sit down, and read. That public access does not let a visitor move in furniture, store boxes in the lobby, or run a private shop from a reading table. Staff control the building. A group that wants to use a meeting room for its own purpose asks for the room, follows the conditions staff set, and leaves the room as it found it.
Public ROW works in a similar way. A public right of way, usually shortened to public ROW, is a corridor of land held for public travel and for the public facilities the controlling agency allows in it. Travelers may pass through it freely. Passing through is different from occupying it. Placing a cable, a handhole, a reel, or a spoil pile in the corridor is occupancy, and occupancy is controlled work.
Hold three ideas and the rest of the lesson follows from them:
- Public ROW is held for transportation first. Roads, sidewalks, drainage, and the safe movement of people are the reason the corridor exists.
- A public agency controls the corridor. That agency decides which other uses may share the corridor, where they may sit, and under which conditions.
- Permission to build in public ROW is written, specific, and limited. The document names the work it covers. Work outside the document is unauthorized work, even when the ground itself is public.
What Is It?
Public ROW has two parts that always travel together: a physical strip of land, and a legal interest in that strip held for public use.
The federal definition used for federal aid highways states the physical and legal parts together. Under 23 CFR 645.207, right of way is real property, or interests in real property, acquired, dedicated, or reserved for the construction, operation, and maintenance of a highway in which federal aid or direct federal highway funds are or have been involved. Under 23 CFR 710.105, which covers the federal aid right of way program, right of way is real property and rights in that property obtained for the construction, operation, maintenance, or mitigation of a transportation or related facility funded under Title 23 of the United States Code. Both definitions describe land plus rights, obtained for a transportation purpose. State law and local ordinances define ROW for state, county, and city roads in their own wording, and the controlling definition for a given segment is the one in the law and records for that segment.
The legal interest comes in two common forms. The form matters because it decides what rights remain with a private owner underneath the corridor.
- Fee ROW. The public agency owns the land itself. Fee ownership, also called owning the fee or fee simple ownership, is full ownership of the land, subject to the laws that govern public land. In fee ROW, the agency holds the ground, the surface, and the space below and above it that the deed covers.
- Easement ROW. The public agency holds an easement over land that a private owner still owns. An easement is a legal right to use part of land owned by someone else for a stated purpose without owning the land. In easement ROW, the agency holds the right to use the strip for road and allowed utility purposes. The underlying owner keeps ownership of the land and keeps any use of it that does not interfere with the public use. A private owner in easement ROW cannot build over the corridor, block it, or place facilities in it in a way that conflicts with the road use, and the agency cannot use the strip for purposes outside the easement terms.
A city definition shows both forms side by side. The City of Naples, Florida defines right of way to include a strip of land dedicated as an easement or deeded in fee simple ownership to the public and accepted by the city, occupied or intended to be occupied by uses such as a street, a sidewalk, drainage, water and sewer mains, power lines, and similar public infrastructure, and the definition covers the ground surface, the air space above it, and the area below it. A Minnesota statute gives a local government version of the same idea. Minnesota Statutes Section 237.162 defines public right of way as the area on, below, or above a public roadway, highway, street, cartway, bicycle lane, and public sidewalk in which the local government unit has an interest, including other dedicated rights-of-way for travel purposes and utility easements of local government units. Wording differs by state and by city. The structure is the same: a defined area, a public interest in that area, and a public purpose for it.
The agency that holds and manages the corridor is the controlling agency for that segment. Controlling agencies include:
- A state department of transportation for state highways.
- A county road authority for county roads.
- A city public works or transportation department for city streets.
- Another public owner named in the records for a specific facility, where the records say so.
Control follows the segment. One route can pass through state ROW, county ROW, and city ROW in a single day of work. Each segment answers to a different agency, with its own policy, its own permit process, and its own conditions.
Public ROW also has a priority order built into federal rule. Under 23 CFR 1.23, all real property, including air space, within the right of way boundaries of a federal aid project must be devoted exclusively to public highway purposes, and the state highway department is responsible for preserving the ROW free of public and private installations, facilities, and encroachments, except for uses the rule allows or approves. Under the same section, and subject to 23 U.S.C. 111, temporary or permanent occupancy or use of ROW for nonhighway purposes may be approved by the FHWA Administrator only when the Administrator determines the use is in the public interest and will not impair the highway or interfere with the free and safe flow of traffic. Transportation is the primary use. Every other use is secondary, conditional, and approved.
What Does It Look Like?
Public ROW has no single look, because the corridor holds many different things and its edges live in records. Lesson 21 taught the roadside pattern: traveled way in the middle, shoulders, ditch or curb, and an outer band where utility facilities usually sit. This lesson adds the control pattern a beginner should learn to read on a public segment.
Look for these signs of public control:
- Road signs, traffic signals, street lights, and pavement markings installed and maintained as public facilities.
- Sidewalks, curb ramps, crosswalks, and bicycle facilities built for public travel.
- Drainage structures that serve the road: ditches, culverts, inlets, and storm lines.
- Utility facilities placed in an organized band: pole lines, pedestals, handholes, marker posts, and valve or manhole covers that follow the corridor rather than a private yard pattern.
- Agency markers, survey monuments, and posted permit or project signs that tie the segment to a public owner or a public project.
- Maintenance activity by a public crew or a public contractor: mowing, sweeping, snow work, pavement repair, and ditch work performed as corridor upkeep.
Look for these signs that a use may be private or unauthorized, which makes it a question to report rather than a pattern to copy:
- A fence, wall, hedge, or gate built across or deep inside the corridor band shown on the project drawings.
- Signs, displays, parked equipment, stored material, or a structure placed in the corridor with no permit sign and no project record behind it.
- Landscaping, irrigation, or a driveway extension that occupies the outer band where the drawings show open corridor.
- Fresh ground disturbance, a trench, or a facility placement with no locates, no traffic control, and no authorization in the project file.
None of these observations settles ownership or permission by itself. A mowed strip can be fee ROW maintained by the agency, easement ROW mowed by the underlying owner, or private yard. Field appearance raises the question. Records, plats, ROW plans, and the controlling agency answer it.

What Does It Do?
Public ROW does its work through control. The corridor gives the public a continuous strip for travel, and the controlling agency protects that strip so travel, drainage, and future road work remain possible.
It holds transportation as the primary use. The traveled way, shoulders, sidewalks, drainage, slopes, signs, and clear sight lines at intersections and driveways all sit inside the corridor because the road needs them. When a secondary use conflicts with the road use, the road use governs. Federal rule states that priority directly for federal aid ROW in 23 CFR 1.23, and state and local ROW policies apply the same priority under their own law.
It gives utilities a shared, managed place to run. Roads go where people live, so utility networks follow roads. Federal policy in 23 CFR 645.205 states that accommodating utility facilities on the ROW of a federal aid or direct federal highway project is in the public interest when the use and occupancy do not adversely affect highway or traffic safety, do not otherwise impair the highway or its aesthetic quality, and do not conflict with federal, state, or local laws or regulations. That managed sharing is called utility accommodation: the placement of utility facilities inside highway ROW under the controlling agency accommodation policy and written approval. The American Association of State Highway and Transportation Officials, called AASHTO, publishes the Guide for Accommodating Utilities Within Highways and Freeways for agencies to use when they regulate utility use and occupancy of public ROW. The guide addresses agency regulation of the corridor. The legal right of a utility to use or occupy the ROW comes from law and the controlling agency, not from a guide. A guide never grants permission. Law and the controlling agency do.
It sets the terms for every secondary use. Under 23 CFR 645.211, each state transportation department must maintain a utility accommodation policy, and the regulation states that the Federal Highway Administration should use the current editions of two AASHTO publications, A Guide for Accommodating Utilities Within Highway Right-of-Way and the Roadside Design Guide, to assist in evaluating whether those policies are adequate. State standards for regulating utility use and occupancy must address how utilities are accommodated and maintained so the highway and traffic safety are protected. Under 23 CFR 645.213, the written arrangements for a utility to cross or otherwise occupy highway ROW, generally in the form of use and occupancy agreements, must describe the requirements for location, construction, protection of traffic, maintenance, and access restriction, and must address the extent of liability and responsibility for future adjustment of the utility, plus the action taken for noncompliance. In plain terms, the corridor comes with written terms, and the terms travel with the permission.
It preserves the corridor for future public work. Roads are widened, rebuilt, and regraded. Drainage is enlarged. Intersections gain turn lanes and signals. An agency that lets the corridor fill with unrecorded private uses loses the room its own future projects need. Preserving ROW free of encroachments, as 23 CFR 1.23 requires for federal aid projects, protects that future room. The same protection explains why an agency can require an occupying utility to adjust or relocate a facility when a highway improvement requires it, under the terms of the agreement, the accommodation policy, and the rights the utility holds.
Where Does It Fit?
Public ROW sits underneath every permission decision in Level 6. The lessons after this one each take one permission instrument in turn. This lesson supplies the ground those instruments act on.
- Private property, Lesson 117, is the contrast case: land where no public corridor exists, where entry and building need the owner right directly.
- A utility easement, Lesson 118, is a specific right over a specific parcel. Public ROW can itself be held as an easement, and a route also uses separate utility easements where it leaves the public corridor.
- A municipal permit, Lesson 119, is a city written authorization for specified work in city ROW.
- A DOT permit, Lesson 120, is the state version of the same instrument for state highway ROW.
Three permission instruments appear again and again in public ROW work. They do different jobs, and one never replaces another:
- A franchise is a grant from a local government, where state law and local ordinance provide for one, that allows a company to use public ROW to provide a service under stated conditions. Whether a franchise, a license, or another local authorization is the required operating instrument depends on the jurisdiction. A franchise answers the question of whether the provider may operate in that jurisdiction ROW at all. A franchise is a general operating right for a service area, defined by the local law and the franchise document.
- A permit, including a use and occupancy agreement, is written approval for a specific installation or a specific body of work in a specific segment, under stated conditions. Under 23 CFR 645.211, all utility installations made on highway ROW are subject to written approval by the state transportation department, except where the use and occupancy agreement itself provides otherwise for matters such as maintenance, service connections on highways other than freeways, or emergency operations. A permit answers the question of whether this work, in this place, built in this way, may proceed.
- A ROW use agreement is the agreement form federal rule uses for a nonhighway use of ROW. Under 23 CFR 710.105, a ROW use agreement covers real property interests, through an instrument such as a lease, a license, or a permit, for use of ROW for nonhighway purposes where the use is in the public interest, stays consistent with the continued operation, maintenance, and safety of the facility, and will not impair the highway or interfere with the free and safe flow of traffic. Federal rule grants those rights only for a specified period of time, because the property may be needed later for highway purposes or another Title 23 purpose. Federal Highway Administration guidance from June 28, 2017 explains the fork: occupancy as a utility is handled under 23 CFR Part 645, and an applicant who does not qualify as a utility under the applicable state law definition may instead request occupancy under the ROW use agreement provisions in 23 CFR 710.405. Any nonhighway use of ROW requires a ROW use agreement and approval under that guidance.
A fiber segment in public ROW normally needs the chain to line up: a provider with the right to operate where a franchise or a similar local authorization is required, a project design that places the plant inside the ROW lines at a location the accommodation policy allows, and a written permit or agreement for the work itself, issued by the agency that controls that segment. A break anywhere in the chain leaves the segment unauthorized, even when every other link is in place.
The level of government also fits in a fixed order:
- Federal rules frame federal aid highways: 23 CFR Part 645 for utility accommodation, 23 CFR Part 710 for ROW and real estate, and 23 CFR 1.23 for the highway purposes rule.
- State law and the state DOT accommodation policy are the working rules for state highways, and state law also frames much of county and city ROW practice.
- County and city ordinances, ROW ordinances, and permit conditions govern local streets and local ROW management.
- The project permit, plans, and contract documents apply all of the above to one segment of one job.
Where the exact width of the corridor, the allowed placement inside it, a fee, a work window, a restoration standard, or a submittal requirement is needed, the source is the controlling agency policy and the project documents for that segment. No general lesson states those values, because they are set segment by segment and agency by agency.
What Is at Stake
The road itself. Public ROW exists so the road can operate safely today and be rebuilt tomorrow. A facility placed in the wrong part of the corridor can narrow drainage, block sight distance, sit in a future widening footprint, or force an emergency repair crew to work around unrecorded plant. The accommodation policy and the permit exist to place secondary uses where they do the least harm to the primary use.
Stop work, removal, and relocation cost. Work placed in public ROW without the required written approval, or outside the limits the approval sets, is unauthorized work. State law, the accommodation policy, and the agreement terms govern what the controlling agency may require for that work, which can include stopping the work, moving or removing the facility, and restoring the corridor, and those documents also govern who bears the cost of the correction. A segment built twice costs far more than a permit review waited on once.
Future adjustment liability. Occupancy in public ROW is conditional by design. The written agreement addresses who bears the cost and responsibility when a highway improvement later requires the utility to adjust its facility, as 23 CFR 645.213 requires the agreement to state. A builder who treats public ROW placement as permanent and unconditional misunderstands the ground it occupies.
Private encroachment pressure. Public ROW that looks empty attracts private uses: fences, signs, storage, parking, and plantings. State examples show how directly agencies treat those uses. Oklahoma law states that ROW acquired by the Department of Transportation or a county is held inviolate for state highway, departmental, or county purposes, that no physical or functional encroachments or uses are permitted within it, and that building a structure on or overhanging the ROW is unlawful and a public nuisance, with exceptions stated in the section, including the lawful use of the ROW for public utility facilities. Missouri Department of Transportation policy defines a ROW encroachment as the placement or maintenance of unauthorized items, or the performance of unauthorized activities, on state ROW, and lists items such as signs and fences among unauthorized items. A fiber crew that adds its own unauthorized staging, storage, or placement to that pressure becomes part of the problem the agency is charged with clearing.
Records and trust. Agencies issue future permits to builders whose past work landed where the permit said it would land, restored the corridor, and closed with accurate records. A crew that builds beyond its authorization teaches the controlling agency to inspect that builder harder, condition that builder heavier, and trust that builder less on every segment that follows.
Safety. Corridor work happens beside live traffic, drainage, and other utilities. Permit conditions on traffic protection, work areas, and access exist because the corridor is a shared public space with the public moving through it. Work performed outside the permit limits can also fall outside the traffic control and safety setup the permit required, which exposes workers and travelers to a setup nobody planned.
What Does Good Look Like?
- The project file names the controlling agency for every segment of the route, segment by segment: state, county, city, or another public owner shown in the records.
- The file shows whether each segment is fee ROW or easement ROW where the records establish it, and the design respects the rights that follow from that form.
- A franchise or other operating authorization is in place where the jurisdiction requires one, and a written permit or use and occupancy agreement covers the work on each segment, issued by the agency that controls that segment.
- The permit conditions are read before mobilization and briefed to the crew: allowed location inside the corridor, work limits, traffic protection, restoration, and any access restrictions.
- Plant, staging, spoil, and equipment all stay inside the limits the permit authorizes. Storage and staging outside those limits sit on ground the project separately has the right to use.
- Drainage, sidewalks, driveways, and sight lines keep working during the work, and disturbed corridor is restored as the permit requires.
- A private use or an older unauthorized placement found inside the corridor is reported to the project and the controlling agency channel. The crew works around it as directed and never treats it as permission for its own placement.
- As built records show where the plant sits relative to the ROW lines, so the agency and the next project start from an accurate corridor record.
From the Field
Picture a fiber crew starting a buried segment where a county road meets a city street. The project file holds a county permit for the county road portion. The drawings show the route turning at the intersection and continuing along the city street, inside city ROW, to reach the next handhole location.
On the first morning, the foreman stages a reel and a spoil pile on a wide grass area inside the city ROW near the corner, and the crew prepares to bore the city block under the county authorization. The area looks like one continuous roadside. The grass, the ditch, and the pole line run through the intersection with no visible break.
An inspector reviewing the segment asks a short question: which document authorizes the work on the city side of the intersection? The file has no city answer. The county permit names county ROW and county conditions. The city segment answers to the city public works department, under the city ROW ordinance and the city permit process. The provider franchise position for the city, and the city permit for this installation, were still moving through the project permitting queue.
The crew holds the city block. Boring stops at the intersection. The reel and the spoil pile move to a staging area the project has the right to use on the county side, clear of the corridor limits the county permit sets for storage. The crew builds the county segment the county permit authorizes, and the permitting staff carry the city authorization to completion through the city process.
The city permit arrives with its own conditions for the block, covering the placement inside the corridor and the restoration of the sidewalk area the work crosses. The crew returns, builds the city block under the city document, and closes the segment with one continuous record that shows two authorizations for two segments of one route.
The decision rule: public ground answers the question of who controls the corridor, and the permit for that segment answers the question of whether the work may proceed there. A route crosses an agency line the same way it crosses a property line, and work stops at that line until the authorization for the next segment is in hand.
What Can Go Wrong?
Treating public as permission. A crew sees public ground, open grass, and an existing pole line, and starts work with no written authorization for that segment. Public ownership or public control never authorizes a specific installation. The permit or agreement does.
Carrying one agency authorization into the next agency segment. A state permit does not authorize city ROW work. A county permit does not authorize state highway work. Each controlling agency approves occupancy in its own corridor, under its own policy.
Confusing a franchise with a permit. A franchise can establish that a provider may operate in a jurisdiction. A franchise does not approve the location, the method, or the conditions for a specific installation. Work built on a franchise alone, where a project permit is required, is unpermitted work.
Building in easement ROW as if the agency owned the fee. In easement ROW, the underlying owner keeps rights that do not interfere with the public use. Work that needlessly destroys owner improvements, blocks owner access beyond the easement terms, or occupies ground outside the easement strip creates a dispute the project records will not support.
Staging and storing in the corridor without authorization. Reels, spoil, pipe, and parked equipment placed in ROW outside the permit limits are occupancy too. Permit conditions and agency policies commonly restrict storage in the corridor, and unauthorized storage draws the same encroachment response as unauthorized plant.
Copying an existing private encroachment. A fence, sign, or structure already sitting in the corridor without authorization proves only that an encroachment exists. Copying its line, tying into it, or placing plant by reference to it spreads the error into the new work.
Ignoring the future adjustment term. A design that places plant with no regard for a planned road improvement, or a builder who never reads the adjustment term in the agreement, sets up a relocation argument the documents already answered. The term was in the file before the work started.
Assuming the corridor width from the last job. ROW widths and allowed placement zones are set in the records and the accommodation policy for that road. A width or an offset carried from another road, another county, or another state has no standing on this segment.
What Should Someone Notice in the Field?
- Identify the controlling agency for the ground you are standing on, and confirm the segment limits where that agency control begins and ends.
- Confirm the written authorization for your segment is in the project file, and compare your work location against the location and limits the document allows.
- Check whether staging, spoil, and parked equipment sit inside the authorized limits, or on separate ground the project has the right to use.
- Read the corridor as a transportation facility first: traveled way, shoulders, sidewalk, drainage, signs, and sight lines all have priority over the space your work wants.
- Note fences, signs, stored items, structures, and plantings inside the corridor band that the drawings do not show, and report them as possible encroachments through the project channel.
- Note any work by others in the corridor with no visible permit sign, locates, or traffic control, and report it rather than treating it as a model to follow.
- Check that drainage paths, driveway access, sidewalk passage, and intersection sight lines remain open while your work occupies the corridor.
- Report any point where the drawings, the permit limits, and the ground disagree, and hold the affected work until the project and the controlling agency resolve the conflict.
- Know the boundary: recognizing public ROW, reading its control pattern, and checking your work against a permit are field awareness tasks. Granting permission, issuing a permit, deciding an encroachment, surveying a ROW line, and performing regulated or hazardous work belong to the controlling agency, licensed professionals, and qualified workers named in the project documents. Reading this lesson does not qualify anyone to do that work.
Key Terms
Public right of way (public ROW): Land, and the legal rights in that land, held for public transportation and for the utility and other uses the controlling public agency allows inside it, covering the surface, the space above it, and the ground below it as the controlling definition states.
Fee ROW: Public ROW where the public agency owns the land itself in fee simple ownership.
Easement ROW: Public ROW where the public agency holds an easement for road and allowed utility purposes over land a private owner still owns.
Controlling agency: The public agency that owns or manages a ROW segment and sets the conditions for using it, such as a state department of transportation, a county road authority, or a city public works department.
Utility accommodation: The managed placement of utility facilities inside highway ROW under the controlling agency accommodation policy and written approval, governed federally for federal aid highways by 23 CFR Part 645 and in practice by state and local policies.
Use and occupancy agreement: The written arrangement, often issued as a permit, that sets the terms under which a utility may cross or occupy highway ROW, including location, construction, traffic protection, maintenance, access restrictions, future adjustment responsibility, and noncompliance action.
Franchise: A grant from a local government, where state law and local ordinance provide for one, that allows a company to use public ROW to provide a service under stated conditions. Whether a franchise, a license, or another local authorization is the required operating instrument depends on the jurisdiction. A franchise covers operating rights in a jurisdiction and does not approve a specific installation.
ROW use agreement: An agreement, through an instrument such as a lease, a license, or a permit, that allows a nonhighway use of ROW when the use is in the public interest, stays consistent with the operation, maintenance, and safety of the facility, and does not impair the highway or interfere with traffic. Federal rule grants those rights only for a specified period of time, because the property may be needed later for highway purposes or another Title 23 purpose.
Encroachment: An unauthorized placement, structure, stored item, or activity inside ROW, or a placement outside the limits its authorization allows.
Work limits: The location, extent, and conditions a permit or agreement authorizes for a specific body of work inside ROW. Work beyond those limits is unauthorized work.
Check Your Understanding
- A segment of road ROW is held as an easement over private land. The underlying owner wants to build a small storage shed inside the strip. What does this lesson say about that plan, and what may the owner still do with the land?
Answer: The owner keeps ownership and keeps uses that do not interfere with the public road and allowed utility use. A shed inside the corridor that occupies the strip and conflicts with the road use interferes with the easement purpose and is an encroachment question for the controlling agency. The owner may continue uses that stay clear of the public use, under the easement terms and local law.
- Why does fiber work inside public ROW still need a written permit or agreement, when the corridor is public?
Answer: Public describes who the corridor serves and who controls it. Federal policy allows utility accommodation in federal aid highway ROW only when the use does not harm highway safety, impair the highway, or conflict with applicable law, and state accommodation rules require written approval for utility installations on highway ROW. The permit or use and occupancy agreement sets the location, construction, traffic protection, maintenance, and adjustment terms for that specific work.
- What is the difference between a franchise and a project permit in public ROW work?
Answer: A franchise is a grant from a local government, where state law and local ordinance provide for one, that allows a company to use public ROW to provide a service under stated conditions. Whether a franchise, a license, or another local authorization is the required operating instrument depends on the jurisdiction. A permit or use and occupancy agreement approves a specific installation in a specific segment, with its location, methods, and conditions. A franchise does not approve a specific build, and a permit does not grant operating rights across a jurisdiction.
- In the From the Field scenario, why did the crew stop at the intersection, and what did the crew do while the city authorization was completed?
Answer: The county permit authorized work in county ROW only. The city block sat in city ROW under a different controlling agency, and no city authorization was in the file. The crew held the city block, moved staging to ground the project had the right to use, and built the county segment the county permit authorized. The city block was built later, under the city permit and its conditions.
- A foreman points to a fence and a row of stored trailers already sitting inside the corridor and says the corridor is clearly treated as open ground on this road. How does this lesson answer that claim?
Answer: An existing unauthorized placement is an encroachment, and agencies are charged with preserving ROW free of encroachments. An older encroachment grants no rights and sets no precedent a crew may copy. The observation gets reported through the project channel, and the crew work stays inside its own written authorization.
Lesson Takeaway
Public ROW is public in purpose and public in control. The corridor belongs to the transportation use first, the controlling agency manages every secondary use inside it, and fiber work proceeds segment by segment under written authorization that names the work and its limits. After this lesson, an open grass strip beside a road reads as managed public ground with an owner, a policy, and a permit process, and the first field question on any public segment is simple: which agency controls this ground, and which document authorizes this work here?
Sources and Technical References
23 CFR 645.205 and 23 CFR 645.207, Utility Accommodation, Subpart B. Section 645.205 states the federal policy that accommodating utilities on federal aid highway ROW is in the public interest when the use does not adversely affect highway or traffic safety, impair the highway or its aesthetic quality, or conflict with federal, state, or local law. Section 645.207 defines right of way and utility facility for this part: https://www.law.cornell.edu/cfr/text/23/645.207
23 CFR 645.205, Utility Accommodation policy, Subpart B text: https://www.govinfo.gov/link/cfr/23/645?link-type=pdf§ionnum=207&year=mostrecent
23 CFR 645.211, State Transportation Department Accommodation Policies, requiring state accommodation policies and standards for regulating utility use and occupancy of highway ROW, stating that all utility installations on highway ROW are subject to written approval by the state transportation department except as the use and occupancy agreement provides, and referencing the AASHTO Guide for Accommodating Utilities Within Highway Right of Way as an evaluation aid: https://www.govinfo.gov/content/pkg/CFR-2024-title23-vol1/pdf/CFR-2024-title23-vol1-sec645-211.pdf
23 CFR 645.213, Use and Occupancy Agreements (Permits), stating the required content of the written arrangements for a utility to cross or occupy highway ROW, including location, construction, traffic protection, maintenance, access restriction, future adjustment liability, and noncompliance action: https://www.law.cornell.edu/cfr/text/23/645.213
23 CFR 1.23, Rights of Way, stating that real property within ROW boundaries of a federal aid project must be devoted exclusively to public highway purposes, that the state must preserve ROW free of installations, facilities, and encroachments except as allowed, and that other occupancy may be approved only when it is in the public interest and will not impair the highway or interfere with the free and safe flow of traffic: http://www.law.cornell.edu/cfr/text/23/1.23
23 CFR 710.105, Definitions, defining right of way as real property and rights in it obtained for a transportation facility funded under Title 23, and defining a ROW use agreement as an interest granted through an instrument such as a lease, license, or permit for a nonhighway use that is in the public interest and consistent with the operation, maintenance, and safety of the facility: https://www.law.cornell.edu/cfr/text/23/710.105
Federal Highway Administration, Memorandum, Utility Accommodation and Other Uses of Highway Right of Way, June 28, 2017, explaining that utility occupancy is governed by 23 CFR Part 645, that nonhighway uses require a ROW use agreement and approval, and that an applicant who does not qualify as a utility under the state law definition may request occupancy under 23 CFR 710.405: https://www.fhwa.dot.gov/utilities/170628.cfm
American Association of State Highway and Transportation Officials, Guide for Accommodating Utilities Within Highways and Freeways, 1st Edition, 2024, merging and updating the earlier AASHTO highway and freeway utility accommodation publications and covering subjects from functional classification to utility permits and alternative uses of ROW: https://aashtojournal.transportation.org/aashto-issues-new-state-dot-right-of-way-guidebook/
Minnesota Statutes Section 237.162, Public Rights of Way Definitions, defining public right of way as the area on, below, or above a public roadway, highway, street, cartway, bicycle lane, and public sidewalk in which the local government unit has an interest, including dedicated ROW for travel and utility easements of local government units: https://www.revisor.mn.gov/statutes/cite/237.162
Oklahoma Statutes Title 69, Section 1208, stating that ROW acquired by the Department of Transportation or a county is held inviolate for highway, departmental, or county purposes, that encroachments and structures in the ROW are prohibited and treated as a public nuisance, with exceptions stated in the section, including lawful public utility facilities: https://law.justia.com/codes/oklahoma/title-69/section-69-1208/
Missouri Department of Transportation, Engineering Policy Guide, Category 140, Encroachments and Items Permitted on MoDOT Right of Way, defining a ROW encroachment as the placement or maintenance of unauthorized items or the performance of unauthorized activities on state ROW: https://epg.modot.org/index.php/Category:140_Encroachments_and_Items_Permitted_on_MoDOT%E2%80%99s_Right_of_Way
Graphic Brief 1
Graphic title: Public ROW: Public in Purpose, Controlled in Use
Main objects: A cross section of one public road corridor drawn left to right: a private parcel at the far left, the ROW band in the middle, and a private parcel at the far right. Inside the ROW band, left to right: a grass outer band with a pole line and a buried fiber line shown as a dashed line, a ditch, a shoulder, the traveled way in the center, a second shoulder, a sidewalk, and a second grass outer band with a handhole. A control post symbol stands at the top of the ROW band: a small agency sign panel over the whole band. Two holding symbols sit over the ROW band: a deed symbol over one half labeled Fee, and an easement document symbol over the other half labeled Easement.
Placement: Title at the top. Cross section across the middle, with the ROW band clearly wider than the traveled way. Private parcels outside the ROW lines on both sides, drawn in a different marker color. The agency sign panel centered above the ROW band, with thin lines dropping to both ROW lines to show agency control over the whole band. Fee and easement symbols placed over separate halves of the same band. White space at the bottom for the key teaching point.
Labels: Public ROW. Traveled way. Shoulder. Ditch. Sidewalk. Pole line. Buried fiber. Handhole. Private parcel. ROW line (from records). Controlling agency. Fee ROW: agency owns the land. Easement ROW: agency holds the right, owner keeps the land.
Arrows and relationships: One double headed arrow spans the full ROW band, labeled Public ROW. One shorter double headed arrow spans only the traveled way, labeled Road. Blue arrows run from the agency sign panel down to a permit document symbol placed over the fiber line, showing occupancy happens by written approval. A red circle and slash sits over a small private storage box drawn faintly in the outer band, showing private storage is an unauthorized use.
Important technical details: The fiber line and the handhole sit inside the ROW band, under the permit document symbol. The private parcels sit fully outside the ROW lines. The fee and easement halves form one continuous corridor with no gap at the middle, showing the holding form can change along a route while the corridor continues. No width, depth, offset, fee amount, or dimension number appears anywhere on the board, since those values come from the records and the permit for the segment.
What not to show: No crew, vehicle, or excavation in progress. No fence drawn on a ROW line. No numbers of any kind. No decoration, shading, or logos.
Key teaching point: Public ROW is one managed corridor. The public agency controls the whole band, the holding can be fee or easement, and fiber occupies the corridor only under written approval.
Graphic Brief 2
Graphic title: One Route, Two Agencies, Two Authorizations
Main objects: A plan view of one route running left to right across the board, crossing a vertical agency boundary line near the middle. The left segment is labeled County ROW with a county permit document symbol above it. The right segment is labeled City ROW with a separate city permit document symbol above it. The fiber route is drawn as a solid line in the county segment and stops at the boundary line with a stop hand symbol. In the city segment, the same route continues as a dashed planned line to a handhole symbol. A staging area symbol sits on the county side, on a separate lot outside the corridor, labeled Authorized staging. A second staging symbol inside the city corridor is crossed out in red.
Placement: Title at the top. Route across the middle. Agency boundary line vertical, clearly labeled, dividing the board into two control zones with different light marker outlines. County permit symbol above the left zone. City permit symbol above the right zone, drawn with a clock symbol beside it to show authorization still in process. Stop hand exactly on the boundary line where the solid fiber line ends. White space at the bottom for the key teaching point.
Labels: County ROW. City ROW. Agency boundary. County permit: this segment. City permit: required for this segment. Authorized staging (separate ground). No staging in the corridor beyond permit limits. Work stops at the agency line.
Arrows and relationships: A green arrow runs along the built county segment. A red stop arrow points at the boundary line from the county side. A dashed blue arrow runs along the planned city segment, showing design intent without authorization to build. No arrow crosses the boundary as built work.
Important technical details: The corridor itself is drawn continuous through the boundary, because the roadside looks continuous. The control zones change at the boundary even though the grass and the ditch do not. The two permit symbols are separate documents with separate condition tags, showing one authorization never covers the other agency segment. No road names, place names, dates, widths, or permit numbers appear anywhere on the board.
What not to show: No built fiber line inside the city segment. No crew working past the stop hand. No single permit symbol covering both zones. No people, logos, or decoration.
Key teaching point: A route crosses an agency line the same way it crosses a property line. Each segment needs the written authorization of the agency that controls that segment, and work stops at the line until that authorization is in hand.