What You Are Learning
By the end of this lesson you will be able to define a utility map in plain words and explain what it is trying to show. You will be able to name the kinds of utilities a utility map commonly shows, both above ground and underground, and the kinds of information that may appear with each line, such as owner, type, size, material, and status, when the source provides it. You will be able to explain where the information on a utility map comes from, including old records, as built drawings, visible surface features, field survey, surface geophysical designating, and exposure at a specific point. You will be able to describe the four quality levels in the American Society of Civil Engineers guideline ASCE 38, from Quality Level D to Quality Level A, and explain that a quality level describes how the information was obtained and how much confidence it deserves, not a guaranteed accuracy number. You will be able to tell the difference between a utility map, a construction print, and a geographic information system. You will be able to explain why utility maps can be wrong, incomplete, or out of date, even when they look neat and precise. Finally, you will be able to state the safety boundary clearly: a utility map is a starting point for planning and awareness. It never replaces a locate request through the one call system, field locating, or careful exposure work by qualified people where the job and the law require it.
Start With the Basics
Outside plant, usually shortened to OSP, is the part of a fiber network built outdoors: cables on poles or underground, conduit, handholes, splice closures, and the structures that hold them. New OSP work rarely goes into empty ground or onto empty poles. Streets and easements already carry water lines, sewer lines, gas lines, electric lines, and other communication lines, some active and some abandoned.
A utility is a service system and the physical plant that delivers it. In this lesson, utility also means that physical plant itself, such as a pipe, a cable, a duct, or a conduit run. An existing utility is a utility that is already in place before the new work starts, whether or not the new job owns it.
Before anyone designs or digs, the project team needs a picture of what is already there. That picture, drawn on a map of the project area, is the subject of this lesson.
Define four working ideas first.
A record is any stored information about a utility, such as an old drawing, an as built, a maintenance note, a repair record, or a database entry. A record says what someone documented at some time. It is not a fresh measurement by itself.
As built means documentation made or corrected after construction to show what was actually placed, as opposed to what was designed before construction. An as designed drawing shows the plan before the work. Confusing the two is a common source of map error, because field changes made during construction may never have been drawn into the plan.
Field verification means checking a record against the actual site by observing, surveying, detecting, or exposing the utility, using a method matched to the decision that depends on it. Different methods give different levels of confidence, and this lesson explains that range.
A quality level, in the ASCE 38 sense used later in this lesson, is a professional opinion of the reliability of utility information, based on the means and methods used to collect and depict it. It tells a reader how the information was earned. It does not promise that every line is within a stated distance of the real utility, and no universal tolerance should be read into it.
Hold one idea before you read the rest. A line on a utility map looks equally certain whether it came from a surveyed exposure or from a hand sketch copied for decades. The drawing style is not evidence. The source and the quality level are the evidence.
What Is It?
A utility map is a drawing, a printed sheet, a digital file, or a map view that shows the known or believed locations of existing utilities in a defined area, in relation to streets, property features, project limits, and each other. It is a compilation. Someone gathered information from several sources, at possibly different dates and by different methods, and depicted the results together in one view so a project team can plan around what is already there.
A utility map commonly covers some or all of the following, depending on the area and the records available: water mains and services, sanitary sewer and storm sewer, natural gas lines, electric power lines above ground and underground, communication lines including telephone, cable television, and fiber, and related structures such as manholes, valve boxes, hydrants, pedestals, poles, and handholes. Where the source provides it, a map entry may also identify the utility owner, the type and size of the facility, the material, whether it is shown as active or abandoned, and a depth or elevation. Where the source does not provide a detail, a careful map leaves it unstated rather than filling it in by guess.
A utility map may be produced by a utility owner for its own system, by a city or agency for its area, by a designer or engineer compiling records for a specific project, or by a subsurface utility engineering provider engaged to investigate and depict utilities for that project. Subsurface utility engineering, usually shortened to SUE, is a branch of engineering practice described by the Federal Highway Administration and by ASCE as managing risks associated with utility mapping at appropriate quality levels, utility coordination, relocation design and coordination, condition assessment, communication of utility data, and related work. SUE is a process that combines records research, surveying, and geophysics under professional direction. It is not a single device or a single site visit.
Name what a utility map is not. It is not proof that a utility is exactly where the line sits. It is not proof that no other utility exists where no line is drawn. Absence of a line can mean no utility, or it can mean no record. It is not a locate mark on the ground, and it is not permission to dig. It is information of a stated or unstated quality, to be used with field methods and damage prevention duties that other lessons in this curriculum cover.
It also helps to separate three related things that field conversation often blends.
A utility map shows what already exists, as far as its sources know. A construction print, taught in Lesson 72, shows what is to be built. A project drawing may overlay the two, showing existing utilities beneath or beside the proposed route so conflicts can be seen, and that combined view is often what a crew actually holds. When you read such a sheet, keep the two questions separate: which lines claim to describe the ground as it is, and which lines instruct the new work.
A geographic information system, usually shortened to GIS, is a software based system for storing, managing, analyzing, and displaying information tied to real world locations, in layers. A utility map can be one printed or on screen view taken from GIS data. GIS can also hold roads, parcels, buildings, and many other layers beside utilities. The difference matters for accuracy. Putting record data into GIS does not improve the record. A line that was approximate on paper stays approximate in GIS, even though the screen renders it sharp and zoomable. GIS is a container and a tool. It is not a quality level.
What Does It Look Like?
A utility map has a recognizable shape across its paper and digital forms.
The base is the ground itself, drawn in plan view, meaning looking down from above as a street map does. You will usually see street names and centerlines or curbs, project limits, right of way or easement lines where they are shown, and surface features that help a reader orient: buildings, driveways, intersections, and visible utility structures. A north arrow and a scale statement or scale bar should appear, as on other plan documents in this level, so the reader can orient the sheet and judge distances honestly.
Against that base, each utility is drawn as a line following its believed path, usually with a line style, a color, or a label that identifies the type of utility and often the owner. The legend for the map or drawing set defines those line styles, colors, symbols, and abbreviations for that document. Read the legend for the map in your hands. Colors and styles are not universal across owners and designers, and a color you learned on one system does not transfer by right to another.
Structures appear as symbols at points along the lines: a manhole where a sewer run can be accessed, a valve box over a water valve, a pedestal for a communication line, a pole carrying aerial lines. Those visible points matter. On many maps they are the most trustworthy features shown, because they can be found and surveyed on the surface, while the buried line between them is inferred to connect them.
Good utility maps also carry information about themselves. Look for a title block or map notes identifying who compiled the map, when, from what sources, and for what project or area. Look for quality level designations, where the SUE process has been used, shown per utility or per segment. Look for notes that state limits in plain words, such as records based, not field verified, or similar wording in the language that map uses. Look for a date. A map with no date, no source note, and no compiler is a map whose confidence you cannot judge, and that is itself useful information.
In digital form, the same map may appear as layered GIS data, as a computer aided design file, or as a static portable document that freezes one view at one date. A static file does not update when the underlying data changes. Two people can hold two different dates of the same named map and disagree while both read honestly. Naming the date out loud is a basic field habit with maps, just as naming the revision is with prints.
Physical appearance in the field is ordinary. The utility map may be a sheet inside the print set, a separate exhibit in the job file, or a view on a tablet in the truck. What matters is not the medium. What matters is whether the reader can answer, from the document itself or from the job file: whose map is this, what sources built it, how old is it, and what quality level, if any, does it claim.

What Does It Do?
A utility map does four jobs.
First, it gives early awareness. In planning and design, it shows the project team the general congestion of an area, which utilities are present, and where conflicts with a proposed route are likely. The Federal Highway Administration describes Quality Level D information, the records only level, as useful for exactly this stage: project planning and route selection, where an overall feel for utility congestion guides early choices. Early awareness is real value. It is not final certainty, and using a planning level map as a digging level document is a misuse.
Second, it focuses field effort. A map tells investigators and locators where to look, which owners to coordinate with, which visible structures to survey, and which crossings are critical enough to justify stronger verification, up to exposure at a specific point where the project requires it. Without the map, field effort is spread blind. With it, effort goes where the risk is.
Third, it supports coordination. Utility owners, designers, agencies, and contractors can point to the same depiction while discussing a conflict, a relocation, or a crossing. SUE practice exists in large part to make that conversation happen during design, when moving a proposed line on paper is cheap, instead of during construction, when a conflict is discovered by an excavator. A widely cited study commissioned by the Federal Highway Administration and performed by Purdue University, analyzing 71 highway projects, concluded that spending on SUE returned several dollars in avoided cost for each dollar spent. That figure belongs to that study and those projects. It is cited here only to show why owners invest in better utility information early, not as a promise for any specific job.
Fourth, it becomes part of the record. The map used on a project, with its sources and dates, shows what the team knew and when they knew it. After construction, updated records and as builts should feed back into the owner records and GIS, so the next project starts from better information than this one did. When that feedback step is skipped, the next map inherits the same errors, and the lesson repeats.
Notice what the map does not do. It does not mark the ground. Paint and flags placed under the one call damage prevention process are a separate field act by the facility owners or their locators, governed by state law and the locate request for that dig. It does not expose anything. It does not grant clearance to dig at a crossing. Those steps have their own qualified people, their own timing, and their own rules, which this lesson does not replace or summarize into a shortcut.
Where Does It Fit?
The utility map appears at the start of a project and stays useful, in updated forms, through its end.
In planning, records are requested from utility owners and agencies, old project plans and as builts are gathered, and a first composite depiction is compiled. Composite here means combined from multiple sources into one view. At this stage most information is records based, the lowest quality level, and the map is used for route selection and for scoping what further investigation the project needs.
In design, the map is improved where the design needs it. Visible above ground features are surveyed and plotted, and the record lines are correlated against them. Where the proposed work crosses or runs close to existing utilities, surface geophysical methods may be used to designate the approximate horizontal position of buried utilities. At critical conflict points, a project may obtain precise horizontal and vertical information by actually exposing the utility and measuring it, usually at a specific point. The designer then routes the new work using information whose quality is known segment by segment, rather than uniformly guessed.
In construction, the crew reads the utility information as awareness: where known utilities run, where records were weak, and where extra care and the required locate and exposure steps apply. The construction duties themselves, including the one call request, waiting for responses, respecting marks, and the methods qualified people use inside a tolerance zone, are governed by state damage prevention law, the job documents, and company procedure. A tolerance zone is the width of space around a utility where special care rules apply under applicable law. Its width and its rules are set by the state and the job, and this lesson states no width as a rule. If the field reveals a utility the map did not show, or shows one in a different position, that is new information to report through the job process the same day, so the record can be corrected and the work can proceed on direction.
After construction, the map and the project utility information feed the owner records. New plant is recorded, relocated utilities are updated, and abandoned facilities are noted, where the owner process captures them. That closing step decides whether the next project map is better or merely newer.
Inside this curriculum, this lesson sits in Level 4, Read the Construction Information, after the lessons on prints, sheets, legends, and symbols, and alongside the existing utility recognition taught in Level 3. It teaches you to read the document that claims to describe what is already in the ground, and to ask the question that makes the document useful: how was each part of this picture obtained.
Why Does It Matter?
It matters because underground work is done in shared ground. A strike on a gas line, an electric line, a water main, or a communication cable can injure people, cut service to a neighborhood or a hospital, close a road, and stop a project. Many strikes involve failures that have nothing to do with maps, such as digging without a locate request. This lesson covers the map specific share of that risk: work planned or performed as if a record line were a measured fact.
It matters because map errors are quiet. A wrong line does not announce itself. The map looks complete, the route looks clear, and the first evidence of error can be the excavator finding the utility directly. Every step that improves the information before digging, records research, surface survey, designating, and exposure at critical points, moves the discovery earlier, to a stage where it costs time on paper instead of damage in the ground.
It matters because confidence has to be matched to the decision. Choosing between two broad route corridors can responsibly use records level information. Designing a bore crossing close to a gas line cannot responsibly rest on the same level of information. The quality level system exists so that matching is explicit instead of assumed. A reader who cannot tell which parts of a map are records and which parts are field verified cannot make that match, and will either over trust weak information or waste strong effort where it is not needed.
It matters because the map you use today becomes the record someone else uses later. Reporting a found utility, a moved utility, or a wrong line through the job process is not paperwork for its own sake. It is how the shared picture improves. The Federal Highway Administration history of SUE notes that utility records provided by companies were, in its words, more often than not inaccurate and incomplete, which is one reason surface geophysics and vacuum excavation were brought into engineering practice in the first place. Treating records as a starting point, and field truth as the correction, is the professional habit this lesson is building.
What Does Good Look Like?
A good utility map identifies itself. The compiler, the date, the project or area, the sources used, and the limits of the information are stated on the map or in its accompanying notes. A reader does not have to guess who made it or from what.
Quality is stated, not implied. Where the ASCE 38 process is used, utilities or segments carry a quality level designation, and the depiction distinguishes records based segments from surveyed, designated, and exposed segments. Where no formal quality level is assigned, the notes say plainly what was and was not done, for example that locations come from owner records and visible features only, with no geophysical designating performed.
Above ground evidence agrees with the drawing. Visible structures shown on the map are found in the field in the positions plotted, and visible structures found in the field that are missing from the map are reported and added through the project process. Correlation between the surface picture and the record lines is the Quality Level C step, and skipping it leaves obvious checks undone.
The map is current for its stated purpose and it is singular. The team works from one identified version with a date, and older versions are removed or marked superseded in the job file. When new field information changes a line, the change is issued, not penciled differently into three separate copies.
Its limits are respected in use. Planning decisions are made from it freely. Design decisions at close crossings cite stronger verification where the project requires it. Digging decisions never rest on it alone. The locate request is made, marks are obtained, and exposure or other required steps at critical points are performed by the people qualified and assigned to perform them, through the job process.
Finally, discrepancies flow back. A utility found where none was drawn, a line found offset from its depiction, or an abandoned facility found live are each written down with location detail and reported the same day. Good maps are maintained by the people who use them reporting what the ground actually said.
What Can Go Wrong?
Records were never accurate. Some utilities were installed without good documentation, installed in a different position than the design showed, or documented against landmarks that have since changed or disappeared. The Federal Highway Administration identifies recurring causes in its SUE materials: records referenced to changed surface features, no centralized records storage, no standard format, and no clear responsibility for keeping records. A map compiled from those records inherits every one of those weaknesses.
Records were accurate once and went stale. Utilities are relocated for road work, repaired after damage, extended to new customers, and abandoned in place. Each change is a chance for the record to fall behind the ground. A map printed from a database that was never updated after a relocation shows a trench that no longer carries the line, and may miss the line where it now runs.
Digitizing added new errors. Old paper records are scanned, traced, and converted into design files and GIS layers. The Federal Highway Administration warns that digitizing record data into computer aided design or GIS can result in even more errors, because tracing, scaling, and coordinate mistakes enter during conversion, while the output looks more precise than the source ever was.
Private and unrecorded facilities are missing. Owner records cover owner systems. Private lines on the customer side of a meter or service point, old farm or site lines, and facilities installed by parties who kept no central record may not appear in any owner response. A clean area on the map can still contain plant that nobody documented.
Abandoned utilities mislead in both directions. An abandoned line drawn without its status can send a crew avoiding a pipe that carries nothing, while an abandoned line removed from records entirely can still be struck as a physical object in the trench path. Status is information. A map that does not state it leaves the reader guessing.
Quality levels get ignored or inflated. A reader who treats a records based composite as if every line were exposed and surveyed has inflated the map. A compiler who depicts designated or exposed results on some segments, without labeling which segments earned which level, invites that inflation. The defense is labeling, and a reader habit of asking which level each critical segment carries before relying on it.
The map gets used as a locate. This is the most dangerous failure. A crew that digs from the map, without the locate request, without marks, and without the required care at crossings, has skipped the entire damage prevention process that exists to find the utility in the ground, in the present tense. The map describes the past as recorded. Locating addresses the ground as it is. Reading this lesson does not qualify anyone to perform locating, designating, or exposure work, and it does not soften that boundary in any way.
What Should Someone Notice in the Field?
Notice the map credentials before you notice its lines. Can anyone on the job answer, from the document or the job file: who compiled this map, when, from what sources, and at what quality level for the segments that matter today? If nobody can answer, the map is being used on appearance alone, and that is a stop and check item to raise.
Notice agreement between the map and the surface. Walk the visible evidence: poles, pedestals, manholes, valve boxes, hydrants, handholes, and markers. Features on the ground that are missing from the map, or features on the map that cannot be found on the ground, are both findings. Either one lowers confidence in the buried lines drawn between them, and both should be reported in plain words with the location.
Notice paint and flags as a separate layer of truth. Locate marks on the ground come from the locate process for a specific request and area, not from the project map. Where ground marks and map lines disagree, do not average them and do not silently choose one. Report the disagreement through the job process and let the qualified locators and the supervisor resolve it before digging in that spot.
Notice the segments with no stated quality. At a crossing that matters, a line with no quality level, no source note, and no date deserves a direct question: what do we actually know about this utility? Asking that question early is the job of every reader. Answering it with stronger investigation is assigned through the project, to qualified people, by the methods the project specifies.
Notice new information being captured. When the ground reveals something the map missed, notice whether it gets written down with a location reference, a description, and the date found, and whether it reaches the supervisor the same day. A crew that reports findings is improving the record. A crew that covers a surprise and moves on is passing the same surprise to the next crew.
Notice your own limit, and state it. Noticing a weak map, a missing feature, or a disagreement between marks and lines, and raising it clearly, is every worker job. Performing geophysical designating, interpreting its results as a quality level deliverable, exposing a utility, or declaring a crossing clear for excavation are qualified tasks with their own training, equipment, and legal duties. This lesson qualifies you to read and question a utility map. It qualifies you for none of those tasks.
Practical Example
The following example is hypothetical. It is invented to teach utility map reading, not to describe a real job, a real map, or a real company.
Hypothetical example: a clear corridor that was not clear. A hypothetical fiber crew is preparing to bore along a hypothetical commercial street for a hypothetical network owner. The job file includes a utility composite map compiled by the designer from owner records. Its notes state the sources honestly: locations from utility owner records and a survey of visible surface features, with quality levels assigned per segment. Most water and sewer segments carry Quality Level C, records correlated with surveyed manholes and valve boxes. One gas segment crossing the proposed bore path carries Quality Level D, records only, because no surface feature sits on that segment to correlate against.
The foreman, Jordan, reads the quality designations before the route walk, not after. On the walk, Jordan finds the manholes and valve boxes where the map shows them, which supports the Quality Level C segments. At the gas crossing, Jordan finds no surface feature, and the map note and the Quality Level D label agree that this segment is the weakest information on the sheet. Jordan raises that specifically: the design crossing rests on records only.
Through the project process, the owner representative upgrades that crossing before construction. A SUE provider designates the gas line using surface geophysical methods and surveys the designated marks, raising the segment depiction to Quality Level B, and the designated position sits noticeably to one side of the record line. Because the bore design passes close to that position, the project obtains Quality Level A information at the critical point by exposing the line with nondestructive excavation and measuring it, performed by the qualified crew assigned to that work. The design is adjusted on paper, the map in the job file is reissued with the new quality levels and the corrected line, and only then does the construction sequence proceed, with its normal locate request and marks obtained for the dig through the one call process.
The lesson is in the sequence. The original map was not useless and it was not trusted blindly. Its own labels told the reader exactly where it was strong and where it was weak. The reader believed the labels, asked for stronger information only where the decision was critical, and let qualified people produce it. The corrected line cost effort during design. Found by a bore head during construction, it would have cost far more, in every sense that matters.
Key Terms
Utility map: a drawing, printed sheet, digital file, or map view that shows the known or believed locations of existing utilities in a defined area, compiled from records, survey, and field investigation sources of stated or unstated quality.
Utility owner: the company, agency, or party that owns and operates a utility system, such as a water utility, a gas company, an electric utility, or a communication provider, and that keeps records of its own plant.
Record: any stored information about a utility, such as an old drawing, an as built, a maintenance or repair note, or a database or GIS entry. A record documents what someone recorded at some time.
As built: documentation made or corrected after construction to show what was actually placed, as distinct from an as designed drawing, which shows what was planned before construction.
Geographic information system (GIS): a software based system for storing, managing, analyzing, and displaying information tied to real world locations in layers. GIS is a container for map data. Placing record data in GIS does not raise its quality.
Subsurface utility engineering (SUE): a branch of engineering practice that manages risks associated with utility mapping at appropriate quality levels, utility coordination, relocation design and coordination, condition assessment, communication of utility data, utility relocation cost estimates, implementation of utility accommodation policies, and utility design, combining records research, surveying, and geophysics under professional direction.
Quality Level D: under ASCE 38, information derived from existing records or oral recollections. It is the lowest reliability level and is suited to planning and route selection.
Quality Level C: under ASCE 38, information obtained by surveying and plotting visible above ground utility features and using professional judgment to correlate that information with Quality Level D records.
Quality Level B: under ASCE 38, information obtained through appropriate surface geophysical methods to determine the existence and approximate horizontal position of subsurface utilities. The activity is called designating, and the designated marks can be surveyed and plotted.
Quality Level A: under ASCE 38, precise horizontal and vertical location of a utility obtained by actually exposing it and measuring it, usually at a specific point. Exposure is commonly by nondestructive methods such as vacuum excavation, performed by qualified people.
Designating: using surface geophysical methods to indicate the presence and approximate horizontal position of a buried utility, the Quality Level B activity. Designating does not expose the utility.
Locating, in the SUE sense: obtaining precise position and other data about a utility through its exposure, the Quality Level A activity. This engineering use of the word is distinct from the one call locate marks placed for excavation, which are a separate process under state damage prevention law.
One call system: the notification system, reached in the United States through 811, through which an excavator requests that facility owners mark their utilities before digging, under the damage prevention law of the state where the work occurs. A utility map never replaces this request.
Check Your Understanding
- In your own words, what is a utility map, and what two things does the neatness of its lines tell you nothing about?
- A designer gives you two documents for the same street. One shows existing water and gas lines as believed from records. The other shows the new fiber route to be built. Which is the utility map and which is the construction print, and why does the difference matter when you read a combined sheet?
- Put Quality Levels D, C, B, and A in order from lowest to highest reliability, and name the method that earns each level.
- A utility layer is moved from old paper records into a GIS. A reader says the lines must now be accurate because they are digital and zoomable. What is wrong with that claim?
- A map shows no utility in the path of a planned bore. Name two different reasons the ground could still contain a utility there, and state what the map alone never authorizes the crew to do.
Answer key:
- A utility map is a compiled depiction of the known or believed locations of existing utilities in an area, built from records, surface survey, and field investigation sources. The neatness of its lines tells you nothing about the source of each line or its reliability. A surveyed exposure and a decades old sketch render as equally sharp lines. Source notes and quality levels, not appearance, carry the confidence information.
- The records based depiction of existing water and gas is the utility map information: it claims to describe the ground as it already is, as far as its sources know. The new fiber route is the construction print information: it instructs what is to be built. On a combined sheet the difference matters because the two kinds of lines have opposite jobs. Existing lines are evidence to be questioned and verified to a level matched to the decision. Proposed lines are instruction to be followed unless changed through the design process.
- Lowest to highest: D, then C, then B, then A. Quality Level D comes from existing records or oral recollections. Quality Level C adds surveying and plotting visible above ground features and correlating them with the records. Quality Level B applies appropriate surface geophysical methods to determine existence and approximate horizontal position, called designating. Quality Level A exposes the utility and measures it, obtaining precise horizontal and vertical location, usually at a specific point.
- GIS is a container and display tool, not a method of verification. Tracing record data into GIS changes its format, not its source. The Federal Highway Administration warns that digitizing can add further errors during conversion. The line keeps the quality of the record it came from until field methods earn it a higher quality, no matter how sharply the screen draws it.
- First, the utility may exist with no record reaching the map compiler: a private line, an unrecorded installation, or a facility whose owner records were incomplete. Second, the record may once have existed but the map may be stale or the facility may have been installed or relocated after the map sources were gathered. Absence of a line proves only absence of a record in that compilation. Separately, a utility map never authorizes digging by itself. Excavation requires the damage prevention process for the job and state, including the one call locate request and the other required steps, performed through qualified and assigned people.
Lesson Takeaway
A utility map is a compiled picture of what is believed to be in the ground and on the poles in an area, built from records, surface survey, designating, and, at specific points, exposure. Its value depends entirely on knowing how each part was obtained. ASCE 38 names that range: Quality Level D from records or recollection, Quality Level C correlated with surveyed surface features, Quality Level B designated by surface geophysics, and Quality Level A exposed and measured. Read the source notes, the date, and the quality designations before you trust a line, remember that GIS and neat drafting add format rather than accuracy, and expect records to be incomplete, stale, or wrong in places, because the history of utility record keeping says they often are. Use the map to plan, to coordinate, and to focus verification where the decision is critical. Never use it as a substitute for the locate process or for qualified field work at a crossing. This lesson qualifies you to read a utility map critically and to ask what each line is based on. It does not qualify you to designate, locate, expose, or clear any utility.
Sources and Technical References
- Federal Highway Administration, Subsurface Utility Engineering brochure, describing SUE and the ASCE standard guideline quality levels D through A, with Quality Level D from existing records or oral recollections, Quality Level C from surveying visible above ground features correlated with records, Quality Level B from surface geophysical methods for existence and approximate horizontal position, and Quality Level A from actual exposure and measurement: https://www.fhwa.dot.gov/design/sue/suebrochure.cfm
- Federal Highway Administration, SUE Then and Now, history of subsurface utility engineering, including that records provided by utility companies were more often than not inaccurate and incomplete, and the roles of air and vacuum excavation and surface geophysics in the development of SUE practice: https://www.fhwa.dot.gov/programadmin/history.cfm
- Federal Highway Administration, Applying Subsurface Utility Engineering to Highway and Road Projects, on sources of utility information, poor records practice including records referenced to changed features, no centralized storage, no standard format, and digitizing record data into computer aided design or GIS resulting in further errors and data of unknown reliability: http://www.fhwa.dot.gov/programadmin/sueshow.cfm
- Federal Highway Administration, Avoiding Utility Relocations, Appendix B Best Practices, including that Quality Level D information may provide an overall feel for utility congestion but is often limited in comprehensiveness and accuracy, with usefulness confined to project planning and route selection: https://www.fhwa.Dot.gov/utilities/utilityrelo/b.cfm
- Federal Highway Administration, Sample SUE and Utility Coordination Scope of Work, defining SUE as a branch of engineering practice managing risks associated with utility mapping at appropriate quality levels, and defining a utility quality level as a professional opinion of the quality and reliability of utility information determined by the means and methods of the professional: https://www.fhwa.dot.gov/programadmin/htmldoc4.cfm
Flagged and hedged items: ASCE 38 is cited in its long used 38-02 form in the Federal Highway Administration materials above. A newer edition, ASCE 38-22, was published in 2022 and retains the four quality levels. Readers should verify which edition a specific contract or agency requires, because the contract and the agency specify the governing edition, not this lesson. No accuracy tolerance, depth, clearance, offset, or tolerance zone width is stated in this lesson as a requirement, because ASCE 38 quality levels describe method and reliability, not a universal numeric tolerance, and because depths, clearances, and zone widths are set by the applicable standard, the utility owner, the permit, the state law, or the contract for a specific job. The Purdue University return figure for SUE spending is reported as the conclusion of that named study of 71 highway projects and is not presented as a guaranteed result for any other project. State damage prevention requirements, including one call timing and tolerance zone rules, vary by state and must be verified for the state and job where work occurs.