Lesson 73: How Do You Find Yourself on a Print?

What You Are Learning

By the end of this lesson you will be able to stand on a real street with a construction print in your hands and answer one question with confidence: where am I on this sheet, and where is the work in relation to me? You will be able to find and use the north arrow to turn the print until it matches the ground around you. You will be able to use street names, intersections, stationing, and match lines to narrow your position on the sheet. You will be able to use the sheet index and a key plan to confirm you are even looking at the right sheet. You will be able to pick out landmarks you can see, such as utility poles, handholes, pedestals, hydrants, and street addresses, and match them to their symbols and labels on the print. You will be able to state the two landmark rule used in this lesson: confirm your position with two independent landmarks that agree before you trust that position for work decisions. You will also be able to explain what scale can and cannot tell you on a field print, and what to do when the print and the ground do not line up: stop, protect the work area, and get the mismatch resolved through your supervisor and the job process instead of guessing.

This lesson teaches a practical field reading skill. It does not qualify you to survey, to set or move survey control, to establish property lines or easement boundaries, or to stake construction in place of a licensed surveyor or the party your contract assigns to that work. Finding yourself on a print tells you where you are standing in relation to the drawing. It is not a measurement of record, and it never replaces layout, locating, or verification steps the job requires.

Start With the Basics

A construction print, covered in Lesson 72, is a sheet in a plan set that shows planned work from above in plan view, along with existing features the designer recorded. A plan view is a view looking straight down, as if you were above the ground looking at the streets, poles, and buried routes laid out flat. Outside plant, usually shortened to OSP, is the fiber network built outdoors: poles, conduit, handholes, pedestals, cabinets, and the cable routes that connect them.

Finding yourself on a print means matching a position on that flat drawing to the physical place where you are standing. It sounds simple until you try it on a street you do not know, holding a sheet that may be turned any direction, may show only a short stretch of the route, and may use symbols instead of pictures.

Define the working words this lesson depends on before using them.

Orientation means the direction a sheet is turned in relation to the real world. A print is oriented when the direction at the top of the drawing in your hands matches the direction you are facing on the ground, so left on the paper is left in the field and right on the paper is right in the field.

A north arrow is a small arrow on a plan sheet, usually marked with the letter N, that shows which way is north on that drawing. It is the single most important mark for orientation, because the top of the sheet is not automatically north. Designers rotate plan views to fit long routes on a sheet, so north can point up, sideways, or at an angle, and it can differ from sheet to sheet in the same set.

A landmark, for this lesson, is any feature that appears both on the print and on the ground and that you can identify in both places with confidence. A pole with a number tag, a handhole lid in the sidewalk, a street intersection, a fire hydrant, and a building with a readable address can all serve as landmarks. A patch of grass cannot, because it looks the same in a hundred places.

Stationing is a system for naming positions along a route by distance from a starting point. Lesson 77 teaches stationing in full. For this lesson you only need the basic shape of it: positions along the route carry station labels, and those labels increase in one direction along the route, so they tell you which way along the line you are and roughly how far.

A match line is a marked line on a sheet that shows where the drawing stops on this sheet and continues on another sheet, with a note telling you which sheet holds the continuation. Lesson 74 covers plan sheets and their parts in more detail. For this lesson, a match line matters because standing near one means half of what you need may be drawn on the next sheet.

A key plan, sometimes called a location plan or an index plan on smaller sets, is a small overview drawing of the whole project area with the individual sheets marked on it as boxes or outlines. It shows where each sheet fits in the whole job. A sheet index is the written list, usually on the title sheet of the set, that names every sheet in order. The key plan shows you where. The sheet index tells you what exists.

A control point is a point whose position has been established by survey work, such as a monument, a marker, or a point listed in the project control information. Control points matter in this lesson for one reason only: you may use a visible monument as a landmark, but establishing, moving, or staking from control belongs to surveyors and to the party the contract assigns. Recognizing a point is not the same as being qualified to survey from it.

Hold one idea before you read the rest. You do not find yourself on a print with one clue. One clue can be wrong, copied from an old design, or matched to the wrong look alike feature. You find yourself with a small chain of clues that agree: the right sheet, the right direction, and at least two landmarks that both match. When the clues agree, you can work. When they do not, that disagreement itself is important information, and Section 10 and Section 11 of this lesson explain what to do with it.

What Is It?

Finding yourself on a print is the repeatable process of putting the drawing and the ground into the same frame of reference. In plain terms, it is answering four questions in order.

First, am I holding the right sheet? A route that runs for miles is cut into many plan sheets. The sheet index and the key plan answer this question. So do the street names and station ranges printed along the route on the sheet itself.

Second, which way is this sheet turned? The north arrow answers this question. Until you have found the north arrow and turned the sheet so its north matches real north in relation to your body, every left and right judgment you make from the paper can be exactly backwards.

Third, where along the route am I? Station labels, street intersections, and match lines answer this question. They place you along the line of the work, the way mile markers place you along a highway.

Fourth, exactly where am I standing in relation to the drawn features? Landmarks answer this question. A pole, a handhole, a driveway, a hydrant, or an address that you can see and that is also drawn and labeled on the sheet fixes your position across the route as well as along it.

Notice what this process is not. It is not scaling a distance off the paper and pacing it out as if that settled a work position. It is not following the route line on the sheet and assuming the ground must match it. And it is not a survey. Surveying establishes positions with instruments and records that carry legal and construction weight, and it is done by qualified surveyors under the rules of the state where the work sits. This lesson teaches recognition and cross checking, the reading skill a crew member uses to know which part of the design they are looking at before the qualified layout, locate, and verification steps do their own work.

The process also has a built in honesty rule. Your position on the print is only as good as your weakest clue. If you found the north arrow but matched only one landmark, and that landmark is a pole that could be one of several identical poles in a row, you have a probable position, not a confirmed one. Field language should reflect that. Saying “I believe we are at this pole, and I am checking the next handhole to confirm it” is good field communication. Saying “we are here” on one weak match is how crews bore on the wrong side of a street.

What Does It Look Like?

In the field, finding yourself looks like a short pause before work starts, not like a long study session. Picture the physical scene.

A crew member stands at a street corner or beside a pole, holding either a paper sheet, often a reduced size field print, or a tablet or phone showing the plan set as a PDF. The sheet is turned in the hands, sometimes rotated completely around, until the street layout on the paper runs the same way as the streets on the ground. A second crew member is often looking in the other direction, calling out what is actually there: the intersecting street name from the sign, the pole number from the tag, the handhole in the grass behind the sidewalk.

On the sheet itself, the features that do this work have recognizable looks.

The north arrow is usually a slim arrow or a small circle with an arrow through it, marked N, placed in open space near the plan view, a corner of the drawing area, or next to the title block. State plans preparation manuals commonly require a north arrow and a scale on each plan sheet, placed where they are easy to see. Florida DOT guidance, for example, calls for the north arrow and scale at a point of maximum visibility on the plan view. The exact placement varies by designer, so the skill is to look for it on every sheet, every time, rather than to assume it sits where the last sheet put it.

Street names are printed along the street lines, and intersecting streets are labeled where they cross the route. On a well drawn sheet you can read the name of the street the route follows and the name of each cross street in order. That order is a powerful check: if the cross streets on the ground come in a different order than on the sheet, you are on the wrong sheet, on the wrong stretch, or facing the wrong way.

Station labels appear along the route centerline or the proposed alignment as numbers with tick marks. In the stationing system used on most United States highway and utility plans, one station equals 100 feet. When stationing begins at 0+00 and no station equation intervenes, a label such as 12+50 names a point 1,250 feet along the line from that origin, meaning 50 feet past station 12+00. If stationing begins at another value or a station equation intervenes, find a distance by subtracting station values within the same stationing segment. Lesson 77 builds this out fully. For orientation, what you see is a sequence of labels that increase in one direction. If you walk the route and the labels on the sheet decrease, you are reading the sheet backwards along the route.

Match lines appear as a marked line drawn across the plan at the edge of the drawn area, often dashed or chain style and often drawn heavier than the surrounding lines, labeled with words such as MATCH LINE and a reference to the sheet where the route continues. Style and weight vary by designer, so read the label, not only the line. United States Navy drafting instruction, quoted in standard line convention references, describes match lines the same way: when an object is too large for one sheet, the points where it stops on one sheet and continues on the next must be identified with corresponding match lines. On the ground, a match line has no physical form at all. It exists only on paper, which is exactly why it catches people out. Nothing on the street tells you the drawing changed sheets.

The key plan appears on the title sheet or an early sheet of the set as a small map of the whole route with rectangles showing the coverage of each plan sheet, each rectangle labeled with its sheet number. The sheet index appears nearby as a table listing sheet numbers and sheet titles in order.

Landmarks on the sheet appear as symbols with labels: a small circle or pole symbol with a pole number, a rectangle for a handhole or vault, a pedestal symbol, building outlines with addresses, hydrant symbols, and existing utility lines in their own line styles per the legend, which Lessons 75 and 76 teach. The labels matter more than the symbols for orientation. A pole symbol tells you a pole was recorded there. A pole symbol with the same number as the tag on the pole in front of you tells you that you found yourself.

Whiteboard illustration: find yourself on a print with the right sheet, the north arrow, and two landmarks

What Does It Do?

This skill does four jobs on a fiber construction job.

First, it gets the crew to the right work location. Fiber routes run through neighborhoods where streets repeat, poles look alike, and one block resembles the next. The difference between the correct handhole and a similar handhole one street over is the difference between building the design and building a mistake that someone has to tear out. Finding yourself on the print is how a crew confirms that the structure in front of them is the structure the sheet is talking about, before any digging, boring, or setting work begins.

Second, it makes every other piece of information on the sheet usable. A construction note that says to bore on a particular side of the street, a detail that applies at a specific crossing, and a station range where a method changes all depend on knowing where you are on the sheet. A note read at the wrong location is worse than a note never read, because it gets applied with confidence in the wrong place. Orientation is what connects the notes, symbols, and callouts on the paper to the correct piece of ground.

Third, it catches design and field mismatches early, while they are still cheap to resolve. If the print shows a handhole at a corner and no handhole exists at that corner, or the print shows the route on the east side of the street and the existing plant is clearly on the west side, the crew that found itself carefully is the crew that notices. That notice, raised through the supervisor before work proceeds, is the starting point of the mismatch process that Lesson 95 covers in full. The crew that never oriented itself never notices. It just builds the discrepancy into the ground.

Fourth, it keeps communication precise. When a crew member calls a supervisor, an inspector, or a locator, “we are lost” helps nobody. “We are on sheet 12, at the intersection shown at station 14+00, confirmed by the pole number and the handhole at the corner, and the print shows a second handhole that is not here” tells the listener exactly where you are and exactly what does not match. Good orientation turns a vague problem into a specific question, and specific questions get resolved faster.

Where Does It Fit?

Finding yourself on a print sits near the start of almost every field task in Level 4, and it connects the lessons around it.

Lesson 72 introduced the construction print itself: what a plan set is and what a sheet contains. This lesson is the first skill you use on that sheet when you arrive at the work location. Lesson 74 then takes apart the plan sheet piece by piece, and Lessons 75 and 76 teach the legend and the symbols, which deepen the landmark matching this lesson introduces. A symbol you cannot yet name can still serve as a landmark if its label matches the ground, and the legend lessons will make those matches faster and more certain.

Lessons 77, 78, and 79 teach stationing, offsets, and footage in full. This lesson uses stationing at a recognition level, as a direction and position check along the route. Those lessons turn it into a working measurement language.

This lesson also leans on Level 3. Recognizing existing utilities and their surface evidence, the poles, handholes, pedestals, markers, and locate marks on the ground, is what gives you landmarks to match. A reader who completed Level 3 can look at a corner and inventory what is actually there. This lesson teaches matching that inventory to the sheet.

Finally, this lesson is the front door to Lesson 95, What Happens When the Print Does Not Match the Field, and it shares ground with Lesson 71, What Do You Do When the Field Does Not Match the Locate. The shared principle is identical: when two sources of position information disagree, you stop and resolve the disagreement through the proper process. You do not average them, you do not pick the one you like, and you do not build through the disagreement hoping it resolves itself. This lesson teaches you to detect the disagreement. Those lessons govern the full response, so this lesson points to them rather than repeating them.

In the daily rhythm of a job, the fit is simple. The crew arrives, the lead orients the crew on the print before work is assigned, each crew member who moves to a new sheet or a new stretch repeats the process, and anyone who becomes unsure of their position at any point stops and reorients before continuing. Orientation is not a one time morning event. It is repeated every time the sheet, the street, or the task changes.

Why Does It Matter?

It matters because almost every expensive field error begins as a position error. Crews rarely build the wrong thing on purpose. They build the right thing in the wrong place, on the wrong side of the street, at the wrong structure, or one sheet too far along the route. Each of those errors started with someone who thought they knew where they were on the print and did not check.

It matters because fiber work is tied to exact structures. A splice goes in a specific handhole or closure. A bore crosses under a specific street at a specific crossing with specific existing utilities nearby. A pedestal serves specific addresses. Work placed at a look alike structure down the street does not partly count. It is wrong plant, in the wrong record, and it has to be found, removed or abandoned under the owner process, and rebuilt where the design put it.

It matters because of safety, and this point deserves plain language. Existing utilities sit where the records and the locate marks say they sit in relation to the drawn route. A crew working from a sheet it has oriented wrongly can believe it is clear of a buried facility that is actually in its bore path, because the crew mirrored the street in its head. Orientation errors are not just paperwork errors. They feed directly into the damage prevention system Level 3 taught: correct sheet, correct side of the street, correct understanding of where the marked facilities are in relation to your work. Finding yourself carefully is part of working safely around existing plant. It never replaces the 811 process, the marks, or potholing and verification steps. It makes those steps land in the right place.

It matters because records follow the work. As built documentation, which the Fiber Optic Association design guidance stresses must record the overall route and exact locations, including which side of streets facilities are on and where buried plant and splice closures lie, is only accurate if the crew knew where it was when it built. A crew that built at the wrong location and documented confidently has poisoned the record the next crew, the next locator, and the owner will trust.

It matters because time spent orienting is small and time spent recovering from a wrong location is large. The two landmark check in this lesson takes minutes. Moving a crew, re locating, re permitting, tearing out misplaced work, and repairing trust with an owner or a property owner takes days. Orientation is one of the cheapest forms of quality control on the job.

What Does Good Look Like?

Good orientation follows the same order every time, until the order becomes habit.

Good starts with the right sheet. Before leaving the truck or opening the work, the crew member finds the project in the sheet index, locates the sheet that covers the work area on the key plan, and confirms the sheet in hand by its street names. If the streets on the sheet are not the streets at the work location, nothing else on that sheet gets used until the right sheet is in hand.

Good orients the sheet before reading details. The crew member finds the north arrow, notes where north falls on the sheet, and physically turns the sheet or the tablet view so the drawing aligns with the ground. If you are facing the intersection in the field, the intersection on the paper sits in the same relative direction. A practical check follows: a street that runs to your left on the ground should run to your left on the paper. If it runs to your right, the sheet is upside down in your hands, no matter how the text on it reads. Text direction is a weak clue, because designers place labels to fit the sheet. The north arrow is the authority.

Good then fixes position along the route. The crew member finds the nearest labeled intersection and the station labels near it, and confirms the direction in which stations increase. Walking a short distance, or driving one block, should move the ground features in the same order the sheet shows them: cross streets, driveways, and structures in sequence.

Good confirms with two independent landmarks. Independent means the two landmarks do not depend on each other and are not the same kind of guess twice. A pole number that matches its label on the sheet is one. A handhole drawn at the corner you are standing on, visible in the ground where the sheet puts it, is a second. A street address on a building that the sheet prints beside that building outline is a second or a third. Two landmarks of different types, in different positions, that both agree with the sheet, make it very unlikely you are at a look alike location, because a wrong location would have to fool both checks at once. One landmark is a hypothesis. Two agreeing landmarks are a position.

Good checks scale honestly. The crew member reads the stated scale in the title block or under the plan title, and checks the graphic bar scale printed on the sheet against it. The bar scale is drawn as a small printed ruler divided into feet or meters, and because it is printed as part of the sheet, it shrinks or grows with the sheet if the sheet was copied at a different size. If the bar scale and the stated scale disagree, the print in hand is not at its stated size, and distances measured off it with a scale ruler will be wrong. Written dimensions, station labels, and callouts on the sheet govern over anything you measure off the paper with a ruler. That is a common drafting practice rule, not a trick: figures written on the drawing are the designer stated values, while a paper measurement is only as good as the reproduction. Sheets marked NTS, meaning not to scale, are diagrammatic, and no distance should be scaled off them at all. Scale awareness in this lesson means one thing: use distances off the print for rough orientation, such as judging that a structure is about one block along, and never present a scaled paper measurement as a verified field position.

Good ends with a spoken confirmation. The crew lead states the sheet number, the location in plain words, and the confirming landmarks, and the crew hears it before work starts. “Sheet 12, north side of the Elm Street and 5th Street intersection, stations increasing to the east, confirmed by pole 118 and the handhole at the corner.” Anyone on the crew who cannot match that statement to the ground says so at that moment, while saying so is still free.

What Can Go Wrong?

The failures in this skill are quiet ones. Nobody notices them happening, which is why the checks exist.

The most common failure is assuming the top of the sheet is north. On many route sheets the plan is rotated so a long street fits the page, and north may point to the side or even downward. A crew that reads the sheet as if up were north will mirror the job in its head: east becomes west, the north side of the street becomes the south side, and every offset and side callout gets applied to the wrong ground. The print was never wrong. It was simply never oriented.

A second failure is using the wrong sheet with confidence. Sheets in a route set look alike, streets repeat their patterns, and the correct handhole on sheet 14 can have a near twin on sheet 9. A crew that skips the index and key plan and works from the first sheet whose drawing resembles the corner in front of it can build an entire segment in a location the design never intended.

A third failure is the single landmark match. A crew finds one pole, decides the sheet matches, and stops checking. Poles in a line are deliberately similar, tags can be hard to read or can have been replaced, and a handhole of the same size sits at many corners. The second landmark exists in this lesson precisely because the first landmark, alone, fails in exactly these ordinary ways.

A fourth failure is trusting a scaled distance from a bad reproduction. Field prints are often printed at half size or copied from copies. A distance measured off such a sheet with a ruler can be off by a large factor while looking perfectly precise. The failure is worse than having no measurement, because a precise looking wrong number gets defended. The bar scale check and the rule that written figures govern exist to prevent it.

A fifth failure is following the sheet across a match line without changing sheets. The route line runs off the edge of the drawn area, the crew keeps walking the ground and glancing at the same sheet, and the features stop matching because the drawing they need is on the next sheet. The reverse also happens: a crew flips to the next sheet but keeps reading station direction from the previous sheet, when the new sheet may present the route running the other way on the page.

A sixth failure is treating a phone map or a satellite image as a substitute for the print. A map application can help you reach the neighborhood and can confirm a street name, and there is nothing wrong with using one to travel to the site. But a consumer map shows where you are in the world, not where you are in the design. It does not know the sheet, the stationing, the design side of the street, or the structures the design calls out, and its position estimate can be off by enough to place you at the wrong structure. Use it to arrive. Use the print, oriented and confirmed, to work.

A seventh failure is pressing on when the print and the ground disagree. The sheet shows a handhole that is not there, a pole line on the other side of the street, or a street that dead ends where the sheet shows it running through. Each disagreement has a cause: an old revision, a design that assumed work not yet built, a field condition that changed, or your own wrong position. Guessing which cause it is and building anyway is how small mismatches become strikes, tear outs, and bad records. The correct response is covered next, and it starts with stopping.

What Should Someone Notice in the Field?

Notice orientation first, before content. When you pick up any sheet, your eyes should find the north arrow before they find the work. Notice where north points on this sheet, and notice whether it points the same way it did on the last sheet you used. In a single set, it often does not. Notice the sheet number and title as well, and whether the key plan puts this sheet where you are standing.

Notice street order and street names. Read the cross streets on the sheet in order along the route and compare them with the signs and the visible intersections in order on the ground. Notice any street the sheet shows that you cannot find, and any street in front of you that the sheet does not show. New development, renamed streets, and older designs all produce these gaps, and each one is a signal to slow down and add landmarks before trusting your position.

Notice labeled structures, not just structures. A pole is a weak landmark. A pole whose tag number matches the number printed on the sheet is a strong one. A handhole lid with a size or owner marking that matches the sheet callout is stronger than a handhole shaped patch in the grass. Train your eye to read the small print on the sheet: pole numbers, structure numbers, addresses, and station callouts are the sheet offering you confirmations. Take them.

Notice which side of the street things are on. Side of street is a fast and consequential orientation check in OSP work, because designs specify sides and existing plant occupies sides. If the sheet draws the existing pole line on the side of the street opposite to the poles you are looking at, something is wrong with the sheet, the design stage, or your orientation, and it must be resolved before that sheet guides any placement decision.

Notice station direction by movement. If you walk in the direction the sheet says stations increase and the features you pass appear on the sheet in reverse order, you are oriented backwards along the route even if your north check passed. The two checks catch different errors: the north arrow fixes rotation, and station sequence fixes which end of the stretch you are on.

Notice the edges of the sheet. When the features around you start falling off the drawn area, notice the match line and its sheet reference before you run out of drawing. Notice, too, the limits of the survey or the existing conditions the sheet shows: a sheet may draw existing plant in detail near the route and only roughly farther away, so a distant feature that does not match perfectly is weaker evidence than a near feature that does not match.

Notice your own certainty level and say it out loud. There is a felt difference between “two landmarks agree and the street order matches” and “this pole looks right.” Notice when you only have the second feeling. That feeling is the signal to get the second landmark, not to start the work.

Finally, notice disagreement and treat it as a finding, not an inconvenience. When the print and the ground do not line up after you have checked the right sheet, the north arrow, and two landmarks, notice exactly what disagrees, in specific words: which structure, which side, which street. Specific findings are what your supervisor and the designer need. The response itself is the subject of the next section.

Practical Example

The following example is hypothetical. It is invented to teach the orientation process, not to describe a real job or a real company.

Hypothetical example: a crew finds itself, catches a mirror error, and confirms before boring. A hypothetical two person fiber crew, led by Sam, arrives to place a short underground segment connecting two handholes on a street the print calls Walnut Avenue. Sam opens the plan set PDF on a tablet and goes first to the sheet index, finds the sheets covering Walnut Avenue, then checks the key plan and opens the sheet whose coverage box contains the intersection the crew is parked at. On that sheet, the north arrow points to the left side of the page, not the top, because the designer rotated the route to fit the sheet. Sam turns the tablet so the arrow direction matches the real north the crew establishes from the street layout and a compass application used only as a rough direction aid, and now the drawn intersection sits the same way as the real one.

Sam reads the cross streets in order along the route on the sheet, then looks up and reads the signs in order on the ground. They match. Sam finds the first landmark: a pole at the corner whose tag number matches the pole number printed on the sheet. Good, but Sam does not stop there. The design handhole the crew must open is drawn on the opposite side of the street from the pole, near the corner. Walking to that corner, Sam finds a handhole where the sheet puts it, with the lid marking matching the sheet callout. Two independent landmarks now agree, the street order agrees, and stations on the sheet increase in the direction the foreman said the work runs. Sam states the confirmation out loud, and the crew opens the correct handhole.

The catch in this example comes next, and it is the instructive part. A second crew member, rechecking the sheet while Sam documents the open handhole, notices that the existing duct line the sheet draws entering that handhole from the south is, in the open handhole, entering from the north wall instead. The crew has confirmed where it is standing. The disagreement is now inside the design information itself, not in the crew orientation. Sam does not resolve it by assumption, does not flip the sheet to make it fit, because the two landmarks already fixed the orientation, and does not start the bore. Sam stops the placement work at that structure, keeps the handhole protected, photographs the actual duct entries, and calls the supervisor with the specific finding: sheet number, structure, what the sheet shows, and what the ground shows. That is the handoff point where Lesson 95, on prints that do not match the field, takes over. The lesson of this example is the division of labor: orientation proved where the crew was, and because orientation was solid, the crew could prove the mismatch was real and report it precisely instead of doubting itself or building through it.

Key Terms

Orientation: turning a print so the directions on the sheet match the directions on the ground, so left, right, and side of street judgments from the paper are true in the field.

North arrow: the arrow marked N on a plan sheet that shows which direction is north on that drawing. It governs orientation, and it can point any direction on the page.

Plan north: a north direction adopted for the drawing itself, which on some drawing sets is shown alongside or instead of true geographic north. Where a sheet distinguishes the two, read its notes and use the arrow the sheet provides for orienting that sheet, and ask your supervisor if the distinction is unclear.

Key plan: a small overview drawing of the whole project area, usually on the title sheet or an early sheet, with each plan sheet coverage marked and labeled, so a reader can find which sheet covers a given location.

Sheet index: the written list of every sheet in the set, in order, with sheet numbers and titles, usually on the title sheet. It is the table of contents of the plan set.

Landmark: a feature that appears both on the print and on the ground and can be identified confidently in both places, such as a numbered pole, a handhole, an intersection, a hydrant, or an addressed building.

Two landmark rule: the practice in this lesson of confirming your position with two independent landmarks of different types that both agree with the sheet before trusting that position for work decisions.

Stationing: the system of naming positions along a route by distance from an origin, in which one station equals 100 feet and, when stationing begins at 0+00 and no station equation intervenes, a label such as 12+50 names a point 1,250 feet along the line. Taught in full in Lesson 77.

Match line: a marked line at the edge of the drawn area on a sheet, labeled with the sheet where the drawing continues, showing where this sheet coverage ends and the next sheet coverage begins.

Scale: the stated relationship between distances on the drawing and distances on the ground, shown as a written statement in the title block or under the plan title and often also as a graphic bar scale.

Bar scale: the graphic scale printed on the sheet as a small divided ruler. Because it is printed with the drawing, it changes size with any reproduction of the sheet, so it reveals when a print is not at its stated size.

NTS: an abbreviation for not to scale, meaning the drawing or view is diagrammatic and no distance should be measured off it with a ruler. Written dimensions and labels are the only values to use.

Control point: a point whose position was established by survey work, such as a monument or marker. It may serve as a visible landmark, but establishing or staking from control is survey work for qualified parties.

Check Your Understanding

  1. A plan sheet shows the north arrow pointing toward the bottom of the page. A crew member turns the sheet so the text reads upright and starts calling out sides of the street. What is wrong, and what should the crew member do instead?
  2. Why does this lesson require two independent landmarks instead of one good one before a position is trusted for work decisions?
  3. Your field print was printed at half size. The stated scale and the bar scale on the sheet no longer agree. Which values on the sheet can you still trust for position, and which can you not?
  4. You have confirmed the right sheet, oriented it by the north arrow, and matched a pole number and a handhole. The sheet then shows a second handhole at the next corner that is not on the ground. State your next steps in order.
  5. What is the difference between finding yourself on a print and surveying, and why does that difference matter for what you may do with a control point you can see?

Answer key:

  1. The crew member oriented the sheet by its text instead of by its north arrow. Designers rotate plan views to fit the sheet and place labels to fit, so upright text is no guarantee of orientation. With north pointing down the page, reading the sheet upright mirrors the ground: sides of the street and left and right directions come out backwards. The crew member should turn the sheet until the north arrow direction matches real north in relation to the ground, confirm with street order, and only then read sides and directions from it.
  2. A single landmark can be a look alike. Poles in a line are similar, tags can be misread or replaced, and same size handholes sit at many corners, so one match can be a coincidence at the wrong location. Two independent landmarks of different types, in different positions, must both be fooled at once for the position to be wrong, which is far less likely. One landmark gives a probable position to check. Two agreeing landmarks give a position worth working from.
  3. You can still trust the written information: sheet identity, street names and their order, station labels, structure numbers and addresses, dimensions and callouts written as figures, and the landmark relationships the drawing shows. You cannot trust distances measured off the paper with a scale ruler against the stated scale, because the reproduction changed the size of everything drawn. The bar scale exposes the problem because it shrank with the print. Use the print for orientation and rough judgment of distance, and never present a scaled measurement from it as a verified position.
  4. Stop the placement work that depends on the missing structure. Do not flip the sheet to force a match, because your orientation is already proven by the two landmarks. Protect any open structure, note the disagreement in specific words, which sheet, which structure, what the sheet shows and what the ground shows, photograph the corner from a safe position, and notify your supervisor through the job process so the mismatch is resolved under the print mismatch process covered in Lesson 95. Work that does not depend on the disputed structure follows your supervisor direction.
  5. Finding yourself on a print is a reading and recognition skill: matching the drawing to visible features so you know which part of the design you are looking at. Surveying establishes positions with instruments and records that carry construction and legal weight, and it is performed by qualified surveyors under state rules. You may use a visible monument or control point as a landmark to confirm where you are. You may not establish, move, or stake construction from control based on this lesson, and your print based position never replaces the layout, locating, or verification steps the job assigns to qualified parties.

Lesson Takeaway

You find yourself on a print in a fixed order: get the right sheet from the index and the key plan, orient the sheet by its north arrow and never by its text or by the top of the page, place yourself along the route with street order and station labels, and then confirm the position with two independent landmarks that both agree with the sheet before you trust it. Read scale honestly: written figures, station labels, and callouts govern, a paper measurement is only as good as the reproduction, and a view marked not to scale gives you no distances at all. When the print and the ground still disagree after that work, stop, state the disagreement in specific words, and hand it to the mismatch process. This lesson makes you a careful reader of your own position. It does not make you a surveyor, and it never replaces layout, locating, or verification by the qualified parties your job assigns.

Sources and Technical References

  • Florida Department of Transportation, Plans Preparation Manual, Volume 2, Chapter 10, Roadway Plan and Roadway Plan Profile: the baseline or centerline is centered in the plan portion with stationing running left to right, tick marks are placed at every station, and a north arrow and scale are shown at a point of maximum visibility, preferably in the upper right portion of the plan view: https://fdotwwwalpha.blob.core.windows.net/sitefinity/docs/default-source/content2/roadway/ppmmanual/2013r/volume2/v2chap10.pdf?sfvrsn=3804dbb7_0
  • Florida Department of Transportation, Plans Preparation Manual, Volume 2, Chapter 9, Project Layout: the complete project alignment is shown with the outlines of the plan sheets superimposed on it to depict the sheet sequence in relation to alignment stationing, with each sheet outline containing its plan sheet number, which is the key plan function this lesson teaches: https://fdotwwwalpha.blob.core.windows.net/sitefinity/docs/default-source/content2/roadway/ppmmanual/2013/volume2/v2chap09.pdf?sfvrsn=96514fe4_0
  • Contract Plans Reading training textbook, as reproduced in course materials: in surveying, a station is equal to 100 feet; a point 500 feet from station 0 is station 5; and a location such as Sta. 98+76.54 means a point 76.54 feet ahead of station 98+00, with station labels defining the exact location of items described in the plans: https://www.slideshare.net/slideshow/contractplansreadingtextbook-64987453/64987453
  • Line Conventions, ManufacturingET.org, quoting United States Navy NAVEDTRA 14069 drafting instruction: match lines are used when an object is too large to fit on a single drawing sheet and must be continued on another sheet, the points where the object stops on one sheet and continues on the next must be identified with corresponding match lines, and road plans and maps are given as the typical example: http://www.manufacturinget.org/2011/07/line-conventions/
  • California Department of Transportation, Plans Preparation Manual, Chapter 2, Section 2.5, Layouts, Profiles, and Superelevation Diagrams: match lines are placed when a route is shown on more than one sheet, stationing in most instances progresses left to right on a sheet but in some instances progresses bottom to top, and crossroad stationing can progress differently from mainline stationing, which supports this lesson warning that station direction must be confirmed on each sheet: http://dot.ca.gov/-/media/dot-media/programs/design/documents/cadd/ppm-text-ch2-sect2-5-a11y.pdf
  • Missouri Department of Transportation, Engineering Policy Guide 236.13, Designing Right of Way Plans: plan sheets carry a north arrow on each plan sheet and match lines at the beginning and end of each plan sheet, as standard required sheet elements: https://epg.modot.org/index.php?title=236.13_Designing_Right_of_Way_Plans&diff=cur&oldid=20345
  • City of Petaluma plan organization guidelines, representative of municipal plan set organization: the title sheet includes a complete sheet index, a project description, and a vicinity map, followed by general notes and the plan sheets in a stated order, which is the index and overview structure this lesson teaches the reader to use first: https://storage.googleapis.com/proudcity/petalumaca/uploads/2019/06/Guidelines-for-Plan-Organization-and-Sheet-Identification2020.pdf
  • The Fiber Optic Association, FOA Reference for Fiber Optics, Outside Plant Fiber Optic Network Design, documentation: OSP documentation must record the overall route and details on exact locations, for example on which side of streets facilities are placed, which cable is on poles, and where and how deep buried cables and splice closures lie, which is why side of street and exact structure identification in this lesson matter beyond the day of construction: https://www.foa.org/tech/ref/OSP/design.html

Flagged and hedged items: The two landmark rule is stated in this lesson as the Fiber Done Right field practice taught by this curriculum, not as a requirement quoted from a national standard. No source cited here sets a required number of confirming landmarks, so the rule is presented as a job practice the reader follows under this curriculum and their employer process, not as law or as an industry standard. The statement that written dimensions govern over distances scaled off a drawing is presented as common drafting and construction practice, consistent with how not to scale views and reproduction size changes are treated in drawing reading instruction; specific contracts can and do state their own order of precedence for dimensions, and the contract documents for the actual job govern if they say otherwise. A compass or a phone compass application is mentioned only as a rough direction aid for orientation; this lesson makes no claim about its accuracy, and it never substitutes for the north arrow on the sheet or for survey control. No specific print scale is stated as standard for OSP sheets, because scales vary by designer, sheet type, and project, and any scale quoted as typical would mislead on a real set. The plan north versus true north distinction is described in general terms only, because conventions differ between drawing sets; the sheet own notes and arrows govern on the actual job, and unclear cases are referred to the supervisor rather than resolved by the reader.


Previous lesson: Lesson 72: What Is a Construction Print? |
Back to Level 4 hub |
Next lesson: Lesson 74: What Is a Plan Sheet?