Lesson 63: What Is a Tolerance Zone?

What You Are Learning

By the end of this lesson you will be able to do four things. First, you will be able to define a tolerance zone in plain words. Second, you will be able to build one on paper: start with the width of the buried facility, then add the distance your state sets on each side of it. Third, you will be able to explain why work methods change inside the zone. Fourth, you will be able to explain what the zone does not mean, because the two most common misunderstandings about it both lead to damaged utilities.

This lesson teaches recognition and understanding. Reading it does not qualify you to excavate, to locate utilities, or to work inside a tolerance zone. That work is governed by state law, by your employer’s procedures, and by training and supervision on the job.

Start With the Basics

In earlier lessons you learned that before anyone digs, the excavator contacts the state notification center, often called 811, and facility operators send locators out to mark their buried lines. A locator uses detection equipment to estimate where a buried pipe, cable, or conduit runs, then paints lines and sets flags on the ground above it.

Here is the fact this whole lesson rests on: those marks are approximate. The word approximate means close to the true position, but not exact. Locating equipment reads a signal from below ground. Soil conditions, nearby metal, depth, and how the facility was installed can all shift the reading by inches. A facility can also bend or drift from a straight line between two points. So the paint shows where the facility is believed to be, within a margin of error. It does not show the facility itself, and it gives no depth information at all.

Because the marks carry a margin of error, the law and industry practice draw a wider band around the facility and say, in effect: inside this band, slow down and change how you work. That band is the tolerance zone.

Two terms from earlier lessons matter here. A facility is the buried utility itself, meaning the actual pipe, cable, or conduit in the ground, including its outside wall. Potholing, also called daylighting, means carefully exposing a buried facility by hand digging or vacuum excavation so you can see it and confirm its exact position. Both terms come back below with work attached to them.

What Is It?

A tolerance zone is a horizontal band of ground centered on a buried facility. It is made of three parts added together: a set distance on one side of the facility, the width of the facility itself, and the same set distance on the other side of the facility.

The set distance is measured from the outside edge of the facility, not from the paint line. This point was corrected in Lessons 59 and 60 and it matters, so it is worth repeating here. The paint line is only an estimate of where the center or edge of the facility lies. The legal and practical measurement starts at the real thing: the outer wall of the pipe, cable, or conduit. Total zone width equals facility width plus the set distance, twice.

Who sets the distance? In the United States, state law sets it. There is no single national number, and anyone who gives you one number as a national rule is wrong. The Common Ground Alliance, usually shortened to CGA, is an industry group that publishes widely used damage prevention best practices. CGA Best Practice 5-19 describes a tolerance zone of the width of the facility plus 18 inches on either side of the outside edge of the facility, measured on a horizontal plane. The same practice states plainly that it does not override state requirements that specify more than 18 inches. In other words, 18 inches is an industry best practice floor, not a federal rule, and state law controls where the work happens.

State distances commonly fall between 18 and 24 inches on each side, and Hawaii uses 30 inches on each side of the exterior surface under Hawaii Revised Statutes Section 269E-2. Do not treat any range in this lesson as a complete list for every state. Some states write the zone differently, as a formula based on the marked centerline. California law, for example, defines the tolerance zone from the field marking in three ways: 24 inches on each side of a single marking assumed to be the centerline; 24 inches plus one half the specified size on each side when the size is specified on a single marking; and 24 inches from each outside marking when the markings show the width of the installation. The lesson is not to memorize every state. The lesson is to look up the rule for the state you are standing in, every time the state changes.

Oklahoma example, labeled as Oklahoma only: the Oklahoma Underground Facilities Damage Prevention Act defines the approximate location of an underground facility as a strip of land two feet, which is 24 inches, on either side of the facility. The Common Ground Alliance state information page for Oklahoma likewise lists a 24 inch tolerance zone with a hand dig provision. So in Oklahoma, work the math with 24 inches on each side. Do not carry that number into another state without checking that state’s law first.

One more limit on the definition. The tolerance zone is a horizontal measurement. It describes a band across the surface and down through the dig area in plan view, meaning as seen from above. It says nothing about how deep the facility is. A facility inside the zone horizontally can be shallower or deeper than anyone expects.

What Does It Look Like?

On the ground, a tolerance zone is invisible until someone builds it from the marks. Picture a straight run of orange paint and orange flags crossing a grass shoulder. Orange in the APWA uniform color code means communication, alarm, or signal lines, cables, or conduit, which includes fiber. The paint line is the locator’s estimate. The tolerance zone is the full band you get when you measure the state’s set distance outward from each outside edge of the facility the paint represents.

In practice, crews make the zone visible in simple ways. They stretch a tape measure across the marks and lay down extra flags or paint ticks at the zone edges. They talk about the zone in the pre-work briefing so the equipment operator, the spotter, and the hand crew all picture the same band. On a crossing, where a new bore path will pass an existing line, the zone shows up as the stretch of ground where the crew potholes first before any drilling reaches it.

You can also recognize the zone by a change in behavior. Outside the band, you may see a machine trenching or a drill working under the site plan. At the edge of the band, the machine stops or pulls back, and people with hand tools or a vacuum excavator take over. That change of pace at an unmarked boundary is the tolerance zone doing its job in real time.

What you will not see is a painted outline of the zone itself in most cases. Locators mark facilities, not zones. Turning marks into a zone is the excavator’s job, and it starts with knowing the facility size from the marks or the ticket information and the set distance from state law.

Whiteboard illustration: what a tolerance zone is

What Does It Do?

The tolerance zone does three jobs.

First, it converts an approximate mark into a workable safety margin. Instead of pretending the paint is exact, it admits the mark could be off and sizes the careful-work area to cover that error plus the width of the facility itself.

Second, it tells everyone on site where the digging rules change. Inside the zone, the goal shifts from moving dirt efficiently to finding the facility without touching it. CGA Best Practice 5-20 describes excavation within the tolerance zone this way: the excavator exercises reasonable care to protect the facility, using methods that can include potholing, hand digging where practical, soft digging, vacuum excavation, and pneumatic hand tools. Federal OSHA rules point the same direction without using the term tolerance zone. OSHA standard 29 CFR 1926.651(b) requires the estimated location of underground installations to be determined before excavation opens, and requires the exact location to be determined by safe and acceptable means when the excavation approaches that estimated location. Potholing is the field method that satisfies that idea: expose the facility, see it, and only then plan the machine work around its confirmed position.

Third, it creates a shared reference for decisions. When a foreman says a bore crossing sits inside the tolerance zone of a gas line, everyone who knows this lesson understands the next steps without a long debate: confirm the state rule, expose the facility carefully, verify position and depth at the crossing, protect it, and keep mechanized equipment back until that is done.

Where Does It Fit?

The tolerance zone sits in the middle of the damage prevention sequence you have been building across Level 3. The sequence runs like this. Plan the work. Contact 811 and open a ticket. Wait for operators to respond and for locators to mark. Review the marks against what you know about the site. Then, before and during excavation, apply the tolerance zone to every marked facility in or near the dig area, and expose facilities where your work will cross or run close to them.

It also connects forward. The verification habits in this lesson, checking marks, exposing crossings, and watching for mismatches, feed directly into the crossing and paralleling decisions covered later in this level. A tolerance zone is not a stand alone topic. It is the working space where locating, excavation method, and boring clearance all meet.

Finally, it fits inside a legal frame with layers you should keep separate. Federal OSHA rules set worker protection duties for excavation, including determining exact locations by safe means as you approach them. State damage prevention law sets the notification process, the marking duties, and the tolerance zone distance and hand dig rules for that state. CGA best practices offer industry guidance that many states and companies adopt, but they do not replace state law. Contract documents and facility owner requirements can add stricter rules on a specific job. When layers conflict, the stricter applicable requirement and your employer’s direction govern, and questions go to your supervisor rather than being settled at the trench edge.

Why Does It Matter?

It matters because marks can be wrong by inches and machines remove dirt by the bucketful. A backhoe bucket, a trencher chain, or a drill head does not feel a conduit the way a hand shovel does. The first contact a machine makes with a buried facility is often the damaging contact. Inside the tolerance zone, that risk is at its highest, because the facility is somewhere inside that band by definition.

The consequences of a strike depend on the facility. An electric strike can injure or kill. A gas strike can release flammable gas and force evacuations. A water main break can flood an excavation and undermine the ground around it. A fiber strike rarely threatens life, but it can cut service to homes, businesses, hospitals, and emergency systems, and it can be expensive and slow to repair. The tolerance zone exists so that the careful methods get used in the exact strip of ground where these outcomes are most likely.

It also matters legally and financially. State laws tie liability for damage to whether the excavator followed the damage prevention act, including respecting marked facilities and using required care near them. Oklahoma law, for example, prohibits using powered or mechanized equipment directly over marked routes until the precise location has been determined, the facility has been exposed, and it has been properly protected, with a narrow exception for removing pavement or masonry and then only to the depth of that pavement or masonry. Working carelessly inside a tolerance zone is therefore not just risky. In many states it is a violation even before anything is hit.

What Does Good Look Like?

Good work around a tolerance zone is quiet and methodical. It looks like this:

The crew confirms the ticket is valid, the marks are present, and the responses are complete before digging starts. Missing or unclear marks are resolved through the notification center instead of being guessed at.

Someone on the crew states the state rule out loud: the set distance for this state, and the facility sizes shown on the marks, so the zone widths for the day are numbers everyone shares.

At each crossing or close parallel run, the facility is exposed by potholing or another careful method allowed in that state before mechanized work reaches it. The exposed facility’s actual position and depth are checked against the plan, and the plan changes if the ground truth differs.

Mechanized equipment stays out of the zone, or is used only as state law, the facility owner, and the site plan allow after the facility is located and protected. A spotter watches when equipment works near a zone edge.

Marks are maintained. If paint fades or flags are disturbed, work pauses in that area and re-marking is requested. If a facility is found somewhere the marks did not predict, the crew stops, protects the area, and notifies the facility operator and the notification center so the mismatch is corrected for everyone.

Documentation matches the field: pothole locations and depths found are recorded, photos are taken where the employer requires them, and the next crew inherits facts instead of rumors.

What Can Go Wrong?

The most common failure is treating the paint line as the facility. A crew measures from the paint, assumes the line sits exactly under it, and digs confidently a short distance away, straight into a facility that was offset from its mark. Measuring from the paint instead of from the outside edge of the facility shrinks the real zone and is exactly the error this lesson exists to prevent.

The second failure is treating the edge of the zone as a guarantee. Outside the tolerance zone does not mean clear ground. Unmarked facilities exist. Private facilities, such as lines owned by a property owner rather than a utility operator, may never be marked through the 811 process at all. Facilities can also be mismarked by more than the zone allows. The zone is where extra care is required. It is not a promise that care is unnecessary everywhere else.

The third failure is the mismark that nobody acts on. A crew potholes at a crossing and finds the facility well to one side of its marks, closer to the work than expected. If they note it privately and keep digging on the original plan, the next crossing on the same line can surprise them, because the whole mark may be shifted. The correct response is to stop, expose and protect what was found, and report the mismatch through the operator and the notification center so the facility gets re-marked.

Other failures follow the same pattern of rushing: using a machine to search for a facility inside the zone, letting marks expire or fade and digging anyway, assuming depth from past jobs on the same street, and boring through a crossing that was never exposed. Each one replaces verified position with a guess, in the ground where guessing costs the most.

There is also a paperwork version of going wrong: using another state’s distance from memory. A crew that works in two states can easily carry an 18 inch habit into a 24 inch state and build every zone that day too small, or carry the larger number the other way and work to the wrong state’s rule. State lines change the rule even when the dirt looks the same.

What Should Someone Notice in the Field?

You do not need to be the excavator to add value around tolerance zones. An inspector, a trainee, or any crew member walking the site can notice these things:

Marks are present, legible, and in the expected colors, and flags have not been knocked down or moved.

The crew can answer a simple question: what is the tolerance zone distance in this state, and has anyone laid out the zone edges at the crossings?

There is evidence of potholing at crossings: small, neat excavations, a vacuum excavator on site, or exposed and protected facilities visible in the trench.

Mechanized equipment is working outside marked bands, and it slows or stops at zone edges rather than digging through them.

Marks and reality agree. Where a facility has been exposed, its position lines up reasonably with its marks. A visible offset is a finding worth raising, not a detail to keep quiet.

No one is using the phrase “we are outside the zone” as a reason to stop paying attention. New or unexpected material in the spoil, such as conduit fragments, warning tape, tracer wire, or bedding sand where none was expected, gets the work paused and checked.

Raising these observations is recognition work, and it is valuable. Performing the excavation inside the zone is separate work that belongs to qualified, authorized people under the site plan and state law.

Practical Example

Hypothetical example. Imagine a fiber crew in Oklahoma preparing to bore across an existing 2 inch communication conduit. The marks show the conduit size, and Oklahoma defines the approximate location as a strip 24 inches on either side of the facility. The tolerance zone math is 24 inches plus the 2 inch facility width plus 24 inches, for a total zone width of 50 inches. The crew lays tape on the ground and flags both edges of that 50 inch band across the bore path.

Because the bore will cross inside that band, the crew does not drill through on the marks alone. A vacuum excavator potholes at the crossing and exposes the conduit. The exposed conduit sits 7 inches to one side of the paint line, still inside the zone, which is exactly the kind of offset the zone is built to absorb. Now the crew knows the real position and the depth at the crossing, records both, adjusts the bore plan to keep the clearance the project requires, and only then drills, with the exposed crossing watched as the drill passes.

For contrast, run the same 2 inch facility under the CGA best practice distance of 18 inches on each side, which some states use in their own law: 18 plus 2 plus 18 equals a 38 inch total zone. Same facility, different state rule, different band on the ground. That difference is why the state lookup comes before the tape measure, every time.

Key Terms

Tolerance zone: The horizontal band made of the width of a buried facility plus a set distance on each side of its outside edge, inside which excavation methods and care change under state law and best practice.

Facility: The buried utility itself, such as a pipe, cable, or conduit, measured at its outside wall.

Outside edge: The outer surface of the facility. Tolerance zone distances are measured from here, not from the paint line.

Approximate location: The legally recognized idea that marks show where a facility is believed to be within a margin of error, not its exact position.

Potholing (daylighting): Carefully exposing a buried facility, usually by hand digging or vacuum excavation, to confirm its exact position and depth.

Soft digging: Low impact excavation methods intended to expose facilities without damaging them, including hand digging and vacuum excavation.

Mismark: A mark that does not represent the facility’s actual position within the allowed tolerance, requiring correction through the operator and notification center.

Notification center: The state one call system, commonly reached through 811, that routes excavation notices to facility operators and tracks responses.

Check Your Understanding

  1. A facility is 4 inches wide. Your state’s set distance is 18 inches on each side. What is the total tolerance zone width, and where is the 18 inches measured from?
  1. Why does the tolerance zone exist if locators already mark the facility?
  1. A crew member says, “We are two feet outside the tolerance zone, so this ground is definitely clear.” Name two reasons that statement is wrong.
  1. In Oklahoma, what distance on each side does state law use to define the approximate location of an underground facility, and what total zone width does that produce for a 6 inch facility?
  1. A pothole reveals a gas line noticeably offset from its paint marks. What should happen next, and why should the crew not simply adjust quietly and keep working?

Answer key:

  1. 40 inches total: 18 plus 4 plus 18. The 18 inches is measured from the outside edge of the facility on each side, not from the paint line.
  2. Because marks are approximate. Locating has a margin of error and the facility can sit offset from its paint, so the zone reserves a band where careful methods are used until the facility is actually exposed and confirmed.
  3. Any two of: unmarked or private facilities may be present; a facility can be mismarked beyond the zone; the zone gives no depth information; the general duty to determine locations and dig with care applies outside the zone as well.
  4. Oklahoma: 24 inches (two feet) on each side. Total for a 6 inch facility is 24 plus 6 plus 24, which is 54 inches. This is an Oklahoma figure from Oklahoma law and must not be assumed for other states.
  5. Stop work in the affected area, protect the exposed facility, and notify the facility operator and the notification center so the line can be re-marked. A shifted mark at one point means other marks for the same facility may also be shifted, so the mismatch has to be corrected for the rest of the job and for the next excavator.

Lesson Takeaway

The tolerance zone is the width of the facility plus your state’s set distance on each side, measured from the outside edge of the real facility, never from the paint alone. It exists because marks are approximate. Inside it, careful methods such as potholing, hand digging, and vacuum excavation replace machine digging until the facility is exposed and confirmed. Outside it, stay alert anyway, because the zone is a care boundary, not a guarantee of clear ground. Look up the state rule, build the band, expose the crossing, and act on mismatches out loud.

Sources and Technical References

Common Ground Alliance, Best Practices, Practice 5-19 (Excavation Tolerance Zone) and Practice 5-20 (Excavation within Tolerance Zone). CGA states the zone as the width of the facility plus 18 inches on either side of the outside edge on a horizontal plane, not intended to preempt state requirements specifying more than 18 inches, and lists potholing, hand digging, soft digging, and vacuum excavation among the methods to consider inside the zone. https://carcga.org/BP_22.0_Web.pdf

Common Ground Alliance, Best Practices guide hosted copy, Practice 5-19 text as above. https://cdn.pelicancorp.com/pdfs/26-cbyd-resources-bestpractices.pdf

Common Ground Alliance, State Resource and Information Map, Oklahoma page. Lists Oklahoma as a 24 inch tolerance zone with a hand dig clause under the Oklahoma Underground Facilities Damage Prevention Act. https://commongroundalliance.com/State/Oklahoma

Oklahoma Underground Facilities Damage Prevention Act, Title 63, Section 142.6(B), as published by OKIE811. Defines the approximate location of underground facilities as a strip of land two feet on either side of such underground facilities, and requires operators to mark so the excavator can employ hand dug test holes to determine precise location. https://okie811.org/law/

Oklahoma Underground Facilities Damage Prevention Act, Title 63, Section 142.7, via Justia. Powered or mechanized equipment shall not be used directly over marked routes until the precise location has been determined and the facilities exposed and properly protected, with an exception for pavement or masonry removal only to the depth of that pavement or masonry. https://law.justia.com/codes/oklahoma/title-63/section-63-142-7/

OSHA, 29 CFR 1926.651(b), Specific excavation requirements, via Cornell Law Institute. Estimated locations must be determined before excavation, utility owners contacted, and exact locations determined by safe and acceptable means as excavation approaches them. This federal rule does not set a tolerance zone width. https://www.law.cornell.edu/cfr/text/29/1926.651

Underground Services, Inc. (SoftDig), Understanding the Tolerance Zone. Summarizes state variation as ranging from 18 to 30 inches on either side, with states split mainly between 18 and 24 inches, and works the example of a 2 inch pipe in an 18 inch state producing a 38 inch total zone. Industry source, used for the variation summary only, not as law. https://www.softdig.com/blog/understanding-tolerance-zone-best-practices-excavation/

California Government Code, Section 4216 definitions, via California Legislative Information. Defines tolerance zone from the field marking in three ways: 24 inches on each side of a single marking assumed to be the centerline; 24 inches plus one half the specified size on each side when the size is specified; and 24 inches from each outside marking when the markings show the width. Included to show that some states use a marking based formula rather than the outside edge method. http://leginfo.legislature.ca.gov/faces/codes_displayText.xhtml?article=2&chapter=3.1.&division=5.&lawCode=GOV&part&title=1.

Unverifiable flags: No factual claim in this lesson is left flagged as unverifiable. Two cautions apply. First, state tolerance zone distances change when legislatures amend damage prevention acts, so the Oklahoma, California, and variation figures above should be rechecked against current state law before being used on a specific project. Second, no single official fifty state table was found in these sources, so the variation figures are presented as sourced state examples, not as a complete census of every state. The Hawaii 30 inch figure is from Hawaii Revised Statutes Section 269E-2: https://law.justia.com/codes/hawaii/2019/title-15/chapter-269e/section-269e-2/


Previous lesson: Lesson 62: What Is White Lining? |
Back to Level 3 hub |
Next lesson: Lesson 64: What Is Positive Response?