Introduction
An existing utility is any utility facility that was already present in, on, or above a work area before your project disturbs the ground or the airspace. It counts no matter who owns it, whether it is in service, and whether any record, print, or mark shows it. The pipes, cables, ducts, and structures already in a corridor belong to other owners, and your new fiber has to fit into the space they already occupy.
This lesson opens Level 3, Recognize Existing Utilities, and it is the definition the rest of the level depends on. Lessons 47 through 56 take the kinds of existing utilities one at a time. Lessons 57 through 66 teach the system that identifies and verifies them before digging. Lessons 67 through 71 teach what happens when that system strains. Everything in the level starts from the judgment built here: what counts as existing, how what you meet gets classified, and what each source of information can and cannot prove.
What This Lesson Gives You
- Sort any facility you meet into four honest classes: known and active, abandoned, private or non located, and unknown.
- Read a street’s poles, risers, meters, covers, pedestals, and marks as one connected picture of what is already there.
- State what records, marks, and positive responses each prove, and what none of them can prove, before a crew treats a corridor as known.
- Hold a claimed abandoned line as live until its owner confirms the status in a form the project can file.
- Write every disagreement between records, marks, and the field as a question with an owner, and escalate it before digging instead of guessing past it.
Start With the Basics
Picture a quiet residential street on the morning before a fiber bore. The road looks empty. The yards look empty. A beginner sees grass, pavement, a few poles, and some colored paint, and thinks the work is about the new fiber that is not there yet.
A trained reader sees the opposite. The street is already full. Under the pavement and under the grass is a layered network built over decades by many different owners, at different times, for different purposes. Electric lines bring power to every house. Gas lines bring fuel to furnaces and water heaters. Water lines bring drinking water in under pressure, and sewer lines carry waste away. Older communications and cable lines already occupy the corridor your new fiber wants to share. Storm drains carry rain water under driveways and roads. Some of those facilities are overhead on poles, where you can see them. The larger share is buried, where you cannot.
Every one of those facilities was there before your project arrived. That is what the word existing means in this course, and it has three edges worth fixing in mind:
- Existing does not mean old. A gas service placed last month is an existing utility on the day your bore reaches it.
- Existing does not mean shown on the prints. A private line to a detached garage that no record ever captured is still an existing utility.
- Existing does not mean active only. A line that its owner has taken out of service and left in the ground is still physically there, still occupies space, and still must be dealt with as a physical object in your path until its owner confirms its status and the project plans around it.
Think of moving into an old house. The pipes and wires inside the walls were there before you arrived, they belong to the house, and you work around them. The previous owner’s notebook may describe the plumbing as it was twenty years ago and say nothing about the line a later owner ran out to the garage. A wall that looks empty can still hide a pipe, and cutting into the wall on the strength of the notebook is how a renovation floods a kitchen. A fiber corridor works the same way. The plant was there first, the written record of it may be old or incomplete, and the surface you can see is only the outside of the wall.
Three ideas carry the whole lesson:
- Existing means before you, owned by someone else. Your project works around existing utilities. It does not own them, and it does not get to declare what they are, move them, or cut them.
- No single source tells the whole story. Records tell you what someone wrote down. Marks tell you what a locator could find and chose to mark under a ticket. Surface features tell you what announces itself at ground level. The buried facility itself is the only complete truth, and you meet it only through careful verification the project plans.
- Uncertainty is information. When sources disagree, or when a source is silent where a facility should exist, that disagreement or silence is a finding to write down and escalate. It is not a gap to fill with a guess so the crew can start on time.
What Is It?
An existing utility, also called an existing facility in damage prevention language, is any utility facility that is already present in, on, or above the work area before your project disturbs the ground or the airspace, regardless of who owns it, whether it is in service, and whether any record, print, or mark shows it. Each part of that definition does work.
A utility facility is the physical plant that delivers or carries a service: pipes, conduits, ducts, cables, wires, valves, meters, pedestals, cabinets, manholes, handholes, poles, guys, anchors, vaults, and the other structures that belong to that service. When this lesson says facility, it means that physical plant. Keep three ideas separate:
- The facility is the physical plant itself. A buried gas pipe is a facility.
- The service is what the facility carries. The gas inside the pipe is the service, and it is where the hazard lives.
- The facility owner, also called the utility owner or operator in state damage prevention laws, is the company, agency, or person responsible for the plant.
Already present before your work starts means the test is timing, not age, size, or importance. If it was placed before your excavation, bore, or aerial work begins, it is existing for your project. Your new duct, cable, handholes, and poles are proposed or new facilities. Everything else you will meet is existing until your project places its own plant.
Regardless of who owns it means public and private facilities both count. A city water main, a gas company distribution line, an electric company feeder, another carrier’s fiber, and a property owner’s private line beyond a meter are all existing utilities if they are in your work area. Ownership decides who must be contacted, who can confirm status, and who repairs damage. It does not decide whether the facility can hurt someone or stop the job. A private line cuts the same as a public line.
Whether it is in service means status is a separate question from presence. A facility can be present and active, present and abandoned, or present and of unknown status. Presence is a physical fact you can sometimes verify. Status, meaning whether the facility is live, pressurized, energized, out of service, or formally abandoned, is a fact only its owner can confirm from its own records and field checks. A fiber crew never settles status by looking at a pipe, a cable, or a disconnected meter and deciding that it looks dead.
Whether any record shows it means a facility does not stop existing because paperwork missed it. Records are evidence about a facility. They are not the facility itself.
The working words
To use the definition in the field, you need its working words, each defined before it is built on.
811 is the free national three digit number in the United States that reaches the local notification center, also called a one call center. A one call center is the organization for a state or region that takes a notice of planned excavation from an excavator and notifies member facility owners whose buried facilities may be in the work area, so those owners can mark or otherwise respond. One call describes that notification system as a whole. People use the phrases 811 ticket, one call ticket, and locate ticket for the record that the notification creates. State law governs the ticket: who must contact the center, how far in advance, what information the notice must contain, how long a ticket stays valid, and what each party must do next. Those rules vary by state and must be verified for the state of the job. Lesson 57 teaches 811 in full. This lesson uses the term only at the overview level: contacting 811 is how a project formally asks member owners to help identify their existing utilities before digging.
A locator is a trained person who, on behalf of a facility owner or a locating company, uses records and locating equipment to determine the approximate position of a buried facility and places temporary marks for it. Locating is skilled work with its own equipment, methods, and limits. Reading marks in the field is part of a fiber crew member’s job. Performing a locate as a locator is a separate role that this lesson does not teach or authorize.
Positive response is the system by which facility owners tell the excavator, through the notification center or a related system, what they did in response to a ticket: for example, that facilities were marked, that the owner has no facilities in the work area, or that more time or information is needed. The exact response codes, the method of checking them, and the duty to check them are set by state law and by the notification center for that state. Lesson 64 teaches positive response in full. The overview point for this lesson is narrow: a ticket is not complete because paint appeared. The crew verifies that each notified owner has responded, and that the response matches the field, before it treats the locate as ready.
Tolerance zone means the corridor around a buried facility where state rules require careful exposure methods, such as hand digging or vacuum excavation, and restrict mechanical digging until the exact location of the facility is determined. State law defines the zone, how it is measured, and how wide it is, and states differ on each point. This lesson states no single width or measurement point as universal. Lesson 63 teaches the tolerance zone in full.
An as-built, also called an as-built drawing or record drawing, is a record that is meant to show what was actually built and where it was placed, as distinct from a design drawing that shows what was planned. An as-built is only as good as the field information that went into it and the updates that followed it. A replaced service, a field change that was never drawn, and a repair on a new path can each make an as-built wrong without anyone intending to mislead. Treat every as-built as a lead to verify, not as proof of current position or status.
SUE stands for subsurface utility engineering. It is an engineering practice that investigates existing subsurface utilities in a planned, documented way and depicts them with a stated quality level that tells the reader how the information was obtained. The industry guideline for that depiction in the United States is ASCE 38-22, published by the American Society of Civil Engineers, as a standard guideline for investigating and documenting existing utilities. Under that guideline:
- Quality Level D is information from records and recollections alone.
- Quality Level C adds a survey of visible surface features correlated with the records.
- Quality Level B uses surface geophysical methods to designate the approximate horizontal position of a buried facility.
- Quality Level A exposes the facility, usually by vacuum excavation, and measures its precise position at that point.
Quality levels describe confidence in the depiction. They do not change the facility itself. A formal SUE investigation is used only when a project commissions one. When no investigation has been commissioned, the project relies on records, surface reading, and the ticket locate, and a print that carries a quality level should be read for exactly what that level says about how the information was obtained.
Abandoned, in the strict sense this course uses, means a facility that its owner has formally taken out of service, disconnected or made safe under its own procedures and applicable rules, and recorded as abandoned in its own records. Abandoned does not mean old looking, disconnected at one visible end, silent, unmarked, or unused as far as a neighbor or a crew can tell. Only the owning utility can confirm that a facility is abandoned. Lesson 55 teaches abandoned utilities in full.
A private facility, also called a private utility or a customer owned facility, is a facility that is owned by the property owner or another private party rather than by a member utility, and that is therefore commonly outside the scope of what a public 811 ticket will mark. Common examples, where local rules place them on the private side, include:
- The line beyond a meter or beyond a utility’s point of delivery to a building.
- A private line to a detached building, yard, or outbuilding.
- Private site systems such as certain irrigation, septic, or site lighting lines.
Where the public and private boundary sits for each service varies by utility, by local code, and by state practice, and must be confirmed for the job in hand. A private locator is a locator hired privately, outside the 811 ticket, to find and mark private facilities. Lesson content on meters in Lessons 39 and 40 taught that boundary from the meter outward. This lesson applies the same boundary idea to every service.
The four classes
With those words in place, the four way classification is straightforward. It classifies every existing utility you may meet by what is known about it and by whether the ticket system will mark it.
- Known and active. The facility appears in owner records or on the prints, its surface evidence or its service to an occupied building shows it is in use, and it is expected to be marked under the ticket if it is a member facility in the work area. Mains and services to occupied buildings mostly belong here. Known and active does not mean exactly located. It means the project knows to expect it, treats it as live, pressurized, or energized as its service requires, and verifies its position by the locate and, where the plan requires it, by careful exposure at crossings.
- Abandoned. The facility is physically present but is claimed to be out of service. That claim is only settled when its owner confirms it. Until that confirmation exists in the project record, the safe working treatment is the same as for a live facility: expect it, avoid it, expose it only under the plan, and never cut, remove, or bore through it on a field judgment that it looks dead. Even after an owner confirms abandonment, the physical pipe, conduit, or cable still occupies the ground. It can block a bore, collapse a trench wall, carry residual product, or be confused with a live parallel facility. Confirmation changes the hazard picture as the owner describes it. It does not make the object vanish.
- Private or non located. The facility is real and may be fully active, but the public ticket does not mark it because it sits on the private side of a boundary or belongs to a non member owner. It will produce no paint and no positive response entry under the public ticket, even though it crosses your bore line. Finding it depends on surface evidence, on property records and interviews through the project process, and, where the project directs it, on a private locate. The classic pattern is the house side segment past a water or gas meter, the electric service beyond the delivery point in systems where that segment is customer owned, and lines to detached garages, barns, yard lights, and outbuildings.
- Unknown. The facility is present but no source the project has checked names it: not on the prints, not in the records the project received, not marked, and with no surface feature the reader recognized, or with a surface feature that was logged as unidentified. Unknown facilities are discovered in three ways: by a careful surface read that spots the clue everyone else missed, by verification work such as potholing at a crossing that finds more than the plan expected, or, in the failure case, by the bore or the excavator hitting them. Lessons 56 and 68 teach unknown utilities and the response to finding one in full. The habit this lesson builds is earlier: assume unknown facilities are possible on every job, especially on older properties, on properties with many past owners or past uses, and in corridors where many utilities have been placed over a long time.
Those four classes are not permanent labels. A facility moves between classes as knowledge improves. An unknown line becomes known when the read finds its riser or its meter. A claimed abandoned line becomes confirmed abandoned only when its owner says so in a form the project can file. A private line becomes located when a private locator marks it. The classification is a tool for honesty about what the project knows today. It is not a sorting of facilities into safe and unsafe. Only the first class is expected and active. None of the four classes means safe to strike.
What Does It Look Like?
An existing utility does not look like one thing. It looks like a whole vocabulary of surface evidence, overhead evidence, marks, and records, and sometimes it looks like nothing at all. Learning to recognize an existing utility means learning all of those forms.
Overhead evidence. Overhead, an existing utility is visible directly. Poles carry electric conductors, communications cables, guys and anchors, transformers, and streetlights. Risers, the vertical runs that take a line from overhead down a pole and underground, or the reverse, are the hinge points: every riser announces a buried facility leaving that pole in some direction. Service drops run from poles or from underground service points to buildings. Lesson 47 teaches electric overhead and underground evidence in full, and Lesson 44 has already taught what a pole itself can tell you. For this lesson, the point is simple: overhead plant is existing utility in plain sight, and each overhead line that dives underground becomes a buried existing utility at the base of that dive.
Ground level evidence. At ground level, an existing utility announces itself through its access points and its endpoints:
- Manhole covers and handhole lids show where underground plant can be reached.
- Pedestals and cabinets house communications and other distribution connections.
- Valve boxes, curb boxes, and cleanouts mark points on water, gas, and sewer lines.
- Fire hydrants announce a pressurized water main, as Lesson 38 taught.
- Gas meter sets announce a pressurized gas service to a property, as Lesson 39 taught.
- Water meter boxes announce a pressurized water service, as Lesson 40 taught, with the meter at the boundary between the utility side and the customer side in most systems.
- Electric meters and service points announce an electric service.
- Storm inlets and grates announce a storm drain system below.
Each of those features is covered in its own Level 3 lesson. Here, learn them as one pattern: a surface feature that belongs to a service means a buried or overhead facility connects to it, runs from it, and must be accounted for on both sides of it, including the private side where that side exists.
Marks. In marks, an existing utility looks like temporary paint, flags, stakes, or whiskers placed by a locator, colored under the APWA Uniform Color Code. APWA is the American Public Works Association. In that code:
- Red is electric.
- Yellow is gas, oil, steam, petroleum, or gaseous materials.
- Orange is communications, alarm, or signal lines.
- Blue is potable water.
- Purple is reclaimed water, irrigation, and slurry lines.
- Green is sewers and drain lines.
- White is proposed excavation.
- Pink is temporary survey markings.
Marks show the approximate horizontal position of a buried facility as the locator determined it. They do not show exact position with certainty, they do not show depth at all, and they do not cover facilities outside the ticket that produced them. A run of marks that ends at a meter, a pedestal, a riser, or a cleanout that matches its color is a coherent picture. A run of marks with no matching surface feature, or a surface feature with no marks where the ticket should have covered it, is a mismatch to resolve. Lessons 59, 60, and 61 teach marks and colors in full.
Records. In records, an existing utility looks like lines and symbols on prints, utility maps, as-built drawings, geographic information system records where a project uses them, and ticket records and positive response entries. Records are the most portable form and the easiest to trust too far. A record line has no weight, no pressure, and no voltage. The buried facility it claims to depict has all three where its service requires them. Hold that difference in mind every time a clean drawing makes a corridor look simple.
Almost nothing. Finally, a private or unknown existing utility may look like almost nothing:
- A faint patched trench line in pavement or grass where a past cut sank or was repaired.
- A single unmarked riser on a building.
- A conduit stub at a foundation.
- A lid with no wording that a reader honestly logs as unidentified.
- No surface sign at all over a line that was buried without a lasting access point.
That near invisibility is not evidence of absence. It is the reason this classification exists. An occupied building is served somehow, even when the reader cannot find its meters. A corridor that has served buildings for decades holds more than its newest records show. The reader records what was found, records what was searched for and not found, and treats the second list as questions, not as clearances.
Illustration coming soon.
What Does It Do?
What an existing utility does depends on which utility it is, and Level 3 spends a lesson on each one. At the level of this definition, every existing utility does three jobs in relation to your project, whatever service it carries.
It delivers a service someone depends on.
- Electric facilities carry power.
- Gas facilities carry fuel gas under pressure.
- Water facilities carry drinking water under pressure, and fire protection water where hydrants and fire services are present.
- Sanitary sewers carry waste away, by gravity in most collection lines and under pressure in force mains where they are used.
- Storm sewers carry rain water and drainage.
- Communications and cable facilities carry signals for homes, businesses, public safety, and other carriers.
- Traffic and streetlight systems carry power and control signals that manage roads.
Interrupting any of those services has consequences beyond your work area: a home without heat or water, a business without power or communications, a road without signals, a flooded street when a storm line is blocked or broken. The service is the reason the facility was built and the reason its owner, its customers, and the public will care if it is damaged.
It occupies space your project also needs. The underground corridor under a road or a right-of-way is finite and already crowded in many places. Each existing facility holds a position, horizontal and vertical, and needs a working and safety space around it that state tolerance zone rules, owner requirements, and the project plan define in their own ways. Your bore, your trench, your handholes, and your duct must fit into the space that remains, with the separations and clearances the prints, the permits, and the owners require. Those separations and clearances are set by the authority that governs each one, whether that is a federal rule, a state law, an industry standard, a manufacturer instruction, a contract specification, or an owner requirement. This lesson states none of them as a universal number. When two facilities want the same space, that is a utility conflict, taught in Lesson 69, and it is resolved by the designer, the owners, and the project lead, not by the bore operator choosing a path in the moment.
It sets the conditions for how your work may proceed. The presence of an existing utility is the reason the project must determine locations before excavation under federal rules, must contact owners through the ticket system under state law, must verify responses and marks in the field under damage prevention best practice, must use careful methods inside tolerance zones, and must expose facilities at critical crossings to confirm exact position where the plan requires it. In short, existing utilities are not background to fiber construction. They are the governing facts the construction method is built around. A project with no existing utilities in its corridor would need almost none of that discipline. No real corridor looks like that.
One more function matters for beginners. An existing utility teaches. Each meter, hydrant, pedestal, riser, cleanout, inlet, and mark is free, surface level information about what is below, offered before any machine starts. A crew that reads that information well starts with a map of risks it did not have to dig to learn. A crew that walks past it starts blind and pays for the same information later, in potholes at best and in strikes at worst.
Where Does It Fit?
In the course. This lesson opens Level 3, Recognize Existing Utilities, and it is the definition the next twenty five lessons depend on:
- Lessons 47 through 54 take the known and active class apart service by service, so you can recognize electric, gas, water, sanitary sewer, storm sewer, telecom, cable TV, and traffic and streetlight plant by its own surface evidence.
- Lesson 55 takes the abandoned class.
- Lesson 56 takes the unknown class.
- Lessons 57 through 66 teach the system that identifies and verifies existing utilities before digging: 811 itself, the locate request, what marks tell us, the colors, paint compared with flags, white lining, the tolerance zone, positive response, and potholing and daylighting.
- Lessons 67 through 71 teach what happens when that system strains: a mismarked utility, a found unknown utility, a utility conflict, a utility strike, and a field that does not match the locate.
Read this lesson as the frame for all of them. Each of those lessons answers one question that this definition raises.
In a project. Information about existing utilities flows in a set order, and this lesson sits at the head of it:
- Desk stage. The designer and the project gather records: owner maps, as-built drawings, prior tickets, permits, and any subsurface utility engineering the project commissions, each with a confidence that matches how it was obtained.
- Site read stage. Taught as a complete method in Lesson 45, the crew compares those records against surface evidence on foot and writes down disagreements.
- Ticket stage. The excavator contacts 811 under the state rules for the job, owners or their locators mark member facilities, and owners give positive responses.
- Verification stage. The crew checks that responses match marks and that marks match surface features, preserves the marks, and plans careful exposure where crossings require exact positions.
- Construction stage. The crew works under the plan around the verified facilities, protects and supports exposed facilities as the plan and the owner require, and stops and escalates when the field shows something the earlier stages missed.
An existing utility can enter that flow at any stage, including the last one, which is why the flow never treats an early stage as final proof.
In the rules picture. Different authorities govern different parts of that flow, and a beginner must keep them separate:
- Federal rules. The Occupational Safety and Health Administration, called OSHA in this lesson, in 29 CFR 1926.651, requires that the estimated location of utility installations that may reasonably be expected to be encountered be determined before an excavation is opened, that utility companies or owners be contacted within established or customary local response times and asked to establish the locations before excavation starts, and that the exact location be determined by safe and acceptable means as excavation approaches that location. Those are federal duties of the employer.
- State damage prevention laws create and govern the 811 system for that state: notice duties, ticket validity, owner response duties, positive response, tolerance zone definition, and enforcement.
- Industry best practices from the Common Ground Alliance, called the CGA in this lesson, describe the disciplines that make the system work in the field, including visual inspection during locating, checking that plant shown on records matches the site, and looking for evidence of facilities that are not on record.
- Industry guidelines such as ASCE 38-22 describe how to investigate and depict subsurface utility information with stated quality levels when a project uses subsurface utility engineering.
- Manufacturer instructions govern particular equipment and materials.
- Contract specifications and permits govern the specific job.
- Common practice fills gaps where none of those speak, and it never outranks a law, a standard the contract adopts, or an owner’s requirement for its own facility.
When this lesson says a rule exists, it names which kind of rule it is. When the governing rule for your job is not in front of you, the lesson teaches you to say that it needs verification rather than to borrow a rule from another state or another project.
In the corridor picture. Existing utilities are the reason fiber shares space under rules at all. The Fiber Optic Association, called the FOA in this lesson, covers underground outside plant construction in its reference material, including records, markers, manholes and handholes, and the need to know existing services before placing new plant. Federal Highway Administration material on utilities in highway right-of-way is background for how utilities are accommodated in road corridors on larger projects. Fiber jobs in this course mostly work under local permits on local roads. The principle is the same at every scale: the corridor was occupied first, the new work fits around the old work, and coordination before construction is cheaper and safer than discovery during construction.
What Is at Stake
Safety. The safety picture differs by service, which is why each service earns its own lesson:
- An energized electric facility can injure or kill on contact or through an arc, without any visible warning at the surface beyond its marks, its risers, and its enclosures.
- A pressurized gas facility that is struck can release gas that can ignite. A gas odor in or near an excavation is a condition to leave and report, never a condition to investigate by staying, sniffing closer, or operating equipment.
- A pressurized water facility that is cut can flood an excavation, erode its walls, and undermine pavement and structures.
- A broken sewer facility can expose workers and the public to unsanitary material, and a later bore can create a cross bore, where a new line passes through an existing pipe and blocks it until the blockage is discovered by a backup or by later cleaning or cutting work.
- A manhole and certain other underground structures can be confined spaces, meaning spaces large enough for a person to enter, with limited entry and exit, and not designed for continuous occupancy. Some of them are permit-required confined spaces, for example because they may contain a hazardous atmosphere, and entry is governed by strict rules and training that this lesson does not provide.
Recognizing an existing utility is the first step that keeps a crew from meeting any of those hazards by surprise. Recognition by itself protects no one. It triggers the ticket, the verification, the method, and the escalation that together provide protection.
Service and the public. Every existing utility in your corridor is someone’s heat, water, power, drainage, communications, or road safety, in use today. Damage prevention reporting in the United States counts damages to underground facilities in large numbers every year, and the CGA publishes that reporting and its analysis so the industry can learn from it. This lesson cites no count as a fixed fact, because the reporting year and the method matter, and the count for any year must be checked in the CGA reporting for that year. The stable point does not need a count: strikes interrupt services that neighbors and businesses are actively using, they trigger emergency responses, and they follow a project in reports and claims long after restoration is done.
Money and the schedule. A bore plan that assumes an empty corridor is priced and scheduled for an empty corridor. The first unknown or private facility in that corridor, found by the bore head, converts a planned crossing into stoppage, repair, utility and owner involvement, possible regulatory reporting, and redesign under pressure. The same facility found by records, by the surface read, or by a planned pothole costs a drawing change, a shifted handhole, or a slower careful crossing. The definition in this lesson is the cheapest tool on the job: treating everything already in the ground as real, owned, and to be verified costs attention. Treating it as absent until proven costs strikes.
Honesty about limits. Beginners often want a single moment when a corridor becomes known and safe. This subject offers no such moment. Records improve and then age. Marks are placed and then fade, get mowed over, or get paved over. A facility placed after the prints were drawn exists before any record of it does, a pattern the CGA visual inspection practice exists to catch, because the time between placing a facility in the field and placing it on permanent records varies by owner and by location. A competent crew therefore works in a standing posture: expect existing utilities everywhere buildings are or were served, verify by more than one source, protect what is found, and keep reporting what does not match. That posture, rather than any single ticket or drawing, is what this lesson is really teaching.
What Does Good Look Like?
Good work with existing utilities looks verified, classified, and documented, not assumed:
- Every work area has a records check before field work: prints, available owner records and as-built drawings, prior ticket information, and any quality level or SUE information the project holds, reviewed with the understanding that records are leads whose age and source limit their trust.
- Every occupied or previously occupied property on the route is treated as served. Its meters, services, risers, hydrants, pedestals, cabinets, cleanouts, inlets, and covers are sought on foot, logged by location and condition, and any expected service that cannot be found is written as a question instead of being treated as absent.
- The 811 ticket for the work is in place under the rules of the state of the job, positive responses are checked for each notified owner, and the responses, the marks, and the surface features are compared in the field before digging. A response or a mark that conflicts with the field is escalated, not worked around. The detailed steps are those of Lessons 57 through 66, applied as the project process directs.
- Each known facility in the corridor is classified in the project notes as known and active, claimed or confirmed abandoned with the owner confirmation named where it exists, private or non located with the plan to find it, or unknown and still to be resolved. No facility is written as abandoned or safe on a field judgment alone.
- Private facilities in the work area are planned for explicitly: the ownership boundary for each service is confirmed for that utility and that property, and a private locate or another project directed verification is arranged where the public ticket will not mark the segment the work will cross.
- Crossings of existing utilities are verified to the level the plan requires, including careful exposure to determine exact location where the work will approach a facility, under the federal duty that exact location be determined by safe and acceptable means as excavation approaches it. Marks alone are never treated as exact position or as any evidence of depth.
- Exposed or encountered existing facilities are protected and supported as the plan and the owner require while work is open, are never moved, cut, or operated by the fiber crew, and are reported exactly as found when their position or condition differs from the plan.
- The before and after record is kept: located photographs and notes of surface features, marks, and conditions before disturbance, and of the corridor as restored, so preexisting damage, preexisting leaks, and unmarked preexisting facilities are not charged to the crew and new findings are not lost.
Good does not mean the corridor turned out to be simple. It means every facility the project could learn about through records, reading, ticketing, and verification was learned about that way, classified honestly, and planned around, and the facilities that could not be resolved were named as open questions with owners, before machines met them.

From the Field
Picture a fiber project about to bore along the west side of a short street, cross to the east side at the far end, and place three handholes. The prints show the water main, the gas main, the sewer main, and an existing communications duct along the route, all drawn as a tidy corridor with room for the new fiber. The 811 ticket is current, marks are down, and positive responses show each notified member owner accounted for. Before any machine is unloaded, the crew lead walks the route with the prints and the ticket information and classifies what the project actually knows, using this lesson’s four classes.
Known and active comes first. The water, gas, and sewer mains match their marks and their surface features: blue marks run hydrant to hydrant and to each water meter box, yellow marks run to each gas meter set, and green marks follow the manhole covers the prints show. Each house has a gas meter and a water meter, so the lead counts a gas service and a water service crossing for every lot, including the lot where the water meter lid is buried under mulch and only the blue marks running to the flower bed reveal it. The crossing list grows past what the tidy prints suggested, and potholing at the street crossing is planned under the project process to determine the exact location of the mains there before the bore passes, as the federal excavation rule requires when work approaches an estimated location.
Abandoned comes next, and it stays a question. Behind one house, the prints carry a dashed line labeled as a former fuel service, with a note that it is out of use. No owner confirmation of abandonment is in the project file, and no mark covers it. The lead does not write abandoned on the crossing list. The lead writes claimed abandoned, owner confirmation not on file, treat as live, and puts it on the questions list for the project lead to route to the facility owner. The bore plan for that lot is held until the owner confirms the status in a form the project can file, or the crossing is verified under the plan as if the line were live. Nobody on the crew is asked to judge the line by its age or its rust.
Private or non located is where the walk earns its keep. At the last house before the street crossing, a detached garage stands behind the house with a light over its door and a small riser on its wall. No marks run to the garage, and the public ticket correctly does not cover the house side lines. The lead logs a probable private line from the house or from the service point to the garage, crossing the planned bore at an unknown angle, and notes that a private locate must be arranged through the project before that lot is bored. At the same house, the gas and water marks stop at their meters, and the lead notes the house side segments past those meters as private in this system, to be confirmed, where the handhole excavation will come close to them.
Unknown is handled honestly. Midway along the route, a round lid with no wording sits in the grass strip, sunk and half covered, matching nothing on the prints and carrying no marks of any color. The lead photographs it in context, logs it as an unidentified cover at its address, and lists it as an unknown facility access point for the designer and the owners to identify through records and the project process. The lead does not lift it, does not guess it into the sewer system because it is round, and does not let the bore line pass over it on the assumption that an unidentified lid must be unimportant.
The comparison that afternoon reclassifies the street. The tidy corridor on the prints becomes a written crossing list: the three mains and their services as known and active, one claimed abandoned service held for owner confirmation, two private segments and one probable private garage line needing a private locate plan, and one unidentified cover needing identification. The street crossing potholes are planned, the handhole nearest the unidentified lid is held in its planned position only until the lid is identified, and construction starts on the segments whose questions are resolved while the held items move through their owners. The bore later runs with no strike. Nothing about the ground changed during that walk. What changed was the project’s honesty about which existing utilities it knew, which it had merely been told about, and which it had not yet earned the right to call understood.
Carry the decision rule out of this walk: read the field before the machines, classify honestly what the project knows and what it only assumes, and let the owner, the locate, and the plan answer each open question before the bore does.
What Can Go Wrong?
Failures with existing utilities are usually failures of the definition: something that was existing was treated as if it were absent, inactive, public, or exactly located when it was none of those things.
- Treating the prints as the corridor. Prints show a clear path. In the field, a service replaced on a new line last year, a private line to a garage, and an older communications duct that was never drawn occupy that path. Records lag the field for routine reasons: placement and repair happen faster than drawing updates, field changes are not always recorded, and each owner keeps records in its own system on its own schedule. The prints are one source. The field is another. The locate is a third. Good work compares all three.
- Treating no marks as no facility. A ticket is completed and one segment has no paint. The crew reads the silence as clearance and bores through a private gas or water segment the ticket never covered, a non member facility, or a member facility that was mismarked or missed. Silence from a ticket means only that no mark was placed for that segment under that ticket. It proves nothing about the ground.
- Treating abandoned as safe. A rusted pipe, a cut cable end, or a disconnected meter is judged dead in the field and cut or removed to clear the bore path. In one version the facility is still live and the cut creates the emergency. In another version the facility is a parallel live line that sat next to the truly abandoned one. In a third version the facility is confirmed abandoned later, and the crew still had no authority to remove another owner’s plant. Only the owner confirms abandonment, and confirmed abandonment still leaves a physical object to plan around.
- Confusing presence with status, and status with position. A crew proves a line exists, hears that it is abandoned from a bystander, and also assumes its position from the prints, stacking three different kinds of knowledge, physical, status, and locational, into one false certainty. Each kind comes from a different source: presence from field evidence and verification, status from the owner, position from locating and careful exposure. A claim is only as strong as its own source.
- Missing the private side at the meter. Blue or yellow marks run neatly to a water or gas meter and stop, the crew assumes the located facility ends there, and the trench continues through the house side line that, in that system, is a private facility outside the ticket. Lessons 39 and 40 taught that the meter is a boundary. This lesson generalizes it: every service has a delivery or ownership boundary somewhere, and the segment beyond it needs its own plan.
- Trusting a mark as exact and as deep. A bore runs tight beside a mark, inside the tolerance zone, on the assumption that the facility sits exactly under the paint and safely below the bore. Marks are approximate horizontal evidence. They carry no depth promise. Facilities also shift in apparent position when a locator signal follows a parallel line, when soil or congestion distorts a signal, or when the facility bends between mark points. Verification at the crossing exists for exactly those reasons.
- Ignoring the overhead half. A crew reads the ground carefully and never looks up. A riser at a pole base, a service drop to a building, and a guy anchor in the bore line each announce buried or surface facilities the ground read alone would miss, and overhead conductors themselves govern where equipment booms and bore entry setups may safely be, under rules and clearances that must be verified with the owner and the project plan rather than guessed.
- Entering or opening to check. Curiosity about an unidentified line or cover leads a worker to open a pedestal or cabinet without authorization, lift a manhole cover, or enter a vault or manhole to look. Underground structures can be confined spaces with hazardous atmospheres that give no reliable warning to an unaided person, energized equipment can be present in enclosures that look passive, and pressurized equipment can be present behind covers. Identification is done from the surface, from records, and through the owner and the project process. Entry and opening belong only to people whose role, training, and authorization cover that structure.
- Treating a hazardous sign as a puzzle. A gas odor, a hissing sound near a gas facility, a downed or exposed conductor, sparking, or a collapsed cover is treated as something to approach, photograph closely, or test. The correct response to those signs is distance and reporting: move people to a safe place, keep ignition sources and equipment away as the project emergency plan directs, and contact the owner and emergency services through that plan. This lesson does not teach hazard investigation, gas testing, or electrical testing, and no field curiosity outranks that limit.
- Failing to report the find. A crew exposes an unmarked line, decides it is probably an old communications duct, backfills over it, and tells no one. The next project inherits the same unknown, the owner never corrects its records, and the facility remains unlocatable for the next excavator. A found facility that is reported through the project and to its owner can be added to records and marked next time. A found facility that is buried silently stays unknown by the crew’s choice.
Nearly every failure on this list shares one root. The crew treated a question about an existing utility as if it were already answered, by whichever source was closest at hand: a drawing, a mark, a neighbor’s memory, or the look of a pipe. The definition in this lesson exists to slow that moment down until the right source has actually answered.
What Should Someone Notice in the Field?
Notice existing utilities the way their owners, their locators, and the next crew will need them described: from the surface, within your authorization, by evidence you can name. You are observing, photographing, noting, comparing, and reporting. You are not locating as a locator, not entering or opening structures beyond your authorization, not operating anything, and not certifying any facility as clear, dead, or abandoned.
- Start with service logic. For each building and each lot, ask what services that building must have or must once have had: electric, gas where the area uses it, water, sanitary sewer, communications, and cable, plus storm drainage for the street itself and private lines to detached structures. An occupied building with no visible evidence for one of those services is a question to log, because the service exists even when its surface feature is buried, removed, inside the building, or simply missed.
- Look up before you look down. Note each pole, its risers, its guys and anchors, transformers and streetlights at recognition level, and each service drop to a building. Note every place an overhead line dives underground. That dive point is the start of a buried facility whose direction must be accounted for in the locate comparison.
- Work the ground level features lot by lot. Find and log each hydrant, gas meter set, water meter box, electric meter and service point, pedestal, cabinet, manhole cover, handhole lid, valve box, cleanout, storm inlet, and irrigation or site box you can see, by type where the evidence supports it, by location, and by condition. Log any cover or enclosure you cannot identify as unidentified, with a photograph. Do not guess it into a system to make the log look complete.
- Read condition as a warning, not as a status. Note damage, leaning, cracking, flooding, soggy ground along a service path in dry weather, patched or sunken trench lines, exposed or shallow looking plant, and guards or markers already in place. Describe what you observed and where. Do not convert a rusty, quiet, or disconnected appearance into a claim that a facility is abandoned, de energized, or depressurized.
- Smell, sound, and sight safety limits. If you notice a gas odor, a hissing sound you cannot explain, sparking, smoke, a downed line, or an exposed conductor, do not approach to confirm it, do not touch it, and do not start or move equipment near it. Move to a safe place and report it at once through the project plan and, where the plan or the situation directs it, to the utility and to emergency services. Reading this lesson does not qualify you to test for gas, to test for voltage, or to judge a safe approach distance to an energized facility. Those distances and tests belong to the owner, to qualified workers, and to the governing rules for that facility, verified for the job.
- Walk the marks as a comparison, not as a decoration. For each color under the APWA code, follow the run from end to end. Note where it starts, where it ends, what surface feature it connects to, where it crosses your planned route, and where it fades, is destroyed, or is missing where a feature says a facility should exist. Compare that picture against the positive response information and the ticket information your project provides: each notified owner accounted for, each claimed marked facility actually marked in a color and place that matches its features, each claimed no conflict area actually showing no conflicting surface evidence.
- Hunt the private side on purpose. At each meter and each delivery point, ask where the facility goes next and who owns that next segment. Note lines suggested toward detached garages, barns, shops, yard hydrants, yard lights, and outbuildings, sprinkler or irrigation controls, and septic features where they are visible, as private facility leads. Where your work will cross a private segment, note that the public ticket will commonly not mark it and that the project needs its private locate or verification plan named before digging.
- Notice the records lag clues. A pedestal, meter, riser, or cover that looks newer than the prints, a fresh patch or trench line with no matching record, a facility in the field that the prints do not show, and a facility on the prints with no field evidence are all the same finding in different clothes: the record and the field disagree, and the disagreement goes on the written questions list with a location and an owner who must resolve it.
- Respect structures and spaces. Do not enter a manhole, a vault, or any other underground structure, and do not treat a handhole or an enclosure as safe to open because it is small or familiar. Some underground structures are confined spaces under federal rules, and some of those are permit-required confined spaces, which can require an entry permit, atmosphere testing, an attendant, and rescue provisions that belong to trained and authorized entry teams. Your field job at a cover is to log and photograph it from the surface and report its condition.
- Close the loop in writing the same day. For each segment, record whether the records, the marks, and the field agree, differ, or leave not enough information. List each open item: a missing service, an unidentified cover, a claimed abandoned facility with no owner confirmation on file, a private segment with no locate plan, a mark and feature mismatch, and a hazardous condition reported and to whom. Hand that list through the project process before digging in that segment.
Safety and limits, plainly. Recognizing an existing utility does not qualify you to locate it as a locator, to expose it by digging outside the project plan, to work on or within any stated clearance of an energized or pressurized facility, to enter a confined space, to open or work inside another utility’s energized or pressurized equipment, to operate another utility’s valve, switch, or apparatus, to test a facility for energy, pressure, or gas, or to declare a facility abandoned, dead, or safe to cut or remove. Those acts belong to the facility owner and to workers with the specific training, credentials, equipment, and authorization each act requires under federal rules, state laws, owner rules, and the project plan. Your recognition work supports those people with early, accurate, written field information. It never replaces them.
Key Terms
- Existing utility. Any utility facility already present in, on, or above the work area before your project starts, regardless of owner, service status, and whether any record or mark shows it. Also called an existing facility.
- Facility and facility owner. A facility is the physical plant that carries a service, such as a pipe, cable, conduit, valve, meter, or structure. The facility owner, or utility owner or operator, is the company, agency, or person responsible for that plant. Only the owner can confirm its status.
- 811 and one call. 811 is the free national number that reaches the local notification center. One call is that notification system as a whole. Contacting it creates a ticket that asks member owners to mark or otherwise respond for their facilities in a work area. Notice, validity, and response duties are set by state law and vary by state.
- Locate ticket. The record created by a one call notice for a stated work area and time. Also called an 811 ticket or a one call ticket. A ticket covers the member facilities and the area it describes. It does not cover private facilities by default.
- Locator. A trained person who determines the approximate position of a buried facility using records and locating equipment on behalf of an owner or locating company, and places its temporary marks. Locating is a separate skilled role from reading marks.
- Locate mark. Temporary paint, flag, stake, or whisker placed by a locator to show the approximate horizontal position of a buried facility, colored under the APWA Uniform Color Code. Marks show no depth and are not exact position.
- APWA Uniform Color Code. The American Public Works Association color system for temporary marks: red electric, yellow gas and petroleum, orange communications, blue potable water, purple reclaimed water and irrigation, green sewer and drain, white proposed excavation, pink temporary survey markings.
- Positive response. The system by which facility owners report back through the notification center what they did for a ticket, such as marked, no facilities in the area, or more information needed. Codes and checking duties are set by state law and the notification center.
- Tolerance zone. The corridor around a buried facility, defined by state law, where careful hand or vacuum exposure methods are required and mechanical digging is restricted until the exact location is determined. States define its width and measurement point differently, and no single width is universal.
- As-built. A record drawing meant to show what was actually built and where, as distinct from a design drawing of what was planned. As-builts can lag repairs, replacements, and field changes and must be verified against the field.
- SUE and ASCE 38-22. SUE is subsurface utility engineering, the practice of investigating and depicting existing subsurface utilities with stated reliability. ASCE 38-22 is the American Society of Civil Engineers guideline for that work, with Quality Level D from records, Level C adding surveyed surface features, Level B designating by geophysical methods, and Level A exposing and measuring the facility at a point.
- Abandoned. A facility its owner has formally taken out of service under its own procedures and applicable rules and recorded as abandoned in its own records. Only the owner can confirm this status. Old, quiet, rusted, or disconnected appearance does not prove it.
- Private facility. A facility owned by a property owner or another private party rather than by a member utility, commonly on the customer side of a meter or delivery point. Private facilities are commonly outside the public 811 ticket and need a private locate or other project directed verification where work will cross them.
- Unknown utility. A facility that is present but named by no source the project has checked: not on the prints, not in the records received, not marked, and with no recognized surface feature, or with a feature logged as unidentified. Unknown is a statement about the project’s knowledge, not about the ground being empty.
Check Your Understanding
- State the definition of an existing utility in your own words, naming the three things that do not change whether a facility counts as existing.
- A prints note and a neighbor both say a buried line behind a house is abandoned and dead, but no confirmation from its owner is in the project file. Classify the line under this lesson’s four classes, state how the crew must treat it, and name who can change its classification.
- Blue marks run to a water meter box and stop. The planned handhole sits between the meter and the house. Explain what the meter boundary means for that excavation, what must be confirmed before digging, and why the neat blue marks do not settle the question.
- During a walk you find a pedestal in the bore line that is on no print, with fresh looking orange marks running to it, and a round lid nearby with no wording and no marks. Classify each finding, and state the correct next step for each.
- A lead says the ticket is complete, every owner gave a positive response, and the marks are down, so the corridor is now known and the crew can bore tight along the paint. Identify at least three separate errors in that statement using this lesson.
Answer key
- An existing utility is any utility facility that was already present in, on, or above the work area before the project started. It counts as existing regardless of who owns it, public or private, regardless of whether it is active, abandoned, or of unknown status, and regardless of whether any print, record, or mark shows it. Presence comes first. Ownership, status, and documentation each answer a different later question.
- The line is classified as claimed abandoned, which in working terms means its status is unconfirmed and it must be treated as a live existing utility. The crew expects it, avoids it, crosses it only under the plan with the verification the plan requires for a live facility, and never cuts, removes, or bores through it on the prints note or the neighbor’s word. Only the facility owner can confirm abandonment from its own records and procedures and move the line into the confirmed abandoned class, and even then the physical facility remains in the ground to be planned around as the owner directs.
- In most systems the meter sits at or near the boundary between the utility owned segment and the customer owned, private segment. Marks under the public ticket commonly cover the utility segment to the meter. The segment from the meter to the house may be a private facility outside that ticket, depending on that utility’s rules and local practice, which must be confirmed for the job. Before digging, the project must confirm what the ticket covered, confirm the ownership boundary for that service at that property, and arrange a private locate or other project directed verification for the house side segment the handhole will approach. The blue marks settle only the segment they were placed for. Their neat end at the meter is the boundary announcing itself, not proof that no line continues past it.
- The pedestal with orange marks is a known facility that the records missed: two field sources, the enclosure itself and marks in the communications color, agree that communications plant is present in the bore line, while the prints differ. Log and photograph it by location and condition, record the records against field conflict exactly, and escalate it to the designer and project lead so the prints or the route are corrected and the crossing is verified under the plan before that segment is bored. It is never ignored because the prints omitted it, and it is never treated as abandoned, because marks and an intact enclosure say nothing that proves it out of service. The unworded lid with no marks is an unknown facility access point, or at minimum an unidentified surface feature over an unknown facility. Log and photograph it as unidentified at its address, do not lift or open it, do not guess its system from its shape, and place its identification on the written questions list for resolution through records, the owners, and the project process before work passes over or near it.
- First error, completeness of knowledge: a completed ticket accounts for the member facilities the ticket covered. It says nothing about private facilities beyond meters and delivery points, non member facilities, or facilities no source has named, so unknown and private classes can still occupy the corridor. Second error, what a response proves: positive response confirms that each owner reported an action. The crew must still compare those responses against the marks and the surface features in the field, because a claimed mark that is missing, misplaced, or matched to the wrong feature is a conflict to escalate, not a clearance. Third error, what a mark is: a mark is approximate horizontal evidence with no depth information, so boring tight along the paint can sit inside the tolerance zone the state rules protect and strike a facility that lies to the side of its paint or shallower than the bore assumes. Exact location at a crossing is determined by safe and acceptable means under the plan, including careful exposure where the plan requires it, before mechanical equipment passes. A fourth error, if counted, is treating any of this as the crew’s field decision: conflicts and held segments move through the project process to the designer, the owners, and the project lead.
Lesson Takeaway
An existing utility is everything that was already there before you arrived: every pipe, cable, conduit, and structure, overhead and buried, public and private, active, abandoned, and unknown, owned by someone else and carrying a service someone depends on, whether or not any print, record, or mark shows it. Learn to sort what you meet into four honest classes. Known and active facilities are expected, treated as live, and verified at crossings. Abandoned is a status only the owner can confirm, and a claimed abandoned line is treated as live until that confirmation is on file, and as a physical object in the ground even after it. Private facilities are real and active and commonly outside the public ticket, so they need their own locate plan past every meter and delivery point. Unknown facilities are the standing possibility on every corridor, announced sometimes by a single unidentified lid or a riser nobody recorded, and sometimes by nothing at all. Records lag the field, marks are approximate and prove no depth, and silence from any single source proves nothing about the ground. The work that respects those facts is a system: records checked, surface read on foot, ticket placed and responses verified, field compared against marks and prints, crossings exposed carefully where the plan requires exact positions, and every disagreement written down and escalated before digging. That system is what Lessons 47 through 71 teach piece by piece. This lesson is its foundation: if it was there before you, it is existing, it is not yours, and it must be accounted for before your work proceeds.
Sources and Technical References
- Common Ground Alliance, Best Practices, Version 22.0. Practice 4-7 on visual inspection during locating: a visual inspection is completed during the facility locating process, checks that plant facilities shown on records match those of the site, helps determine if there are facilities placed that are not on record, notes that the time between placing a facility in the field and placing it on permanent records varies by facility owner and location, and lists evidence of a facility not on record as including poles, dips, enclosures, pedestals, valves, meters, risers, and manholes. Used for the records lag the field principle, the visual inspection discipline, and the surface evidence list in this lesson. https://carcga.org/BP_22.0_Web.pdf
- Occupational Safety and Health Administration, 29 CFR 1926.651, Specific excavation requirements, federal regulation text via Cornell Law Institute. Section (b) on underground installations states that the estimated location of utility installations that may reasonably be expected to be encountered shall be determined prior to opening an excavation, that utility companies or owners shall be contacted within established or customary local response times and asked to establish the location before excavation starts, that when the exact location cannot be established the employer proceeds with caution using detection equipment or other acceptable means, that the exact location shall be determined by safe and acceptable means as excavation approaches it, and that installations shall be protected, supported, or removed as necessary while an excavation is open. Used for the federal duties the definition of an existing utility supports. https://www.law.cornell.edu/cfr/text/29/1926.651
- Tennessee 811, Before You Dig. Describes the excavator sequence of waiting for the legal start date and time on the ticket, checking ticket responses through Positive Response, confirming that responses match the marks at the dig site, and digging with care because locating is not an exact science and the actual location can vary from the marks, and notes that utilities are not required to provide depth information with markings and that depth can vary over time even when an as-built reflects depth at installation. Used as one state notification center’s published overview of the ticket, positive response, and confirmation sequence, and for the depth warning. Notice, validity, and tolerance rules are state rules and vary, and no state example in this lesson is stated as a national rule. https://www.tenn811.com/before-you-dig
- The Rios Group, Subsurface Utility Engineering. States that it completes SUE services in accordance with ASCE 38-22, Standard Guideline for Investigating and Documenting Existing Utilities, and summarizes Quality Level D as information from existing utility records, Quality Level C as surveyed data depicting visible above ground features supplemented with Quality Level D information, Quality Level B as two dimensional horizontal information from non destructive surface geophysical methods, also called designating, and Quality Level A as three dimensional horizontal and vertical information from non destructive vacuum excavation to expose utilities at critical points. Used for the SUE concept and the four quality levels at the overview level taught here. The standard itself, the project specifications, and the project engineer govern any quality level claim on a real job. https://www.rios-group.com/services/subsurface-utility-engineering
- Georgia Code, Title 25, Section 25-9-7, Determining whether utility facilities are present, via a published code text. Provides in subsection (h) that facility owners or operators shall maintain recorded information on abandoned utility facilities, maintain them in a locatable manner, or remove them, shall provide information on abandoned facilities when possible in response to a locate request, and that when located or exposed, all abandoned utility facilities and sewer laterals shall be treated as live utility facilities and sewer laterals. Used as one state’s published rule supporting this lesson’s core abandoned discipline: treat an exposed or located claimed abandoned facility as live. Abandoned facility duties are set by each state’s law and each owner’s procedures and must be verified for the state of the job. https://law.onecle.com/georgia/title-25/25-9-7.html
- The Fiber Optic Association, FOA Reference for Fiber Optics, Outside Plant Construction, Underground Construction. Covers underground outside plant construction, manholes and handholes, markers, and records in shared utility corridors. Used for outside plant context and for records and markers as part of construction documentation. https://www.thefoa.org/tech/ref/OSP_Construction/Underground_Construction.html